Suspension of Project. Contractor may not suspend performance of any part of the Project except as directed and authorized by OMPA. OMPA may, at any time and in its sole discretion, suspend performance of all or part of the Project, as follows: 6.5.1. OMPA will notify Contractor about any Project suspension and identify the scope and effective date of the suspension. Contractor will suspend performance of the Project in accordance with OMPA's notice but will continue to perform the portion of the Project not suspended. Upon receipt of OMPA's notice, Contractor will protect and preserve items committed to or purchased for the suspended portion of the Project and will take commercially reasonable steps to minimize the financial consequences of the suspension. 6.5.2. If the suspension is unrelated to Contractor's failure to comply with this Contract, OMPA will adjust the schedule to reflect the reasonable delay due to the suspension and will reimburse Contractor for the reasonable and direct additional costs incurred by Contractor due solely to the safeguarding or storage of Project materials in accordance with OMPA's instructions. Provided, the aggregate sum of such costs may not exceed the Change Order limits listed in Article 3.
Appears in 9 contracts
Samples: Cooling Tower Repairs Contract, Pro Forma Contract, Pro Forma Contract
Suspension of Project. Contractor may not suspend performance of any part of the Project except as directed and authorized by OMPA. OMPA may, at any time and in its sole discretion, suspend performance of all or part of the Project, as follows:
6.5.1. OMPA will notify Contractor about any Project suspension suspension, and identify the scope and effective date of the suspension. Contractor will suspend performance of the Project in accordance with OMPA's notice notice, but will continue to perform the portion of the Project not suspended. Upon receipt of OMPA's notice, Contractor will protect and preserve items committed to or purchased for the suspended portion of the Project Project, and will take commercially reasonable steps to minimize the financial consequences of the suspension.
6.5.2. If the suspension is unrelated to Contractor's failure to comply with this Contract, OMPA will adjust the schedule to reflect the reasonable delay due to the suspension and will reimburse Contractor for the reasonable and direct additional costs incurred by Contractor due solely to the safeguarding or storage of Project materials in accordance with OMPA's instructions. Provided, the aggregate sum of such costs may not exceed the Change Order limits listed in Article 3.
Appears in 1 contract
Samples: Pro Forma Contract
Suspension of Project. Contractor may not suspend performance of any part of the Project except as directed and authorized by OMPA. OMPA may, at any time and in its sole discretion, suspend performance of all or part of the Project, as follows:
6.5.1. a) OMPA will notify Contractor about any Project suspension and identify the scope and effective date of the suspension. Contractor will suspend performance of the Project in accordance with OMPA's notice but and will continue to perform the any portion of the Project not suspended. Upon receipt of OMPA's notice, Contractor will protect and preserve items committed to or purchased for the suspended portion of the Project and will take commercially reasonable steps shall use its best efforts to minimize the financial consequences impact of the suspension.
6.5.2. b) If the suspension is unrelated to Contractor's failure to comply with this Contract, OMPA will adjust the schedule to reflect the reasonable delay due to the suspension and will reimburse Contractor for the reasonable and direct additional costs incurred by Contractor due solely to the safeguarding or storage of Project materials in accordance with OMPA's instructions. Provided, the aggregate sum of such costs may not exceed the Change Order limits listed in Article 3.
Appears in 1 contract
Samples: Pro Forma Contract