Common use of Stage Payment for Works Clause in Contracts

Stage Payment for Works. 19.5.1 Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.4, the Authority’s Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 (ninety) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate by the Authority’s Engineer. Within 10 (ten) days of the receipt of recommendation of the Authority’s Engineer, the Authority shall make electronic payment directly to the Contractor’s bank account.

Appears in 21 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement, Draft Contract Agreement

AutoNDA by SimpleDocs

Stage Payment for Works. 19.5.1 (i) Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.4, the Authority’s Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 (ninety) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate by the Authority’s Engineer. Within 10 (ten) days of the receipt of recommendation of the Authority’s Engineer, the Authority shall make electronic payment directly to the Contractor’s bank account.

Appears in 12 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement, Procurement and Construction

Stage Payment for Works. 19.5.1 17.5.1 Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.417.4, the Authority’s Authority Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 80 (ninety) percent eighty)percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate (IPC) by the Authority’s Authority Engineer. Within 10 (ten5(five) days of the receipt of recommendation of the Authority’s EngineerAuthority Engineer as above, the Authority shall make electronic payment directly to the Contractor’s bank account.

Appears in 7 contracts

Samples: www.rites.com, rites.com, www.rites.com

Stage Payment for Works. 19.5.1 Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.4, the Authority’s Authority‟s Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 (ninety) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate by the Authority’s Authority‟s Engineer. Within 10 (ten) days of the receipt of recommendation of the Authority’s Authority‟s Engineer, the Authority shall make electronic payment directly to the Contractor’s Contractor‟s bank account.

Appears in 5 contracts

Samples: Procurement and Construction, Agreement, Draft Contract Agreement

Stage Payment for Works. 19.5.1 17.5.1 Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.417.4, the Authority’s Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 (ninety) percent per cent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate by the Authority’s Engineer. Within 10 (ten) days of the receipt of recommendation of the Authority’s Engineer, the Authority shall make electronic payment directly to the Contractor’s bank account.

Appears in 4 contracts

Samples: Procurement and Construction Agreement, Procurement and Construction Agreement, Procurement and Construction Agreement

Stage Payment for Works. 19.5.1 17.5.1 Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.417.4, the Authority’s Authority Engineer shall broadly determine the amount due to dueto the Contractor and recommend the release of 90 80 (ninetyeighty) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate (IPC) by the Authority’s Authority Engineer. Within 10 5 (tenfive) days of the receipt of recommendation of the Authority’s EngineerAuthority Engineer as above, the Authority shall make electronic payment directly to the Contractor’s bank account.

Appears in 4 contracts

Samples: And Construction Agreement, And Construction Agreement, And Construction Agreement

Stage Payment for Works. 19.5.1 Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.4, the Authority’s Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 (ninety) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate by the Authority’s Engineer. Within 10 (ten) days of the receipt of recommendation of the Authority’s Engineer, the Authority shall make electronic payment directly to the Contractor’s bank account.. 71

Appears in 2 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement

Stage Payment for Works. 19.5.1 17.5.1 Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.417.4, the Authority’s Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 90% (ninetyninety per cent) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate by the Authority’s Engineer. Within 10 (ten) days of the receipt of recommendation of the Authority’s Engineer, the Authority shall make an electronic payment thereof directly to the Contractor’s bank account.

Appears in 2 contracts

Samples: Model Agreement, Model Agreement

Stage Payment for Works. 19.5.1 (i) Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.4, the Authority’s 's Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 (ninety) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate by the Authority’s 's Engineer. Within 10 (ten) days of the receipt of recommendation of the Authority’s 's Engineer, the Authority shall make electronic payment directly to the Contractor’s 's bank account.

Appears in 2 contracts

Samples: Draft Contract Agreement, nhidcl.com

Stage Payment for Works. 19.5.1 (i) Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.4, the Authority’s Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 (ninety) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate by the Authority’s Engineer. Within 10 (ten) days ten)days of the receipt of recommendation of the Authority’s Engineer, the Authority shall make electronic payment directly to the Contractor’s bank account.

Appears in 1 contract

Samples: Draft Contract Agreement

Stage Payment for Works. 19.5.1 Within 10 15 (tenfifteen) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.4, the Authority’s Authority‟s Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 (ninety) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate by the Authority’s Authority‟s Engineer. Within 10 15 (tenfifteen) days of the receipt of recommendation of the Authority’s Authority‟s Engineer, the Authority shall make electronic payment directly to the Contractor’s Contractor‟s bank account.

Appears in 1 contract

Samples: Procurement and Construction Agreement

AutoNDA by SimpleDocs

Stage Payment for Works. 19.5.1 17.5.1 Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.417.4, the Authority’s Authority Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 80 (ninetyeighty) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate (IPC) by the Authority’s Authority Engineer. Within 10 5 (tenfive) days of the receipt of recommendation of the Authority’s EngineerAuthority Engineer as above, the Authority shall make electronic payment directly to the Contractor’s bank account.

Appears in 1 contract

Samples: Procurement and Construction Agreement

Stage Payment for Works. 19.5.1 17.5.1 Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.417.4, the Authority’s Authority Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 80 (ninetyeighty) percent per cent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate (IPC) by the Authority’s Authority Engineer. Within 10 5 (tenfive) days of the receipt of recommendation of the Authority’s EngineerAuthority Engineer as above, the Authority shall make electronic payment directly to the Contractor’s bank account.

Appears in 1 contract

Samples: Epc Agreement

Stage Payment for Works. 19.5.1 (i) Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to under Clause 19.4, the Authority’s Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 (ninety) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate by the Authority’s Engineer. Within 10 (ten) days of the receipt of the recommendation of the Authority’s Engineer, the Authority shall make electronic payment directly to the Contractor’s bank account.

Appears in 1 contract

Samples: bridgecorporationltd.com

Stage Payment for Works. 19.5.1 (i) Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant Contractorpursuant to Clause 19.4, the Authority’s Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 (ninety90(ninety) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate by the Authority’s Engineer. Within 10 (ten) days ten)days of the receipt of recommendation of the Authority’s Engineer, the Authority shall make electronic payment directly to the Contractor’s bank account.

Appears in 1 contract

Samples: nhidcl.com

Stage Payment for Works. 19.5.1 (i) Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.4, the Authority’s Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 (ninety) percent of the amount so determined as part payment against the Stage Payment Statement, pending issue of the Interim Payment Certificate by the Authority’s Engineer. Within 10 (ten) days of the receipt of recommendation of the Authority’s Engineer, the Authority shall make electronic payment directly to the Contractor’s bank accountbankaccount.

Appears in 1 contract

Samples: Draft Contract Agreement

Stage Payment for Works. 19.5.1 (i) Within 10 (ten) days of receipt of the Stage Payment Statement from the Contractor pursuant to Clause 19.4, the Authority’s Engineer shall broadly determine the amount due to the Contractor and recommend the release of 90 (ninety) percent of the amount so determined as part payment against the Stage Payment Statement, amountsodeterminedaspartpaymentagainsttheStagePaymentStatement,pending issue of the Interim Payment Certificate by the Authority’s Engineer. Within 10 (ten) days of the receipt of recommendation of the Authority’s Engineer, the Authority shall make electronic payment directly to the Contractor’s bank accountbankaccount.

Appears in 1 contract

Samples: Engineering Procurement And