Safety Certification prior to COD. The Concessionaire shall, not later than 1 (one) month prior to the likely COD, notify the Authority and the Independent Expert of the compliance of Safety Requirements and invite them to observe any or all the tests that may be specified by the Independent Expert in accordance with Applicable Laws and Good Industry Practice to determine and certify that the Storage Facility is safe for entering into commercial service, and the costs of such tests shall be shared equally between the Concessionaire and the Authority; provided that in case of failure in any test requiring repetition thereof, the cost of such second or subsequent test shall be borne entirely by the Concessionaire.
Appears in 4 contracts
Samples: Concession Agreement, Concession Agreement, Concession Agreement
Safety Certification prior to COD. The Concessionaire shall, not later than 1 30 (onethirty) month days prior to the likely COD, notify the Authority and the Independent Expert of the compliance of Safety Requirements and invite them to observe any or all the tests that may be specified by the Independent Expert in accordance with Applicable Laws and Good Industry Practice to determine and certify that the Storage Project Facility is safe for entering into commercial service, and the costs of such tests shall be shared equally between the Concessionaire and the Authority; provided that in case of failure in any test requiring repetition thereof, the cost of such second or subsequent test shall be borne entirely by the Concessionaire.
Appears in 1 contract
Samples: Concession Agreement
Safety Certification prior to COD. The Concessionaire shall, not later than 1 30 (onethirty) month days prior to the likely COD, notify the Authority and the Independent Expert of the compliance of Safety Requirements and invite them to observe any or all the tests that may be specified by the Independent Expert in accordance with Applicable Laws and Good Industry Practice to determine and certify that the Storage Facility Project is safe for entering into commercial service, and the costs of such tests shall be shared equally between the Concessionaire and the Authority; provided that in case of failure in any test requiring repetition thereof, the cost of such second or subsequent test shall be borne entirely by the Concessionaire.
Appears in 1 contract
Samples: Model Concession Agreement