We use cookies on our site to analyze traffic, enhance your experience, and provide you with tailored content.

For more information visit our privacy policy.

Critical Path Sample Clauses

Critical Path. The sequence of activities, events, and dependencies that determine the longest overall duration and the shortest time possible, to complete the Project. Any delay of an activity on the Critical Path directly impacts the planned Project completion date (i.e., there is no float on the Critical Path).
Critical Path. 1.9.1. The term “critical path” as used in the Contract Documents shall mean the construction activity schedule that establishes the minimum overall Project duration.
Critical PathTime extensions shall depend upon the extent to which the Work on the critical path of the Construction Progress Schedule is affected, if applicable. 7.8.3.1 A Change Order granting a time extension may provide that the Contract Times shall be extended for only those specific elements so interfered with, disrupted, hindered, or delayed and related remobilization and that remaining Milestone dates shall not be altered and may further provide for adjustment of Liquidated Damages.
Critical PathTime extensions shall depend upon the extent to which the Work on the critical path of the Construction Progress Schedule is affected, if applicable. Version Control Document
Critical Path. The critical path permits for various QF technologies are as follows:
Critical Path a sequence of Work activities, which establish the total duration of time for the construction of the Project, and if any activity along the critical path were delayed or extended, would change the construction duration established in the approved Baseline Schedule.
Critical Path. 2.6.1 Simultaneously with the funding of the Construction Escrow Account, Tenant will provide aPhase I/II Critical Path” to the City which will set forth the projected start date of each improvement in the Phase I/II Land Based Project and the Riverboat/Floating Facility, the manner in which each improvement in the Phase I/II Land Based Project and the Riverboat/Floating Facility will be constructed and a projected completion date for each improvement in the Phase I/II Land Based Project and the Riverboat/Floating Facility.
Critical Path. The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
Critical Path. The longest continuous sequence of activities through the Project schedule that establishes the minimum overall Project duration to Substantial Completion. Critical Path Method Schedule. A network based method to represent the Contractor’s plan for constructing the Project. The Critical Path Method Schedule consists of two primary components 1) Activities that represent the entire Project scope of Work and 2) logic relationships that connect the activities to one another to determine the sequence of Work.
Critical Path. Sequence of activities that represents the longest path through a project, which determines the shortest possible duration.