Scheduled Control Subsystem. Master Project Schedule - Within (10) ten days of executing a Project Agreement, Contractor shall submit, and the Construction Team shall approve, a master project schedule covering the planning and design approvals, construction and Owner occupancy of the Project. The master project schedule shall be produced and updated either weekly or monthly, as directed by Owner, throughout the Project.
Appears in 4 contracts
Samples: Master Agreement for Construction Management Services, Master Agreement for Construction Management Services, Master Agreement
Scheduled Control Subsystem. Master Project Schedule - Within thirty (1030) ten days of executing a Project Agreement, Contractor shall submit, and the Construction Team shall approve, a master project schedule covering the planning and design approvals, construction and Owner occupancy of the Project. The master project schedule shall be produced and updated either weekly or monthly, as directed by Owner, monthly throughout the Project.
Appears in 3 contracts
Samples: Master Agreement for Construction Management Services, Master Agreement for Construction Management Services, Master Agreement for Construction Management Services