Scheduled Plant Outages. The Seller shall, not less than one (1) month prior to the Commercial Operation Date and on an annual basis for the remainder of the Term, at least one (1) month prior to the anniversary of the Commercial Operation Date provide to the Operating Committee its proposals for Scheduled Plant Outages, including any planned interruption or reduction of the Power Plant’s Contracted Capacity for the remainder of the Contract Year and the forthcoming Contract Year, as appropriate. Such schedule shall include: the number of expected Scheduled Plant Outages and the extent of expected reductions in the Contracted Capacity of the Power Plant as a result of such Scheduled Plant Outages; and the estimated dates and duration of each Scheduled Plant Outage. The Operating Committee shall, upon receipt of the proposals contemplated in clause 12.8.1, meet and coordinate the timing of Scheduled Plant Outages for the forthcoming Contract Year, at least as close to one (1) month prior to the commencement of that Contract Year as possible. If there is a requirement to change the dates of any Scheduled Plant Outage, the Seller shall provide NamPower with written notice at least twenty-eight (28) days in advance of the relevant Scheduled Plant Outage. NamPower may approve such a request for a change of date within five (5) days of such request. Such an approval shall not be unreasonably withheld or delayed. Subject to having complied with the foregoing provisions of this Clause 12.8 (Scheduled Plant Outages), the Seller shall be entitled to remove any Unit and/or the Power Plant from service at the agreed date and time for the Scheduled Plant Outage. The Seller shall be responsible for all costs incurred by it in connection with or arising from any scheduled maintenance carried out by it or on its behalf on the Power Plant. NamPower shall not be entitled to any payment and/or indemnification and/or reimbursement from the Seller in connection with any Scheduled Plant Outages.
Appears in 4 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Scheduled Plant Outages. 12.7.1 The Seller shall, not less than one (1) month Month prior to the Commercial Operation Date and on an annual basis for the remainder of the Term, at least one (1) month Month prior to the anniversary of the Commercial Operation Date provide to the Operating Committee ZESCO its proposals for Scheduled Plant Outages, including any planned interruption or reduction of the Power Plant’s Contracted Capacity capacity for the remainder of the Contract Year and or the forthcoming Contract Year, as appropriate. Such schedule shall include: :
12.7.1.1. the number of expected Scheduled Plant Outages and the extent of expected reductions in the Contracted Capacity capacity of the Power Plant as a result of such Scheduled Plant Outages; and and
12.7.1.2. the estimated dates and duration of each Scheduled Plant Outage. .
12.7.2 The Operating Committee shall, upon receipt of the proposals contemplated in clause 12.8.1, Parties shall meet and coordinate the timing of Scheduled Plant Outages for the forthcoming Contract Year, at least as close to one (1) month Month prior to the commencement of that Contract Year as possible. Year.
12.7.3 If there is a requirement to change the dates of any Scheduled Plant Outage, the Seller shall provide NamPower ZESCO with written notice at least twenty-eight (28) days in advance of the relevant Scheduled Plant Outage. NamPower ZESCO may approve such a request for a change of date within five (5) days of such request. Such an approval shall not be unreasonably withheld or delayed. .
12.7.4 Subject to having complied with the foregoing provisions of this Clause 12.8 12.7 (Scheduled Plant Outages), the Seller shall be entitled to remove any Unit and/or the Power Plant from service at the agreed date and time for the Scheduled Plant Outage. .
12.7.5 The Seller shall be responsible for all costs incurred by it in connection with or arising from any scheduled maintenance carried out by it or on its behalf on the Power Plant. NamPower ZESCO shall not be entitled to any payment and/or indemnification and/or reimbursement from the Seller in connection with any Scheduled Plant Outages.
Appears in 1 contract
Samples: Power Purchase Agreement