Critical Path. 1.9.1. The term “critical path” as used in the Contract Documents shall mean the construction activity schedule that establishes the minimum overall Project duration.
Critical Path. The sequence of activities, events, and dependencies that determine the longest overall duration and the shortest time possible, to complete the Project. Any delay of an activity on the Critical Path directly impacts the planned Project completion date (i.e., there is no float on the Critical Path).
Critical Path. Time extensions shall depend upon the extent to which the Work on the critical path of the Construction Progress Schedule is affected, if applicable.
7.8.3.1 A Change Order granting a time extension may provide that the Contract Times shall be extended for only those specific elements so interfered with, disrupted, hindered, or delayed and related remobilization and that remaining Milestone dates shall not be altered and may further provide for adjustment of Liquidated Damages.
Critical Path. Time extensions shall depend upon the extent to which the Work on the critical path of the Construction Progress Schedule is affected, if applicable. Version Control Document
Critical Path. The critical path permits for various QF technologies are as follows:
Critical Path a sequence of Work activities, which establish the total duration of time for the construction of the Project, and if any activity along the critical path were delayed or extended, would change the construction duration established in the approved Baseline Schedule.
Critical Path a. Unless otherwise specified in the Contract, the project Schedule shall include a Critical Path Method (CPM) diagram schedule showing the sequence of activities, the interdependence of each activity and identifies the Critical Path.
b. The CPM diagram schedule shall be in Calendar Days and indicate duration, earliest and latest start and finish dates for all activities, and total Float Time for all activities except critical activities. The CPM diagram shall be presented in a time scaled graphical format for the Project as a whole.
Critical Path. An identification the key milestones in the due diligence and permitting process, including any milestones relating to obligations of the municipality (e.g., to rezone the property). In this stage, the municipality is agreeing to work with the developer to explore the idea of the project – to determine what challenges may exist and how to overcome them and what benefits the project may offer the community.
Critical Path. The planned sequence of activities for a Project with a logical relationship for the elements of the Work for such Project that control the time of completion of the Work for such Project, as depicted on the Approved Construction Schedule for such Project. The Critical Path for a Project with respect to a specific Substantial Completion is the path with no Float or the least amount of Float.
Critical Path. The Developer will be responsible for initiating and diligently pursuing the Development Approval applications in accordance with the critical path schedule attached hereto as composite Exhibit D (the “Critical Path”), which Critical Path shall serve as the Developer's time frame for performance with respect to obtaining the Development Approvals and constructing the Project. Notwithstanding any other provisions of the Agreement, the dates set forth in the Critical Path shall be extended on a day for day basis for delays occasioned by the following events: acts of God; pandemic or other health related occurrence; terrorism; once construction begins - inclement weather which is in excess of those days normally forecasted by the National Weather Service for the given month in South Florida, which materially and adversely interfere with construction; unforeseen physical conditions on the site; withholding of governmental approvals or restrictions not due to the fault, delay or negligence of the Developer or the imposition of restrictions by a governmental body that materially changes the design or scope of the Project to an extent that renders the Project so difficult to construct as to make it commercially unreasonable; appeals of governmental approvals or lawsuits by any third party (whether individual or otherwise) instituted to prevent the issuance of any approvals or permits, or otherwise stop construction of the development after commencement; or similar events not reasonably foreseeable and beyond the reasonable control of Developer (collectively, “Force Majeure”). By the tenth (10th) Business Day of each month, Developer shall deliver or cause to be delivered to the CRA a list of the days during each proceeding month as to which Developer believes the Force Majeure provisions apply and the reasons therefore, together with supporting documentation as to the extension on the Critical Path. The CRA shall, within ten (10) Business Days after receipt of any such list and supporting documentation, provide notice to Developer as to whether CRA disputes that any of the days set forth on that list would give rise to an extension of time for Developer’s performance based on Force Majeure. In the event the CRA agrees with the extension requested by Developer, or any portion of the requested extension, then the Critical Path schedule shall be so extended hereunder. The CRA shall cooperate with the Developer in processing all necessary Development Approvals to be ...