Short Interval Schedules. 19 The Entity shall prepare a Short Interval Schedule (SIS) to be used throughout the duration of Work. The SIS 20 shall include all current activities and projected activities for the succeeding two (2) weeks. The SIS shall 22 Schedule. The SIS shall be submitted to the District’s Representative prior to the weekly construction
Appears in 3 contracts
Samples: Facilities Lease Agreement, Facilities Lease Agreement, Facilities Lease Agreement
Short Interval Schedules. 19 20 The Entity shall prepare a Short Interval Schedule (SIS) to be used throughout the duration of Work. The SIS 20 21 shall include all current activities and projected activities for the succeeding two (2) weeks. The SIS shall include 22 Schedule. The SIS actual start/finish dates for the preceding one (1) week and it shall be submitted tied to the District’s Representative prior to the weekly constructionupdated Construction Schedule.
Appears in 1 contract
Samples: Facilities Lease Agreement
Short Interval Schedules. 19 28 The Entity shall prepare a Short Interval Schedule (SIS) to be used throughout the duration of Work. The SIS 20 shall include all current activities and projected activities for the succeeding two (2) weeks. The SIS shall 22 Schedule. The SIS shall be submitted to the District’s Representative prior to the weekly construction.
Appears in 1 contract
Samples: Facilities Lease Agreement
Short Interval Schedules. 19 22 The Entity shall prepare a Short Interval Schedule (SIS) to be used throughout the duration of Work. The SIS 20 shall include all current activities and projected activities for the succeeding two (2) weeks. The SIS shall 22 Schedule. The SIS shall be submitted to the District’s Representative prior to the weekly constructionSIS
Appears in 1 contract
Samples: Facilities Lease Agreement
Short Interval Schedules. 19 20 The Entity shall prepare a Short Interval Schedule (SIS) to be used throughout the duration of Work. The SIS 20 shall include all current activities and projected activities for the succeeding two (2) weeks. The SIS shall 22 Schedule. The SIS shall be submitted to the District’s Representative prior to the weekly constructionSIS
Appears in 1 contract
Samples: Facilities Lease Agreement