Supervision and Construction Procedures; Coordination; Cutting, and Patching. A. The CM shall supervise and direct the Work, using the CM's best skill and attention. The CM shall be solely responsible for, and shall have control over, construction means, methods, techniques, sequences and procedures, and shall be responsible for coordinating all portions of the Work under the Contract. B. The CM shall be responsible for the proper fitting of all Work and the coordination of the operations of all trades, Subcontractors, and materialmen engaged upon the Work. The CM shall guarantee to each of its Subcontractors all dimensions which they may require for the fitting of their work to all surrounding work. C. All necessary cutting, coring, drilling, grouting, and patching required to fit together the several parts of the Work shall be coordinated by the CM. D. The CM shall be responsible to DCAMM for the acts and omissions of the CM's employees, agents and Subcontractors of all tiers, and their agents and respective contractors employees, and other persons performing portions of the Work or supplying materials therefor. E. The CM shall be responsible for the inspection of portions of the Work already performed under this Contract to determine that such portions are in proper condition to receive subsequent Work. F. The CM shall employ a registered land surveyor to perform any engineering required for establishing grades, lines, levels, dimensions, layouts, and reference points for the trades. The CM shall be responsible for maintaining benchmarks and other survey marks and shall replace any benchmarks or survey marks that may have become disturbed or destroyed. The CM shall verify the materials shown on the Drawings before laying out the Work and shall be responsible for any error resulting from its failure to exercise this precaution. G. Unless otherwise required by the Contract Documents, or directed in writing by the Designer or DCAMM, Work shall be performed during regular Working Hours which, unless prescribed otherwise by applicable law, shall be 7:00 a.m. to 5:00 p.m. However, if the CM desires to carry on the Work outside of regular working hours or on Saturdays, Sundays, or Massachusetts or federal holidays then the CM shall provide 48 hours notice to allow satisfactory arrangements to be made for inspecting Work in progress and shall bear the costs of such inspection. DCAMM shall bill the CM directly for such costs. H. Work performed outside of regular Working Hours without the consent or knowledge of the Designer and/or DCAMM shall be subject to additional inspection and testing as directed by the Designer. The cost of this inspection and testing shall be borne by the CM whether the Work is found to be acceptable or not. DCAMM at its election shall be entitled either to issue a credit Change Order to cover such cost or to withhold such cost from any further payments due the CM and/or to receive a payment from the CM of the amount of such cost.
Appears in 2 contracts
Samples: Construction Manager at Risk Services Agreement, Construction Manager at Risk Services Agreement
Supervision and Construction Procedures; Coordination; Cutting, and Patching. A. The CM Contractor shall supervise and direct the Work, using the CMContractor's best skill and attention. The CM Contractor shall be solely responsible for, and shall have control over, construction means, methods, techniques, sequences and procedures, and shall be responsible for coordinating all portions of the Work under the Contract.
B. The CM Contractor shall be responsible for the proper fitting of all Work and the coordination of the operations of all trades, Subcontractors, and materialmen engaged upon the Work. The CM Contractor shall guarantee to each of its Subcontractors all dimensions which they may require for the fitting of their work to all surrounding work.
C. All necessary cutting, coring, drilling, grouting, and patching required to fit together the several parts of the Work shall be coordinated done by the CMContractor, except as may be specifically noted otherwise under any particular filed sub-bid section of the Specifications.
D. The CM Contractor shall be responsible to DCAMM the Awarding Authority for the acts and omissions of the CMContractor's employees, agents and Subcontractors of all tiersSubcontractors, and their agents and respective contractors employees, and other persons performing portions of the Work or supplying materials therefor.and
E. The CM Contractor shall be responsible for the inspection of portions of the Work already performed under this Contract to determine that such portions are in proper condition to receive subsequent Work.
F. The CM Contractor shall employ a registered land surveyor to perform any engineering required for establishing grades, lines, levels, dimensions, layouts, and reference points for the trades. The CM Contractor shall be responsible for maintaining benchmarks and other survey marks and shall replace any benchmarks or survey marks that may have become disturbed or destroyed. The CM Contractor shall verify the materials shown on the Drawings before laying out the Work and shall be responsible for any error resulting from its failure to exercise this precaution.
G. Unless otherwise required by the Contract DocumentsSupplementary General Conditions or the Plans and Specifications, or directed in writing by the Designer or DCAMMDesigner, Work shall be performed during regular Working Hours which, unless prescribed otherwise by applicable law, shall be 7:00 a.m. to 5:00 p.m. Hours. However, if the CM Contractor desires to carry on the Work outside of regular working hours Working Hours or on Saturdays, Sundays, or Massachusetts or federal holidays then the CM Contractor shall provide 48 hours notice allow ample time to allow satisfactory arrangements to be made for inspecting Work in progress and shall bear the costs of such inspection. DCAMM The Awarding Authority shall bill the CM Contractor directly for such costs.
H. Work performed outside of regular Working Hours without the consent or knowledge of the Designer and/or DCAMM the Awarding Authority shall be subject to additional inspection and testing as directed by the Designer. The cost of this inspection and testing shall be borne by the CM Contractor whether the Work is found to be acceptable or not. DCAMM The Awarding Authority at its election shall be entitled either to issue a credit Change Order to cover such cost or to withhold such cost from any further payments due the CM Contractor and/or to receive a payment from the CM Contractor of the amount of such cost.
Appears in 1 contract
Samples: Construction Contract
Supervision and Construction Procedures; Coordination; Cutting, and Patching. A. The CM Contractor shall supervise and direct the Work, using the CMContractor's best skill and attention. The CM Contractor shall be solely responsible for, and shall have control over, construction means, methods, techniques, sequences and procedures, and shall be responsible for coordinating all portions of the Work under the Contract.
B. The CM Contractor shall be responsible for the proper fitting of all Work and the coordination of the operations of all trades, Subcontractors, and materialmen engaged upon the Work. The CM Contractor shall guarantee to each of its Subcontractors all dimensions which they may require for the fitting of their work to all surrounding work.
C. All necessary cutting, coring, drilling, grouting, and patching required to fit together the several parts of the Work shall be coordinated done by the CMContractor, except as may be specifically noted otherwise under any particular filed sub‑bid section of the Specifications.
D. The CM Contractor shall be responsible to DCAMM the Awarding Authority for the acts and omissions of the CMContractor's employees, agents and Subcontractors of all tiersSubcontractors, and their agents and respective contractors employees, and other persons performing portions of the Work or supplying materials therefor.
E. The CM Contractor shall be responsible for the inspection of portions of the Work already performed under this Contract to determine that such portions are in proper condition to receive subsequent Work.
F. The CM Contractor shall employ a registered land surveyor to perform any engineering required for establishing grades, lines, levels, dimensions, layouts, and reference points for the trades. The CM Contractor shall be responsible for maintaining benchmarks and other survey marks and shall replace any benchmarks or survey marks that may have become disturbed or destroyed. The CM Contractor shall verify the materials shown on the Drawings before laying out the Work and shall be responsible for any error resulting from its failure to exercise this precaution.
G. Unless otherwise required by the Contract DocumentsSupplementary General Conditions or the Plans and Specifications, or directed in writing by the Designer or DCAMMDesigner, Work shall be performed during regular Working Hours which, unless prescribed otherwise by applicable law, shall be 7:00 a.m. to 5:00 p.m. Hours. However, if the CM Contractor desires to carry on the Work outside of regular working hours Working Hours or on Saturdays, Sundays, or Massachusetts or federal holidays then the CM Contractor shall provide 48 hours notice allow ample time to allow satisfactory arrangements to be made for inspecting Work in progress and shall bear the costs of such inspection. DCAMM The Awarding Authority shall bill the CM Contractor directly for such costs.
H. Work performed outside of regular Working Hours without the consent or knowledge of the Designer and/or DCAMM the Awarding Authority shall be subject to additional inspection and testing as directed by the Designer. The cost of this inspection and testing shall be borne by the CM Contractor whether the Work is found to be acceptable or not. DCAMM The Awarding Authority at its election shall be entitled either to issue a credit Change Order to cover such cost or to withhold such cost from any further payments due the CM Contractor and/or to receive a payment from the CM Contractor of the amount of such cost.
Appears in 1 contract
Samples: Construction Contract
Supervision and Construction Procedures; Coordination; Cutting, and Patching. A. The CM Contractor shall supervise and direct the Work, using the CMContractor's best skill and attention. The CM Contractor shall be solely responsible for, and shall have control over, construction means, methods, techniques, sequences and procedures, and shall be responsible for coordinating all portions of the Work under the Contract.
B. The CM Contractor shall be responsible for the proper fitting of all Work and the coordination of the operations of all trades, Subcontractors, and materialmen engaged upon in the Work. The CM Contractor shall guarantee to each of its Subcontractors all dimensions which they may require for the fitting of their work Work to all surrounding workWork.
C. All necessary cutting, coring, drilling, grouting, and patching required to fit together the several parts of the Work shall be coordinated done by the CMContractor, except as may be specifically noted otherwise under any particular filed sub-bid section of the Specifications.
D. The CM Contractor shall be responsible to DCAMM the Awarding Authority for the acts and omissions of the CMContractor's employees, agents and Subcontractors of all tiersSubcontractors, and their agents and respective contractors contractors’ employees, and other persons performing portions of the Work or supplying materials therefor.
E. The CM Contractor shall be responsible for the inspection of portions of the Work already performed under this Contract to determine that such portions are completed in accordance with industry standards of good workmanship and the Contract Documents and in proper condition to receive subsequent Work.
F. The CM Contractor shall employ a registered land surveyor to perform any engineering required for establishing grades, lines, levels, dimensions, layouts, and reference points for the trades. The CM Contractor shall be responsible for maintaining benchmarks and other survey marks and shall replace any benchmarks or survey marks that may have become disturbed or destroyed. The CM Contractor shall verify the materials shown on the Drawings before laying out the Work and shall be responsible for any error resulting from its failure to exercise this precaution.
G. Unless otherwise required by the Contract Documents, or directed in writing by the Designer or DCAMMthe Awarding Authority, Work shall be performed during regular Working Hours working hours, which, unless prescribed otherwise by applicable lawLaw, shall be 7:00 a.m. to 5:00 p.m. However, if p.m.. If the CM Contractor desires to carry on the Work outside of regular working hours or on Saturdays, Sundays, or Massachusetts or federal holidays holidays, then the CM Contractor shall provide 48 hours at least forty-eight (48) hours’ notice to the Awarding Authority and Designer to allow satisfactory arrangements to be made for inspecting Work in progress and shall bear the costs of such inspection. DCAMM shall bill the CM directly for such costs.
H. Work performed outside of regular Working Hours without the consent or knowledge of the Designer and/or DCAMM shall be subject to additional inspection and testing as directed by the Designer. The cost of this inspection and testing shall be borne by the CM whether the Work is found to be acceptable or not. DCAMM Awarding Authority at its election shall be entitled either to issue a credit Change Order to cover such cost or to withhold such cost from any further payments due the CM Contractor and/or to receive a payment from the CM Contractor of the amount of such cost.
H. Work performed outside of regular working hours set forth above without the consent or knowledge of the Designer and/or the Awarding Authority shall be subject to additional inspection and testing as directed by the Designer. The cost of this inspection and testing shall be borne by the Contractor whether the Work is found to be acceptable or not. The Awarding Authority at its election shall be entitled either to issue a credit Change Order to cover such cost or to withhold such cost from any further payments due the Contractor and/or to receive a payment from the Contractor of the amount of such cost.
Appears in 1 contract
Samples: Construction Contract