Schedule Requirements. The Contractor shall submit an electronic and a paper copy of the initial Work Progress Schedule reflecting accurate and reliable representations of the planned progress of the Work, the Work to date if any, and of the Contractor’s actual plans for its completion. The Contractor shall organize and provide adequate detail so the Work Progress Schedule is capable of measuring and forecasting the effect of delaying events on completed and uncompleted activities.
Appears in 40 contracts
Samples: Agreement, Agreement, assets.system.tamus.edu
Schedule Requirements. The Contractor shall submit an electronic and a paper copy of the initial Work Progress Schedule reflecting accurate and reliable representations of the planned progress of the Work, the Work to date if any, and of the Contractor’s actual plans for its completion. The Contractor shall organize and provide adequate detail so the Work Progress Schedule schedule is capable of measuring and forecasting the effect of delaying events on completed and uncompleted activities.
Appears in 33 contracts
Samples: Agreement for Design Build Services, contracts.hhs.texas.gov, Agreement
Schedule Requirements. The Contractor shall submit an electronic and a paper copy of the initial Work Progress Schedule reflecting accurate and reliable representations of the planned progress of the Work, the Work to date if any, and of the Contractor’s actual plans for its completion. The Contractor shall organize and provide adequate detail detail, so the Work Progress Schedule schedule is capable of measuring and forecasting the effect of delaying events on completed and uncompleted activities.
Appears in 21 contracts
Samples: Contract for Construction, Contract for Construction, Contract for Construction
Schedule Requirements. The Contractor shall submit an electronic and a paper copy of the initial Work Progress Schedule reflecting accurate and reliable representations of the planned progress of the Work, the Work to date if any, and of the Contractor’s actual plans for its completion. The Contractor shall organize and provide adequate detail so the Work Progress Schedule schedule is capable of measuring and forecasting the effect of delaying events on completed and uncompleted activities.
Appears in 3 contracts
Samples: assets.system.tamus.edu, assets.system.tamus.edu, assets.system.tamus.edu
Schedule Requirements. The Contractor shall submit an electronic and a paper copy of the initial Work Progress Schedule reflecting accurate and reliable representations of the planned progress of the Work, the Work to date if any, and of the Contractor’s actual plans for its completioncompletion of all Work. The Contractor shall organize and provide adequate detail so the Work Progress Schedule schedule is capable of measuring and forecasting the effect of delaying events on completed and uncompleted activities.
Appears in 2 contracts
Samples: Construction Manager at Risk Agreement, Professional Services Agreement
Schedule Requirements. The Contractor shall submit an electronic and a paper copy of the initial Work Progress Schedule reflecting accurate and reliable representations of the planned progress of the Work, the Work to date if any, and of the Contractor’s actual plans for its completion. The Contractor shall organize and provide adequate detail so the Work Progress Schedule is capable of measuring and forecasting the effect of delaying events on completed and uncompleted activities.
Appears in 1 contract
Schedule Requirements. The Contractor shall submit an electronic and a paper copy of the initial Work Progress Schedule reflecting accurate and reliable representations of the planned progress of the Work, the Work to date if any, and of the Contractor’s actual plans for its completion. The Contractor shall organize and provide adequate detail so the Work Progress Schedule schedule is capable of measuring and forecasting the effect of delaying events on completed and uncompleted activitiesuncompletedactivities.
Appears in 1 contract