Short Interval Schedules. CONTRACTOR shall prepare a Short Interval Schedule (SIS) to be used throughout the duration of WORK. The SIS shall include all current activities and projected activities for the succeeding two (2) weeks. The SIS shall include actual start/finish dates for the preceding one (1) week.
Appears in 3 contracts
Samples: Construction Services Contract, Construction Services Contract, Construction Services Contract
Short Interval Schedules. CONTRACTOR shall prepare a Short Interval Schedule (SIS) to be used throughout the duration of WORK. The SIS shall include all current activities and projected activities for the succeeding two (2) weeks. The SIS shall include actual start/finish dates for the preceding one (1) week. Eight copies of the SIS shall be submitted to ENGINEER at the weekly construction meeting. CONTRACTOR shall participate in short interval scheduling coordination during the weekly construction meetings.
Appears in 1 contract
Samples: Construction Services Contract