Suspension for Other Reasons. 20.2.1 Owner has the authority to suspend the Work, wholly or in part, for such period as Owner deems necessary because of the failure on the part of Contractor to correct conditions that are unsafe for workers or the general public, to carry out orders properly given, or to perform any requirements of the Contract Documents if (a) Owner gives written notice to Contractor which sets forth the failure with specificity; and (b) Contractor does not commence a cure of such failure within seven (7) days after receipt of such notice, and thereafter diligently pursues such cure to completion within thirty (30) days or, if such failure is not curable within such thirty-day period, commence to cure and diligently pursue such cure within such thirty-day period. The suspended Work shall be resumed when appropriate corrective action has been taken. 20.2.2 Contractor shall not be entitled to any increase in the Contract Price or extension of the Contract Time(s) in connection with any suspension under this Section 20.2, including for the Work described in Section 20.3 unless it is later determined that such suspension was wrongful.
Appears in 2 contracts
Samples: Design Build Contract, Design Build Contract
Suspension for Other Reasons. 20.2.1 Owner has the authority to suspend the Work, wholly or in part, for such period as Owner deems necessary because of the failure on the part of Contractor to correct conditions that are unsafe for workers or the general public, to carry out orders properly given, or to perform any requirements of the Contract Documents if (a) Owner gives written notice to Contractor which sets forth the failure with specificity; and (b) Contractor does not commence a cure of such failure within seven (7) days after receipt of such notice, and thereafter diligently pursues such cure to completion within thirty (30) days or, if such failure is not curable within such thirty-day period, commence to cure and diligently pursue such cure within such thirty-day period. The suspended Work shall be resumed when appropriate corrective action has been taken.
20.2.2 Contractor shall not be entitled to any increase in the Contract Price or extension of the Contract Time(s) Scheduled Substantial Completion Date in connection with any suspension under this Section 20.2, including for the Work described in Section 20.3 unless it is later determined that such suspension was wrongful.
Appears in 2 contracts
Samples: Design Build Contract, Design Build Contract