SCHEDULE OF THE WORK. 6.2.1 Before submitting the first application for payment, the Construction Manager shall submit to the Owner and, if directed, the Design Professional a Schedule of the Work showing the dates on which the Construction Manager plans to commence and complete various parts of the Work, including dates on which information and approvals, self-performed work, selection of allowance items, and other known Owner services, tasks and work are required from the Owner. The Construction Manager shall comply with the approved Schedule of the Work, unless directed by the Owner to do otherwise or the Construction Manager is otherwise entitled to an adjustment in the Contract Time. The Construction Manager shall update the Schedule of the Work on a monthly basis or at appropriate intervals as required by the conditions of the Work and the Project. 6.2.2 The Owner may determine the sequence in which the Work shall be performed, provided it does not unreasonably interfere with the approved project schedule. The Owner may require the Construction Manager to make reasonable changes in the sequence at any time during the performance of the Work in order to facilitate the performance of work by the Owner or Others. To the extent such changes directly increase the Construction Manager's costs or time, the GMP or the dates of Substantial or Final Completion shall be equitably adjusted.
Appears in 4 contracts
Samples: Construction Manager Agreement, Construction Manager Agreement, Construction Manager Agreement
SCHEDULE OF THE WORK. 6.2.1 Before submitting the first application for payment, the Construction Manager shall submit to the Owner and, if directed, the Design Professional a Schedule of the Work showing the dates on which the Construction Manager plans to commence and complete various parts of the Work, including dates on which information and approvals, self-performed work, selection of allowance items, and other known Owner services, tasks and work are required from the Owner. The Construction Manager shall comply with the approved Schedule of the Work, unless directed by the Owner to do otherwise or the Construction Manager is otherwise entitled to an adjustment in the Contract Time. The Construction Manager shall update the Schedule of the Work on a monthly basis or at appropriate intervals as required by the conditions of the Work and the Project.
6.2.2 The Owner may determine the sequence in which the Work shall be performed, provided it does not unreasonably interfere with the approved project schedule. The Owner may require the Construction Manager to make reasonable changes in the sequence at any time during the performance of the Work in order to facilitate the performance of work by the Owner or Others. To the extent such changes directly increase the Construction Manager's costs or time, the GMP or the dates Dates of Substantial or Final Completion shall be equitably adjusted.
Appears in 2 contracts
Samples: Construction Manager Agreement, Construction Manager Agreement