Standard of Works. (a) Unless otherwise provided, the Developer shall, and must cause the Builder to, use suitable new materials and proper and tradesmanlike workmanship when carrying out the Works. (b) The qualitative standard of the design and finishes for the Works must be no less than those described in the following documents: (i) Any relevant Australian Standard; (ii) Any relevant design standards or guidelines and any other requirements or policies applied by the Council from time to time in assessing the adequacy of any works or improvements proposed for the public domain or to be accessible to the public in accordance with this agreement. (c) The Developer will obtain any relevant standards (including design standards), specifications, or guidelines and any other requirements or policies referred to in clause 6.2(b)(ii) of this Schedule from Council if the Council fails to deliver them to the Developer. (d) The Developer may but is not obliged to reinstate any Works where damage or destruction is as a result of: (i) Any act or omission of the Council or its employees, consultants or agents relating to any part of the Works under this agreement; or (ii) The use or occupation by the Council or its employees, consultants or agents, Council's representatives or other contractor of the Council of any part of the Works.
Appears in 4 contracts
Samples: Planning Agreement, Developer Infrastructure Agreements, Developer Infrastructure Agreements Policy
Standard of Works. (a) Unless otherwise provided, the Developer shall, and must cause the Builder to, use suitable new materials and proper and tradesmanlike workmanship when carrying out the Works.
(b) The qualitative standard of the design and finishes for the Works must be no less than those described in the following documents:
(i) Any relevant Australian Standard;
(ii) Any relevant design standards or guidelines and any other requirements or policies applied by the Council from time to time in assessing the adequacy of any works or improvements proposed for the public domain or to be accessible to the public in accordance with this agreement.
(c) The Developer will obtain any relevant standards (including design standards), specifications, or guidelines and any other requirements or policies referred to in clause 6.2(b)(ii) of this Schedule 2 from Council if the Council fails to deliver them to the Developer.
(d) The Developer may but is not obliged to reinstate any Works where damage or destruction is as a result of:
(i) Any act or omission of the Council or its employees, consultants or agents relating to any part of the Works under this agreement; or
(ii) The use or occupation by the Council or its employees, consultants or agents, Council's representatives or other contractor of the Council of any part of the Works; or
(iii) malicious damage and graffiti to any part of the Works by persons not associated with the Developer, Builder or Superintendent.
Appears in 3 contracts
Samples: Voluntary Planning Agreement, Voluntary Planning Agreement, Voluntary Planning Agreement
Standard of Works. (a) Unless otherwise provided, the Developer shall, and must cause the Builder to, use suitable new materials and proper and tradesmanlike workmanship when carrying out the Works.
(b) The qualitative standard of the design and finishes for the Works must be no less than those described in the following documents:
(i) Any relevant Australian Standard;
(ii) Any relevant design standards or guidelines and any other requirements or policies applied by the Council from time to time in assessing the adequacy of any works or improvements proposed for the public domain or to be accessible to the public in accordance with this agreement.
(c) The Developer will obtain any relevant standards (including design standards), specifications, or guidelines and any other requirements or policies referred to in clause 6.2(b)(ii) of this Schedule 3 from Council if the Council fails to deliver them to the Developer.
(d) The Developer may but is not obliged to reinstate any Works where damage or destruction is as a result of:
(i) Any act or omission of the Council or its employees, consultants or agents relating to any part of the Works under this agreement; or
(ii) The use or occupation by the Council or its employees, consultants or agents, Council's representatives or other contractor of the Council of any part of the Works.
Appears in 2 contracts
Samples: Voluntary Planning Agreement, Voluntary Planning Agreement
Standard of Works. (a) Unless otherwise provided, the Developer shall, and must cause the Builder to, use suitable new materials and proper and tradesmanlike tradesman-like workmanship when carrying out the Works.
(b) The qualitative standard of the design and finishes for the Works must be no less than those described in the following documents:
(i) Any relevant Australian Standard;
(ii) Any relevant design standards or guidelines and any other requirements or policies applied by the Council from time to time in assessing the adequacy of any works or improvements proposed for the public domain or to be accessible to the public in accordance with this agreement.
(c) The Developer will obtain any relevant standards (including design standards), specifications, or guidelines and any other requirements or policies referred to in clause 6.2(b)(ii) of this Schedule 2 from Council if the Council fails to deliver them to the Developer.
(d) The Developer may but is not obliged to reinstate any Works where damage or destruction is as a result of:
(i) Any act or omission of the Council or its employees, consultants or agents relating to any part of the Works under this agreement; or
(ii) The use or occupation by the Council or its employees, consultants or agents, Council's representatives or other contractor of the Council of any part of the Works.
Appears in 2 contracts
Samples: Voluntary Planning Agreement, Voluntary Planning Agreement
Standard of Works. (a) Unless otherwise provided, the Developer shall, and must cause the Builder to, use suitable new materials and proper and tradesmanlike workmanship when carrying out the Works.
(b) The qualitative standard of the design and finishes for the Works must be no less than those described in the following documents:
(i) Any relevant Australian Standard;
(ii) Any relevant design standards or guidelines and any other requirements or policies applied by the Council from time to time in assessing the adequacy of any works or improvements proposed for the public domain or to be accessible to the public in accordance with this agreementAgreement.
(c) The Developer will obtain any relevant standards (including design standards), specifications, or guidelines and any other requirements or policies referred to in clause 6.2(b)(ii) of this Schedule 5 from Council if the Council fails to deliver them to the Developer.
(d) The Developer may but is not obliged to reinstate any Works where damage or destruction is as a result of:
(i) Any act or omission of the Council or its employees, consultants or agents relating to any part of the Works under this agreementAgreement; or
(ii) The use or occupation by the Council or its employees, consultants or agents, Council's representatives or other contractor of the Council of any part of the Works.
Appears in 1 contract
Samples: Voluntary Planning Agreement
Standard of Works. (a) Unless otherwise provided, the Developer shall, and must cause the Builder to, use suitable new materials and proper and tradesmanlike workmanship when carrying out the Works.
(b) The qualitative standard of the design and finishes for the Works must be no less than those described in the following documents:
(i) Any relevant Australian Standard;
(ii) Any relevant design standards or guidelines and any other requirements or policies applied by the Council from time to time in assessing the adequacy of any works or improvements proposed for the public domain or to be accessible to the public in accordance with this agreement.
(c) The Developer will obtain any relevant standards (including design standards), specifications, or guidelines and any other requirements or policies referred to in clause 6.2(b)(ii) of this Schedule 2 from Council if the Council fails to deliver them to the Developer.
(d) The Developer may but is not obliged to reinstate any Works where damage or destruction is as a result of:
(i) Any act or omission of the Council or its employees, consultants or agents relating to any part of the Works under this agreement; or
(ii) The use or occupation by the Council or its employees, consultants or agents, Council's representatives or other contractor of the Council of any part of the Works.
Appears in 1 contract
Samples: Voluntary Planning Agreement
Standard of Works. (a) Unless otherwise provided, the Developer shall, and must cause the Builder to, use suitable new materials and proper and tradesmanlike workmanship when carrying out the Works.
(b) The qualitative standard of the design and finishes for the Works must be no less than those described in the following documents:
(i) Any relevant Australian Standard;
(ii) Any relevant design standards or guidelines and any other requirements or policies applied by the Council from time to time in assessing the adequacy of any works or improvements proposed for the public domain or to be accessible to the public in accordance with this agreement.
(c) The Developer will obtain any relevant standards (including design standards), specifications, or guidelines and any other requirements or policies referred to in clause 6.2(b)(ii) of this Schedule from Council if the Council fails to deliver them to the Developer.
(d) The Developer may but is not obliged to reinstate any Works where damage or destruction is as a result of:
(i) Any act or omission of the Council or its employees, consultants or agents relating to any part of the Works under this agreement; or
(ii) The use or occupation by the Council or its employees, consultants or agents, Council's representatives or other contractor of the Council of any part of the Works; or
(iii) The normal wear and tear of the Works through public use, other than damage caused by construction or other vehicles accessing the Land for the purposes of carrying out the construction of the Development.
Appears in 1 contract
Samples: Voluntary Planning Agreement
Standard of Works. (a) Unless otherwise provided, the Developer shall, and must cause the Builder to, use suitable new materials and proper and tradesmanlike workmanship when carrying out the Works.
(b) The qualitative standard of the design and finishes for the Works must be no less than those described in the following documents:
(i) Any relevant Australian Standard;
(ii) Any relevant design standards or guidelines and any other requirements or policies applied notified by the Council from time to time at the date of this agreement in assessing the adequacy of any works or improvements proposed for the public domain or to be accessible to the public in accordance with this agreement.
(c) The Developer will obtain Council must provide any relevant standards (including design standards), specifications, or guidelines and any other requirements or policies referred to in clause 6.2(b)(ii) of this Schedule from Council if the Council fails to deliver them 2 to the DeveloperDeveloper on or before the date of this agreement.
(d) The Developer may but is not obliged to reinstate any Works where damage or destruction is as a result of:
(i) Any act or omission of the Council or its employees, consultants or agents relating to any part of the Works under this agreement; or
(ii) The use or occupation by the Council or its employees, consultants or agents, Council's representatives or other contractor of the Council of any part of the Works.
Appears in 1 contract
Samples: Voluntary Planning Agreement
Standard of Works. (a) Unless otherwise provided, the Developer shall, and must cause the Builder to, use suitable new materials and proper and tradesmanlike workmanship when carrying out the Works.
(b) The qualitative standard of the design and finishes for the Works must be no less than those described in the following documents:
(i) Any relevant Australian Standard;
(ii) Any relevant design standards or guidelines and any other requirements or policies applied by the Council from time to time in assessing the adequacy of any works or improvements proposed for the public domain or to be accessible to the public in accordance with this agreement.
(c) The Developer will obtain any relevant standards (including design standards), specifications, or guidelines and any other requirements or policies referred to in clause 6.2(b)(ii7.2(b)(ii) of this Schedule from Council if the Council fails to deliver them to the Developer.
(d) The Developer may but is not obliged to reinstate any Works where damage or destruction is as a result of:
(i) Any act or omission of the Council or its employees, consultants or agents relating to any part of the Works under this agreement; or
(ii) The use or occupation by the Council or its employees, consultants or agents, Council's representatives or other contractor of the Council of any part of the Works.
Appears in 1 contract
Samples: Voluntary Planning Agreement
Standard of Works. (a) Unless otherwise provided, the Developer shall, and must cause the Builder to, use suitable new materials and proper and tradesmanlike workmanship when carrying out the Works.
(b) The qualitative standard of the design and finishes for the Works must be no less than those described in the following documents:
(i) Any relevant Australian Standard;
(ii) Any relevant design standards or guidelines and any other requirements or policies applied by the Council from time to time in assessing the adequacy of any works or improvements proposed for the public domain or to be accessible to the public in accordance with this agreement.
(c) The Developer will obtain any relevant standards (including design standards), specifications, or guidelines and any other requirements or policies referred to in clause 6.2(b)(ii6.1(b)(ii) of this Schedule 2 from Council if the Council fails to deliver them to the Developer.
(d) The Developer may but is not obliged to reinstate any Works where damage or destruction is as a result of:
(i) Any act or omission of the Council or its employees, consultants or agents relating to any part of the Works under this agreement; or
(ii) The use or occupation by the Council or its employees, consultants or agents, Council's representatives or other contractor of the Council of any part of the Works.
Appears in 1 contract
Samples: Voluntary Planning Agreement