Routine Make Ready Work. The standard interval for Routine Make Ready work (as defined in 7.6.16) for Ducts and Conduit that is to be performed by Ameritech is 25 business days for the first 10 manholes and an additional 2 business days for each additional 5 manholes. There will be no limits on engineering requests per office. Intervals will be adjusted due to changes in requests or delays caused by CLEC. The clock for the standard interval starts when the ASAC receives billing authorization (Form A-1). The clock stops when the ASAC issues an occupancy permit.