Common use of Specific Requirements Clause in Contracts

Specific Requirements. Engineer's QA program shall include at least the following activities: 1. The specific methodology that will be used to cross-check all plans of the various disciplines to one another and for completeness and accuracy at each submittal stage. 2. The specific methodology that will be used to cross-check all the plans and specifications to each other for completeness and accuracy at each submittal stage. 3. A checklist of items that will be researched during the on-site investigation. 4. Maintenance of an "Exception to Project Requirements List." This list shall include all items that are at variance with the Project Program including various Owner departmental Design Guides and other written Project requirements. 5. A system for tracking and documenting all changes to the Project Program.

Appears in 3 contracts

Samples: Engineering Services Agreement, Engineering Services Agreement, Master Agreement for Mechanical and Electrical Engineering Services

AutoNDA by SimpleDocs

Specific Requirements. EngineerArchitect's QA program shall include at least the following activities: 1. The specific methodology that will be used to cross-check all plans of the various disciplines to one another and for completeness and accuracy at each submittal stage. 2. The specific methodology that will be used to cross-check all the plans and specifications to each other for completeness and accuracy at each submittal stage. 3. A checklist of items that will be researched during the on-site investigation. 4. Maintenance of an "Exception to Project Requirements List." This list shall include all items that are at variance with the Project Program including various Owner departmental Design Guides the FDI Manual, and other written Project requirements. 5. A system for tracking and documenting all changes to the Project Program.

Appears in 2 contracts

Samples: Agreement for Architectural Services, Architectural Services Agreement

Specific Requirements. Engineer's QA program shall include at least the following activities: 1. The specific methodology that will be used to cross-check cross -check all plans of the various disciplines to one another and for completeness and accuracy at each submittal stage. 2. The specific methodology that will be used to cross-check cross -check all the plans and specifications to each other for completeness and accuracy at each submittal stage. 3. A checklist of items that will be researched during the on-site investigation. 4. Maintenance of an "Exception to Project Requirements List." This list shall include all items that are at variance with the Project Program including various Owner departmental Owner’s Facilities Design Guides Standard and other written Project requirements. 5. A system for systemfor tracking and documenting all changes to the Project Program.

Appears in 2 contracts

Samples: Engineering Services Agreement, Engineering Services Agreement

Specific Requirements. EngineerArchitect's QA program shall include at least the following activities: 1. The specific methodology that will be used to cross-check all plans of the various disciplines to one another and for completeness and accuracy at each submittal stage. 2. The specific methodology that will be used to cross-check all the plans and specifications to each other for completeness and accuracy at each submittal stage. 3. A checklist of items that will be researched during the on-site investigation. 4. Maintenance of an "Exception to Project Requirements List." This list shall include all items that are at variance with the Project Program including various Owner departmental Design Guides and other written Project requirements. 5. A system for tracking and documenting all changes to the Project Program.

Appears in 1 contract

Samples: Architectural Services Agreement

Specific Requirements. EngineerArchitect's QA program shall include at least the following activities: 1. The specific methodology that will be used to cross-check all plans of the various disciplines to one another and for completeness and accuracy at each submittal stage. 2. The specific methodology that will be used to cross-check all the plans and specifications to each other for completeness and accuracy at each submittal stage. 3. A checklist of items that will be researched during the on-site investigation. 4. Maintenance of an "Exception to Project Requirements List." This list shall include all items that are at variance with the Project Program including the various Owner departmental Design Guides Guides, and other written Project requirements. 5. A system for tracking and documenting all changes to the Project Program.

Appears in 1 contract

Samples: Architectural Services Agreement

Specific Requirements. EngineerArchitect's QA program shall include at least the following activities: 1. The specific methodology that will be used to cross-check all plans of the various disciplines to one another and for completeness and accuracy at each submittal stage. 2. The specific methodology that will be used to cross-check all the plans and specifications to each other for completeness and accuracy at each submittal stage. 3. A checklist of items that will be researched during the on-site investigation. 4. Maintenance of an "Exception to Project Requirements List." This list shall include all items that are at variance with the Project Program including various Owner departmental Design Guides Guides, and other written Project requirements. 5. A system for tracking and documenting all changes to the Project Program.

Appears in 1 contract

Samples: Master Agreement for Architectural Services

Specific Requirements. EngineerArchitect's QA program shall include at least the following activities: 1. The specific methodology that will be used to cross-check cross -check all plans of the various disciplines to one another and for completeness and accuracy at each submittal stage. 2. The specific methodology that will be used to cross-check cross -check all the plans and specifications to each other for completeness and accuracy at each submittal stage. 3. A checklist of items that will be researched during the on-site investigation. 4. Maintenance of an "Exception to Project Requirements List." This list shall include all items that are at variance with the Project Program including various Owner departmental Owner’s Design Guides Standard and other written Project requirements. 5. A system for tracking and documenting all changes to the Project Program.

Appears in 1 contract

Samples: Architectural Services Agreement

AutoNDA by SimpleDocs

Specific Requirements. EngineerArchitect's QA program shall include at least the following activities: 1. The specific methodology that will be used to cross-check all plans of the various disciplines to one another and for completeness and accuracy at each submittal stage. 2. The specific methodology that will be used to cross-check cross -check all the plans and specifications to each other for completeness and accuracy at each submittal stage. 3. A checklist of items that will be researched during the on-site investigation. 4. Maintenance of an "Exception to Project Requirements List." This list shall include all items that are at variance with the Project Program including various Owner departmental the Owner’s Design Guides Standard, and other written Project requirements. 5. A system for systemfor tracking and documenting all changes to the Project Program.

Appears in 1 contract

Samples: Architectural Services Agreement

Specific Requirements. EngineerArchitect's QA program shall include at least the following activities: 1. The specific methodology that will be used to cross-check all plans of the various disciplines to one another and for completeness and accuracy at each submittal stage. 2. The specific methodology that will be used to cross-check all the plans and specifications to each other for completeness and accuracy at each submittal stage. 3. A checklist of items that will be researched during the on-site investigation. 4. Maintenance of an "Exception to Project Requirements List." This list shall include all items that are at variance with the Project Program including various Owner departmental Owner’s Facilities Design Guides Standard, and other written Project requirements. 5. A system for tracking and documenting all changes to the Project Program.

Appears in 1 contract

Samples: Master Agreement for Architectural Services

Specific Requirements. Engineer's QA program shall include at least the following activities: 1. The specific methodology that will be used to cross-check all plans of the various disciplines to one another and for completeness and accuracy at each submittal stage. 2. The specific methodology that will be used to cross-check all the plans and specifications to each other for completeness and accuracy at each submittal stage. 3. A checklist of items that will be researched during the on-site investigation. 4. Maintenance of an "Exception to Project Requirements List." This list shall include all items that are at variance with the Project Program including various Owner departmental Owner’s Facilities Design Guides Standard and other written Project requirements. 5. A system for tracking and documenting all changes to the Project Program.

Appears in 1 contract

Samples: Master Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!