Common use of Suspension of unsafe Construction Works Clause in Contracts

Suspension of unsafe Construction Works. 13.5.1 Upon recommendation of the Independent Engineer to this effect, the Lead ULB may, by notice, require the Concessionaire to suspend forthwith the whole or any part of the Construction Work if, in the reasonable opinion of the Lead ULB, such work is unsafe and potential safety hazard. 13.5.2 The Concessionaire shall, pursuant to notice under Clause 13.5.1, suspend the Construction Works or any part thereof for such time and in such manner as may be specified by the Participating ULBs and thereupon carry out remedial measure to secure the safety of suspended works. The Concessionaire may by notice require the Independent Engineer to inspect such remedial measure forthwith and make a report to the Lead ULB recommending whether or not such suspension hereunder may be revoked. Upon receiving the recommendations of the Independent Engineer, the Lead ULB shall either revoke such suspension or instruct the Concessionaire to carry out such other and further remedial measures as may be necessary in the reasonable opinion of the Lead ULB, and the procedure set forth in Clause 13.5.1 shall be repeated until the suspension hereunder is revoked.

Appears in 2 contracts

Samples: Concession Agreement, Concession Agreement

AutoNDA by SimpleDocs

Suspension of unsafe Construction Works. 13.5.1 13.4.1 Upon recommendation of the Independent Engineer to this effect, the Lead ULB may, Authority may by notice, notice require the Concessionaire to suspend forthwith the whole or any part of the Construction Work Works if, in the reasonable opinion of the Lead ULBAuthority, such work is unsafe and potential threatens the safety hazardof the Existing Hospital or public. 13.5.2 13.4.2 The Concessionaire shall, pursuant to the notice under Clause 13.5.113.4.1, suspend the Construction Works or any part thereof for such time and in such manner as may be specified by the Participating ULBs Authority and thereupon carry out remedial measure measures to secure the safety of suspended works. The Concessionaire may by notice require the Independent Engineer to inspect such remedial measure measures forthwith and make a report to the Lead ULB Authority recommending whether or not such the suspension hereunder may be revoked. Upon receiving the recommendations of the Independent Engineer, the Lead ULB Authority shall either revoke such suspension or instruct the Concessionaire to carry out such other and further remedial measures as may be necessary in the reasonable opinion of the Lead ULBAuthority, and the procedure set forth in this Clause 13.5.1 13.4 shall be repeated until the suspension hereunder is revoked.

Appears in 1 contract

Samples: Concession Agreement

Suspension of unsafe Construction Works. 13.5.1 Upon recommendation of The Construction Supervisor in consultation with the Independent Engineer to this effect, the Lead ULB may, by notice, require the Concessionaire to suspend forthwith the whole or any part of the Construction Work if, in the reasonable opinion of the Lead ULBConstruction Supervisor and / or theULB, such work is unsafe and may cause potential safety hazard. 13.5.2 The Concessionaire shall, pursuant to notice under Clause 13.5.1, suspend the Construction Works or any part thereof for such time and in such manner as may be specified by the Participating ULBs Construction Supervisor and / or the ULB and thereupon carry out remedial measure to secure the safety of suspended works. The Concessionaire may by notice require the Independent Engineer Construction Supervisor to inspect such remedial measure forthwith and make a report to the Lead ULB recommending whether or not such suspension hereunder may be revoked. Upon receiving Based on the recommendations inspection of the Independent Engineerremedial measure undertaken by the Concessionaire, the Lead Construction Supervisor in consultation with the ULB shall either revoke such suspension or instruct the Concessionaire to carry out such other and further remedial measures as may be necessary in the reasonable opinion of the Lead ULBConstruction Supervisor and / or theULB, and the procedure set forth setforth in Clause 13.5.1 shall be repeated until the suspension hereunder is revoked.

Appears in 1 contract

Samples: Concession Agreement

AutoNDA by SimpleDocs

Suspension of unsafe Construction Works. 13.5.1 Upon recommendation of The Construction Supervisor in consultation with the Independent Engineer to this effect, the Lead ULB mayULBmay, by notice, require the Concessionaire to suspend forthwith the whole or any part of the Construction Work if, in the reasonable opinion of the Lead ULBConstruction Supervisor and / or theULB, such work is unsafe and may cause potential safety hazard. 13.5.2 The Concessionaire shall, pursuant to notice under Clause 13.5.1, suspend the Construction Works or any part thereof for such time and in such manner as may be specified by the Participating ULBs Construction Supervisor and / or theULB and thereupon carry out remedial measure to secure the safety of suspended works. The Concessionaire may by notice require the Independent Engineer Construction Supervisor to inspect such remedial measure forthwith and make a report to the Lead ULB recommending whether or not such suspension hereunder may be revoked. Upon receiving .Based on the recommendations inspection of the Independent Engineerremedial measure undertaken by the Concessionaire, the Lead Construction Supervisor in consultation with the ULB shall either revoke such suspension or instruct the Concessionaire to carry out such other and further remedial measures as may be necessary in the reasonable opinion of the Lead ULBConstruction Supervisor and / or theULB, and the procedure set forth setforth in Clause 13.5.1 shall be repeated until the suspension hereunder is revoked.

Appears in 1 contract

Samples: Concession Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!