Submittal Activities Clause Samples
The Submittal Activities clause outlines the requirements and procedures for submitting documents, samples, or other materials for review and approval during a project. Typically, it specifies what types of submittals are required—such as shop drawings, product data, or material samples—along with deadlines, formats, and the process for addressing comments or revisions. This clause ensures that all necessary information is provided in a timely and organized manner, facilitating quality control and coordination between parties involved in the project.
Submittal Activities. The Owner will review and approve, reject or take other appropriate action on submittals such as shop drawings, product data, samples and proposed equal materials or equipment and requested substitutions in a timely manner so as to not impact the construction schedule, and will not approve any submittals unless such submittals conform with (i) the Project design concept; (ii) this Contract; and (iii) the Owner’s budgeted Total Project Construction Cost. The Owner’s review of submittals shall not constitute final acceptance of materials or equipment furnished or installed if such materials or equipment should be defective or not as represented by approved submittals or as otherwise required by the Construction Documents. The DB remains responsible for details and accuracy, for confirming and correlating all quantities and dimensions, for selecting fabrication processes, for techniques of assembly, and for performance of the Work.
Submittal Activities. Submittal activities shall be included in the Project Schedules in a manner consistent with the level of detail shown below: ACTIVITY ABBREVIATION IN ACTIVITY DESCRIPTION Prepare and Submit P/S Review and Approve R/A Revise and Re-submit R/R Fabricate and Deliver (Material or Equipment) F/D or FAB or DEL The Contractor shall define additional submittal activities not shown in the above table when necessary to accurately represent a required submittal. Each re-submittal and the corresponding Authority review period shall be represented by separate activities in the Project Schedules.
Submittal Activities. Submittal activities shall be included in the Project Schedules in a manner consistent with the level of detail shown below: Prepare and Submit P/S Review and Approve R/A Revise and Re-submit R/R Fabricate and Deliver (Material or Equipment) F/D or FAB or DEL