Site Discipline. Contractor shall employ, and require all Subcontractors and Vendors to employ, only skilled workers properly qualified by experience and ability to perform the tasks assigned to them. Contractor shall at all times be responsible for strict discipline and good order among its employees, craft labor, agents and representatives as well as the employees, craft labor, agents and representatives of its Subcontractors and Vendors while performing Work and all other persons performing any Work. When requested by Owner, Contractor shall remove and shall not re-assign to the Work any person who, in Owner’s reasonable opinion, is disorderly, insubordinate, unsafe, unskilled, incompetent or otherwise unfit for tasks assigned to them. 7.7.1 At all times during performance of the Work on the Project, including during any partial use or occupancy by Owner or others, Contractor shall, and shall cause all Subcontractors and Vendors to, abide by each and all of the following requirements: 7.7.1.1 Access to the Project Work area by construction personnel shall be the most inconspicuous route available, in order that the general public and the Owner’s personnel are not inconvenienced. Access shall be arranged with Owner prior to commencement of Work. Access to restricted and/or limited access areas required by Work shall be coordinated with Owner. 7.7.1.2 Owner’s toilet facilities and the Project’s permanent toilet facilities are not to be used by construction personnel. 7.7.1.3 During the FF&E and finish phase of construction, construction personnel are not permitted to eat and smoke where materials are in place nor use tables and chairs or other furniture that are part of the Project. During this phase of the Project, Owner will designate appropriate places for eating. 7.7.1.4 Quiet and courtesy with respect to Owner’s employees and guests is mandatory. 7.7.1.5 Use all best efforts to ensure that Contractor’s and all Subcontractors’ activities do not interfere with any Project and Site systems (i.e., electric, elevator, plumbing, HVAC, etc.) necessary to maintain ongoing operations of the Project and Site. 7.7.1.6 Power outages, mechanical shutdown and so forth shall be carefully coordinated with Owner. Contractor will provide Owner with two (2) full business days, advance notice of any planned shutdowns of any basic Project or Site systems, and will obtain Owner’s written approval prior to commencing any such shutdown. 7.7.1.7 All life safety systems requiring shut-down or tie-ins, in accordance with the above clause 7.7.1.6, shall be coordinated with Owner and shall be performed at such a time to minimize any effect of the safety, health and welfare of the building’s occupants. At the conclusion of each work-day, all operable life safety systems shall be energized and operative. 7.7.1.8 Contractor shall be responsible to Owner for acts and omissions of Contractor’s employees and agents, Subcontractors and Vendors and their respective agents and employees, and other persons performing portions of the Work under a contract or arrangement with or under the direction of Contractor or with or under the direction of any Subcontractor or Vendor. Except to the extent expressly provided otherwise in this Agreement, Contractor shall not be relieved of its obligation to perform the Work in accordance with the Contract Documents either by activities or duties of Owner or Architect, or, by any request, approval or consent of Owner or Architect, or by tests, inspections or approvals required or performed by persons other than Contractor. Contractor shall require and ensure that each Subcontractor and Vendor complies with all applicable requirements set forth in the Contract Documents for Contractor. Except to the extent the Contract Documents expressly provide otherwise, if any dispute arises between Owner, on the one hand, and Contractor, on the other hand, unless Owner directs otherwise, Contractor shall proceed with the performance of its obligations under the Contract with reservation of all rights and remedies it may have under and subject to the terms of the Contract Documents.
Appears in 2 contracts
Samples: Guaranteed Maximum Price Construction Services Agreement (Pinnacle Entertainment Inc), Guaranteed Maximum Price Construction Services Agreement (Pinnacle Entertainment Inc)
Site Discipline. Contractor shall employ, and require all Subcontractors and Vendors to employ, only skilled workers properly qualified by experience and ability to perform the tasks assigned to them. Contractor shall at all times be responsible for strict discipline and good order among its employees, craft labor, agents and representatives as well as the employees, craft labor, agents and representatives of its Subcontractors and Vendors while performing Work and all other persons performing any Work. When requested by Owner, Contractor shall remove and shall not re-assign to the Work any person who, in Owner’s 's reasonable opinion, is disorderly, insubordinate, unsafe, unskilled, incompetent or otherwise unfit for tasks assigned to them.
7.7.1 At all times during performance of the Work on the Project, including during any partial use or occupancy by Owner or others, Contractor shall, and shall cause all Subcontractors and Vendors to, abide by each and all of the following requirements:
7.7.1.1 Access to the Project Work area by construction personnel shall be the most inconspicuous route available, in order that the general public and the Owner’s 's personnel are not inconvenienced. Access shall be arranged with Owner prior to commencement of Work. Access to restricted and/or limited access areas required by Work shall be coordinated with Owner.
7.7.1.2 Owner’s 's toilet facilities and the Project’s 's permanent toilet facilities are not to be used by construction personnel.
7.7.1.3 During the FF&E and finish phase of construction, construction personnel are not permitted to eat and smoke where materials are in place nor use tables and chairs or other furniture that are part of the Project. During this phase of the Project, Owner will designate appropriate places for eating.
7.7.1.4 Quiet and courtesy with respect to Owner’s 's employees and guests is mandatory.
7.7.1.5 Use all best efforts to ensure insure that Contractor’s 's and all Subcontractors’ ' activities do not interfere with any Project and Site systems (i.e., electric, elevator, plumbing, HVAC, etc.) necessary to maintain ongoing operations of the Project and Site.
7.7.1.6 Power outages, mechanical shutdown and so forth shall be carefully coordinated with Owner. Contractor will provide Owner with two (2) full business days, advance notice of any planned shutdowns of any basic Project or Site systems, and will obtain Owner’s 's written approval prior to commencing any such shutdown.
7.7.1.7 All life safety systems requiring shut-down or tie-ins, in accordance with the above clause 7.7.1.6, shall be coordinated with Owner and shall be performed at such a time to minimize any effect of the safety, health and welfare of the building’s 's occupants. At the conclusion of each work-day, all operable life safety systems shall be energized and operative.
7.7.1.8 Contractor shall be responsible to Owner for acts and omissions of Contractor’s 's employees and agents, Subcontractors and Vendors and their respective agents and employees, and other persons performing portions of the Work under a contract or arrangement with or under the direction of Contractor or with or under the direction of any Subcontractor or Vendor. Except to the extent expressly provided otherwise in this Agreement, Contractor shall not be relieved of its obligation to perform the Work in accordance with the Contract Documents either by activities or duties of Owner or Architect, or, by any request, approval or consent of Owner or Architect, or by tests, inspections or approvals required or performed by persons other than Contractor. Contractor shall require and ensure that each Subcontractor and Vendor complies with all applicable requirements set forth in the Contract Documents for Contractor. Except to the extent the Contract Documents expressly provide otherwise, if any dispute arises between Owner, on the one hand, and Contractor, on the other hand, unless Owner directs otherwise, Contractor shall proceed with the performance of its obligations under the Contract with reservation of all rights and remedies it may have under and subject to the terms of the Contract Documents.
Appears in 1 contract
Samples: Guaranteed Maximum Price Construction Services Agreement (Wynn Resorts LTD)
Site Discipline. Contractor shall employ, and require all Subcontractors and Vendors to employ, only skilled workers properly qualified by experience and ability to perform the tasks assigned to them, who are properly credentialed with visas and/or work permits allowing them to be legally employed at the Site. Contractor shall at all times be responsible for strict discipline and good order among its employees, craft labor, agents and representatives as well as the employees, craft labor, agents and representatives of its Subcontractors and Vendors while performing Work and all other persons performing any Work. When requested by Owner, Contractor shall remove and shall not re-assign to the Work any person who, in Owner’s reasonable opinion, is disorderly, insubordinate, unsafe, unskilled, incompetent or otherwise unfit for tasks assigned to themthem or lacks proper work credentials for the tasks assigned or proper immigration papers. No workers shall be permitted to reside at the Site under any circumstances.
7.7.1 At all times during performance of the Work on the ProjectWork, including during any partial use or occupancy by Owner or others, Contractor shall, and shall cause require all Subcontractors and Vendors to, abide by each and all of the following requirements:
7.7.1.1 Access to the Project Work area by construction personnel shall be the most inconspicuous route available, in order that the general public and the Owner’s personnel are not inconvenienced. Access shall be arranged with Owner prior to commencement of Work. Access to restricted and/or limited access areas required by Work shall be coordinated with Owner.
7.7.1.2 Owner’s toilet facilities and the Project’s permanent toilet facilities are not to be used by construction personnel.
7.7.1.3 During the FF&E and finish phase of construction, construction personnel are not permitted to eat and or smoke where materials are in place nor use tables and chairs or other furniture that are part of the Project. During this phase of the Project, Owner will designate appropriate places for eating.
7.7.1.4 Quiet and courtesy with respect to Owner’s employees and guests is mandatory.
7.7.1.5 Use all best efforts to ensure insure that Contractor’s and all Subcontractors’ activities do not interfere with any Project and Site systems (i.e., electric, elevator, plumbing, fire protection, HVAC, etc.) necessary to maintain ongoing operations of the Project and Site.
7.7.1.6 Power outages, mechanical shutdown and so forth shall be carefully coordinated with Owner. Contractor will provide Owner with two (2) full business days, advance notice of any planned shutdowns of any basic Project or Site systems, and will obtain Owner’s written approval prior to commencing any such shutdown.
7.7.1.7 All life safety systems requiring shut-down or tie-ins, in accordance with the above clause 7.7.1.6, shall be coordinated with Owner and shall be performed at such a time to minimize any effect of the safety, health and welfare of the building’s occupants. At the conclusion of each work-day, all operable life safety systems shall be energized and operative.
7.7.1.8 Contractor shall be responsible to Owner for acts and omissions of Contractor’s employees and agents, Subcontractors and Vendors and their respective agents and employees, and other persons performing portions of the Work under a contract or arrangement with or under the direction of Contractor or with or under the direction of any Subcontractor or Vendor. Except to the extent expressly provided otherwise in this Agreement, Contractor shall not be relieved of its obligation to perform the Work in accordance with the Contract Documents either by activities or duties of Owner or Architect/Engineer, or, by any request, approval or consent of Owner or Architect/Engineer, or by tests, inspections or approvals required or performed by persons other than Contractor. Contractor shall require and ensure that each Subcontractor and Vendor complies with all applicable requirements set forth in the Contract Documents for Contractor. Except to the extent the Contract Documents expressly provide otherwise, if any dispute arises between Owner, on the one hand, and Contractor, on the other hand, unless Owner directs otherwise, Contractor shall proceed with the performance of its obligations under the Contract with reservation of all rights and remedies it may have under and subject to the terms of the Contract Documents.
Appears in 1 contract
Site Discipline. Contractor shall employ, and require all Subcontractors and Vendors to employ, only skilled workers properly qualified by experience and ability to perform the tasks assigned to them, who are properly credentialed with visas and/or work permits allowing them to be legally employed at the Site. Contractor shall at all times be responsible for strict discipline and good order among its employees, craft labor, agents and representatives as well as the employees, craft labor, agents and representatives of its Subcontractors and Vendors while performing Work and all other persons performing any Work. When requested by Owner, Contractor shall remove and shall not re-assign to the Work any person who, in Owner’s reasonable opinion, is disorderly, insubordinate, unsafe, unskilled, incompetent or otherwise unfit for tasks assigned to themthem or lacks proper work credentials for the tasks assigned or proper immigration papers. No workers shall be permitted to reside at the Site under any circumstances.
7.7.1 At all times during performance of the Work on the ProjectWork, including during any partial use or occupancy by Owner or others, Contractor shall, and shall cause require all Subcontractors and Vendors to, abide by each and all of the following requirements:
7.7.1.1 Access to the Project Work area by construction personnel shall be the most inconspicuous route available, in order that the general public and the Owner’s personnel are not inconvenienced. Access shall be arranged with Owner prior to commencement of Work. Access to restricted and/or limited access areas required by Work shall be coordinated with Owner. Alterations to and restrictions of access to Work areas in connection with the Original Project Substantial Completion, Expansion Project Substantial Completion, Original Project Final Completion and/or Expansion Project Final Completion, in order that remaining portions of the Project can be opened, and with as little inconvenience as possible, to the general public, are included in the Original Project Guaranteed Maximum Price Premises and Assumptions or the Expansion Project Guaranteed Maximum Price Premises and Assumptions (as applicable).
7.7.1.2 Owner’s toilet facilities and the Project’s permanent toilet facilities are not to be used by construction personnel.
7.7.1.3 During the FF&E and finish phase of construction, construction personnel are not permitted to eat and or smoke where materials are in place nor use tables and chairs or other furniture that are part of the Project. During this phase of the Project, Owner will designate appropriate places for eating.
7.7.1.4 Quiet and courtesy with respect to Owner’s employees and guests is mandatory.
7.7.1.5 Use all best efforts to ensure insure that Contractor’s and all Subcontractors’ activities do not interfere with any Project and Site systems (i.e., electric, elevator, plumbing, fire protection, HVAC, etc.) necessary to maintain ongoing operations of the Project and Site.
7.7.1.6 Power outages, mechanical shutdown and so forth shall be carefully coordinated with Owner. Contractor will provide Owner with two (2) full business days, advance notice of any planned shutdowns of any basic Project or Site systems, and will obtain Owner’s written approval prior to commencing any such shutdown.
7.7.1.7 All life safety systems requiring shut-down or tie-ins, in accordance with the above clause 7.7.1.6, shall be coordinated with Owner and shall be performed at such a time to minimize any effect of the safety, health and welfare of the building’s occupants. At the conclusion of each work-day, all operable life safety systems shall be energized and operative.
7.7.1.8 Without limiting any other provision in this Section 7.7.1, any planned shutdowns of any basic Project or Site systems for the Original Project or Expansion Project following the Expansion Project Substantial Completion or Original Project Substantial Completion, respectively, require advance notice to and written advance approval from Owner prior to commencing any such shutdown.
7.7.1.9 Contractor shall be responsible to Owner for acts and omissions of Contractor’s employees and agents, Subcontractors and Vendors and their respective agents and employees, and other persons performing portions of the Work under a contract or arrangement with or under the direction of Contractor or with or under the direction of any Subcontractor or Vendor. Except to the extent expressly provided otherwise in this Agreement, Contractor shall not be relieved of its obligation to perform the Work in accordance with the Contract Documents either by activities or duties of Owner or Architect/Engineer, or, by any request, approval or consent of Owner or Architect/Engineer, or by tests, inspections or approvals required or performed by persons other than Contractor. Contractor shall require and ensure that each Subcontractor and Vendor complies with all applicable requirements set forth in the Contract Documents for Contractor. Except to the extent the Contract Documents expressly provide otherwise, if any dispute arises between Owner, on the one hand, and Contractor, on the other hand, unless Owner directs otherwise, Contractor shall proceed with the performance of its obligations under the Contract with reservation of all rights and remedies it may have under and subject to the terms of the Contract Documents.
7.7.1.10 Without limiting the provisions of Sections 7.7.1.1 through 7.7.1.9, Contractor acknowledges that upon opening portions of the Project to the general public, such portions are intended to be operated as a “five-star” first class Las Vegas-style resort; accordingly, Contractor shall, and require all Subcontractors and Vendors to, carry out their obligations under the Contract Documents with the utmost duty of care with respect to the general public.
Appears in 1 contract