Shortened Time for Partial Default in the Case of Critical Path Delay. In the case of critical path delay, the District may correct any of the deficiencies described in Article
AutoNDA by SimpleDocs
Shortened Time for Partial Default in the Case of Critical Path Delay. In the case of critical path delay, the Owner may correct any of the deficiencies described in Article 2.2 without prejudice to other remedies providing service of written notice of Critical Path Delay to the Contractor with a specific description of the critical path delay items noting the line item or area of Work that is on the Critical Path and prescribe the length of shortened time to Cure, if any.