Study Eligibility Criteria. To be an Eligible Study, the proposed Project to be studied must: (a) involve the installation or implementation of a Measure or Measures; (b) be in respect of a single Facility of the Eligible Person connected to, or behind the meter of another electricity consumer connected to, a Local Distribution Company’s Distribution System but in the LDC’s service area; (i) in the case of a proposed Small Capital Project, be expected to deliver at least 100 MWh of Annualized Electricity Savings and which may be eligible to receive a Project Incentive up to a maximum of $1,000,000; or (ii) in the case of a Project, be expected to generate, based on a detailed engineering study (and not just a Preliminary Engineering Study) approved by the Technical Reviewer and the LDC, Annualized Electricity Savings of greater than 350 MWh; and (d) not be an Ineligible Project. Pursuant to the terms and conditions of the Preliminary Engineering Study Initiative, (e) the scheduled in-service date of a Project may not occur any later than two years following the date of execution of an agreement for the Project Incentive Initiative or any later than December 31, 2015, unless otherwise approved by the LDC.
Appears in 1 contract
Study Eligibility Criteria. To be an Eligible Study, the proposed Project to be studied must:
(a) involve the installation or implementation of a Measure or Measures;
(b) be in respect of a single Facility of the Eligible Person connected to, or behind the meter of another electricity consumer connected to, a Local Distribution Company’s Distribution System but in the LDC’s service area;
(i) in the case of a proposed Small Capital Project, be expected to deliver at least 100 MWh of Annualized Electricity Savings and which may be eligible to receive a Project Incentive up to a maximum of $1,000,000; or (ii) in the case of a Project, be expected to generate, based on a detailed engineering study (and not just a Preliminary Engineering Study) approved by the Technical Reviewer and the LDC, Annualized Electricity Savings of greater than 350 MWh; and
(d) not be an Ineligible Project. Pursuant to the terms and conditions of the Preliminary Engineering Study InitiativeProgram,
(e) the scheduled in-service date of a Project may not occur any later than two years following the date of execution of an agreement for the Project Incentive Initiative Program or any later than December 31, 20152020, unless otherwise approved by the LDC.
Appears in 1 contract
Study Eligibility Criteria. To be an Eligible Study, the proposed Project to be studied must:
(a) involve the installation or implementation of a Measure or Measures;
(b) be in respect of a single Facility of the Eligible Person connected to, or behind the meter of another electricity consumer connected to, a Local Distribution Company’s Distribution System System, but in the LDC’s service area;
(i) in the case of a proposed Small Capital Project, be expected to deliver at least 100 MWh of Annualized Electricity Savings and which may be eligible to receive a Project Incentive up to a maximum of $1,000,000; or (ii) in the case of a Project, be expected to generate, based on a detailed engineering study (and not just a Preliminary Detailed Engineering Study) Study approved by the Technical Reviewer and the LDC, Annualized Electricity Savings of greater than 350 MWh; and
(d) not be an Ineligible Project. Pursuant to the terms and conditions of the Preliminary Detailed Engineering Study InitiativeProgram,
(e) the scheduled in-service date of a Project may not occur any later than two years following the date of execution of an agreement for the Project Incentive Initiative Program or any later than December 31, 20152020, unless otherwise approved by the LDC.
Appears in 1 contract
Study Eligibility Criteria. To be an Eligible Study, the proposed Project to be studied must:
(a) involve the installation or implementation of a Measure or Measures;
(b) be in respect of a single Facility of the Eligible Person connected to, or behind the meter of another electricity consumer connected to, a Local Distribution Company’s Distribution System System, but in the LDC’s service area;
(i) in the case of a proposed Small Capital Project, be expected to deliver at least 100 MWh of Annualized Electricity Savings and which may be eligible to receive a Project Incentive up to a maximum of $1,000,000; or (ii) in the case of a Project, be expected to generate, based on a detailed engineering study (and not just a Preliminary Detailed Engineering Study) Study approved by the Technical Reviewer and the LDC, Annualized Electricity Savings of greater than 350 MWh; and
(d) not be an Ineligible Project. Pursuant to the terms and conditions of the Preliminary Detailed Engineering Study Initiative,
(e) the scheduled in-service date of a Project may not occur any later than two years following the date of execution of an agreement for the Project Incentive Initiative or any later than December 31, 20152020, unless otherwise approved by the LDC.
Appears in 1 contract