PARTIAL DEFAULT. In case the Commissioner shall declare the Contractor in default as to a part of the Work only, the Contractor shall discontinue such part, shall continue performing the remainder of the Work in strict conformity with the terms of this Contract, and shall in no way hinder or interfere with any Other Contractor(s) or persons whom the Commissioner may engage to complete the Work as to which the Contractor was declared in default.
PARTIAL DEFAULT. In the event of a Breach, the Institution may declare a Partial Default. In which case, the Institution shall provide the Contractor written notice of: (1) the date which Contractor shall terminate providing the service associated with the Breach; and (2) the date the Institution will begin to provide the service associated with the Breach. Notwithstanding the foregoing, the Institution may revise the time periods contained in the notice written to the Contractor.
(1) amounts which would be paid the Contractor to provide the defaulted service; or (2) the cost to the Institution of providing the defaulted service, whether said service is provided by the Institution or a third party. To determine the amount the Contractor is being paid for any particular service, the Institution shall be entitled to receive within five (5) days of any request, pertinent material from Contractor. The Institution shall make the final and binding determination of the amount. Upon Partial Default, the Contractor shall have no right to recover from the Institution any actual, general, special, incidental, consequential, or any other damages whatsoever of any description or amount. Contractor agrees to cooperate fully with the Institution in the event a Partial Default is declared.
PARTIAL DEFAULT. 70.1. In case the Commissioner shall declare the Contractor in default as to a part of the Work only, the Contractor shall discontinue such part, shall continue performing the remainder of the Work in strict conformity with the terms of this Contract, and shall in no way hinder or interfere with any Other Contractor(s) or persons whom the Commissioner may engage to complete the Work as to which the Contractor was declared in default.
70.2. The provisions of this Chapter relating to declaring the Contractor in default as to the entire Work shall be equally applicable to a declaration of partial default, except that the Commissioner shall be entitled to utilize for completion of the part of the Work as to which the Contractor was declared in default only such plant, materials, equipment, tools and supplies as had been previously used by the Contractor on such part.
PARTIAL DEFAULT. In the event the Owner declares the CMR in default in accordance with the provisions of the Contract Documents with respect to a portion of the Work, the CMR shall discontinue such portion of the Work declared in default, shall continue performing the remainder of the Work in strict conformity with the terms of the Contract and shall not hinder or interfere with any other Contractor or persons whom the Owner may engage to complete the Work for which the CMR was declared in default. The expense of such completion shall be paid by the CMR and its Sureties as provided in the Contract Documents.
PARTIAL DEFAULT. In the event of a Breach, the University may declare a Partial Default. In which case, the University shall provide the Contractor written notice of: (1) the date which Contractor shall terminate providing the service associated with the Breach; and (2) the date the University will begin to provide the service associated with the Breach. Notwithstanding the foregoing, the University may revise the time periods contained in the notice written to the Contractor.
(1) amounts which would be paid the Contractor to provide the defaulted service; or (2) the cost to the University of providing the defaulted service, whether said service is provided by the University or a third party. To determine the amount the Contractor is being paid for any particular service, the University shall be entitled to receive within five (5) days any requested material from Contractor. The University shall make the final and binding determination of the amount. The University may assess Liquidated Damages against the Contractor for any failure to perform. Upon Partial Default, the Contractor shall have no right to recover from the University any actual, general, special, incidental, consequential, or any other damages whatsoever of any description or amount. Contractor agrees to cooperate fully with the University in the event a Partial Default is declared.
PARTIAL DEFAULT. In the event the Owner declares the Contractor in default in accordance with the provisions of the Contract Documents with respect to a portion of the Work, the Contractor shall discontinue such portion of the Work declared in default, shall continue performing the remainder of the Work in strict conformity with the terms of the Contract and shall not hinder or interfere with any other contractor or persons whom the Owner may engage to complete the Work for which the Contractor was declared in default. The expense of such completion shall be paid by the Contractor and its Sureties as provided in the Contract Documents.
PARTIAL DEFAULT. In the event of a Breach, the Institution may declare a Partial Default. In which case, the Institution shall provide the Contractor written notice of: (1) the date which Contractor shall terminate providing the service associated with the Breach; and (2) the date the Institution will begin to provide the service associated with the Breach. Notwithstanding the foregoing, the Institution may revise the time periods contained in the notice written to the Contractor.
(1) amounts which would be paid the Contractor to provide the defaulted service; or (2) the cost to the Institution of providing the defaulted service, whether said service is provided by the Institution or a third party. To determine the amount, the Contractor is being paid for any particular service, the Institution shall be entitled to receive within five (5) days of any request, pertinent material from Contractor. The Institution shall make the final and binding determination of the amount. The Institution may assess Liquidated Damages against the Contractor for any failure to perform. Upon Partial Default, the Contractor shall have no right to recover from the Institution any actual, general, special, incidental, consequential, or any other damages whatsoever of any description or amount. Contractor agrees to cooperate fully with the Institution in the event a Partial Default is declared.
PARTIAL DEFAULT. In case the City shall declare Contractor in default as to a part of the Work only, Contractor shall discontinue such part, shall continue performing the remainder of the Work in strict conformity with the terms of the Contract, and shall in no way hinder or interfere with any other contractors or persons whom the City may engage to complete the Work as to which Contractor was declared in default. The provisions of the clauses herein relating to declaring Contractor in default as to the entire Work shall be equally applicable to a declaration of partial default, except that the City shall be entitled to utilize for completion of the Work as to which Contractor was declared in default only such plant, materials, equipment, tools and supplies as had been previously used by Contractor on such part.
PARTIAL DEFAULT. District Right to Take Over Work (Two (2) day notice to Cure and Correct). If the Contractor Defaults or neglects to carry out the Work in accordance with the Contract Documents, the District may provide a two (2) business day written notice to cure (a shorter period of time in the case of Emergency or a critical path delay) Contractor’s Partial Default in a specific segregated area of work. The District’s right to issue a Partial Default of the Contractor’s Work and take over that segregated area of Work includes, but is not limited to:
a. Failure to supply adequate workers on the entire Project or any part thereof;
b. Failure to supply a sufficient quantity of materials;
c. Failure to perform any provision of this Contract;
d. Failure to comply with safety requirements, or due to Contractor is creation of an unsafe condition;
e. Cases of bona fide emergency;
f. Failure to order materials in a timely manner;
g. Failure to prepare deferred-approval items or Shop Drawings in a timely manner;
h. Failure to comply with Contractor’s Baseline or Update Schedule, meet critical Milestones which would result in a Delay to the Critical Path, or Delay the Contract Time;
i. Failure to comply with the Subcontractor selection and award requirements under Education Code section 17406(a)(4);
j. Failure to meet the requirements of the American’s with Disabilities Act;
k. Failure to complete Punch List work; or
l. Failure to proceed on an Immediate Change Directive.
PARTIAL DEFAULT. In the event of a breach, the SCHOOL may declare a partial default.