Commercial Operation Date 6.4.1 The SPV shall ensure that the Project Commercial Operation Date is achieved on or prior to the Scheduled Commercial Operation Date. The SPV shall provide a written notice to MSEDCL at least 30 (thirty) days in advance intimating MSEDCL of the proposed date on which the Commercial Operation Date of a Unit or the Project is proposed to be achieved. 6.4.2 If the Commercial Operation Date for the Units having a capacity equivalent to at least 75% (seventy five percent) of the Contracted Capacity is achieved before the Scheduled Commercial Operation Date, then all Units in respect of which the Commercial Operation Date has been achieved prior to the Scheduled Commercial Operation Date would be eligible for incentives as follows: (a) the Unit(s) injecting energy at 11 kV /22 kV shall be given an incentive of Rs. 0.25/ kWh; and (b) the Unit(s) injecting energy at 33 kV shall be given an incentive of Rs. 0.15/ kWh, for the power sold to MSEDCL for the first 3 (three) years from the Commercial Operation Date. To receive such incentives from MSAPL, which shall be over and above the Tariff, the SPV shall follow the process agreed to by the SPV under the Implementation Agreement. 6.4.3 It is hereby clarified that the aforementioned incentive shall not be available: (i) in respect of any Unit if the Commercial Operation Date for such Unit has not been achieved prior to the Scheduled Commercial Operation Date; and (ii) if the aggregate capacity of the Units for which the Commercial Operation Date has been achieved prior to Scheduled Commercial Operation Date is less than 75% (seventy five percent) of the Contracted Capacity. 6.4.4 In the event that Commercial Operation Date for any of the Units is achieved after the Scheduled Commercial Operation Date, the SPV shall be liable to pay Liquidated Damages as per the provisions set out below. 6.4.5 Without prejudice to any other rights of MSEDCL under this PPA, in case one or more Units of the SPV are unable to achieve Commercial Operation Date within a period of 2 (two) months from the Scheduled Commercial Operation Date, the capacity of such Units shall be annulled, and the Contracted Capacity shall be reduced to that extent. For Illustration: The Project has a Contracted Capacity of 100 MW and comprises of 10 Units of 10 MW each. If at the end of the aforementioned period of 14 (fourteen) months from the Effective Date, the SPV has achieved Commissioning for only 8 out of 10 Units, then the Contracted Capacity of the Project will stand reduced for the capacity of the 2 Units which have not been Commissioned, i.e. the Contracted Capacity will be 80 (100 (original Contracted Capacity)) – 10 (capacity of each Unit)*2 (number of Units not Commissioned).
Post-Commercial Operation Date Testing and Modifications Each Party shall at its own expense perform routine inspection and testing of its facilities and equipment in accordance with Good Utility Practice as may be necessary to ensure the continued interconnection of the Large Generating Facility with the Participating TO’s Transmission System in a safe and reliable manner. Each Party shall have the right, upon advance written notice, to require reasonable additional testing of the other Party’s facilities, at the requesting Party’s expense, as may be in accordance with Good Utility Practice.
Commercial Operation Date Testing and Modifications Prior to the Commercial Operation Date, the Connecting Transmission Owner shall test the Connecting Transmission Owner’s Attachment Facilities and System Upgrade Facilities and System Deliverability Upgrades and Developer shall test the Large Generating Facility and the Developer Attachment Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Developer and Connecting Transmission Owner shall each make any modifications to its facilities that are found to be necessary as a result of such testing. Developer shall bear the cost of all such testing and modifications. Developer shall generate test energy at the Large Generating Facility only if it has arranged for the injection of such test energy in accordance with NYISO procedures.
Commercial Operation (i) On or before December 31, 2021, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.
Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least fifteen (15) days written notice to the SLDC / ALDC / DISCOM as the case may be, of the date on which it intends to synchronize the Power Project to the Grid System. 4.1.2 Subject to Article 4.1.1, the Power Project may be synchronized by the Power Producer to the Grid System when it meets all the connection conditions prescribed in the Grid Code and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 4.1.3 The synchronization equipment and all necessary arrangements / equipment including Remote Terminal Unit (RTU) for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the Power Producer at its generation facility of the Power Project at its own cost. The Power Producer shall synchronize its system with the Grid System only after the approval of GETCO / SLDC / ALDC and GEDA. 4.1.4 The Power Producer shall immediately after each synchronization / tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. 4.1.5 The Power Producer shall commission the Project within SCOD. 4.1.6 The Power Producer shall be required to obtain Developer and/ or Transfer Permission, Key Plan drawing etc, if required, from GEDA. In cases of conversion of land from Agricultural to Non-Agriculture, the commissioning shall be taken up by GEDA only upon submission of N.A. permission by the Power Producer. 4.1.7 The Power Producer shall be required to follow the Forecasting and Scheduling procedures as per the Regulations issued by Hon’ble GERC from time to time. It is to clarify that in terms of GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2019 the procedures for Forecasting, Scheduling & Deviation Settlment are applicable to all solar generators having combined installed capacity above 1 MW connected to the State Grid / Substation including those connected via pooling stations.
ADDITIONAL SPECIAL CONTRACT CONDITIONS Special Contract Conditions revisions: the corresponding subsections of the Special Contract Conditions referenced below are replaced in their entirety with the following:
Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.
Long Term Cost Evaluation Criterion 4. READ CAREFULLY and see in the RFP document under "Proposal Scoring and Evaluation". Points will be assigned to this criterion based on your answer to this Attribute. Points are awarded if you agree not increase your catalog prices (as defined herein) more than X% annually over the previous year for the life of the contract, unless an exigent circumstance exists in the marketplace and the excess price increase which exceeds X% annually is supported by documentation provided by you and your suppliers and shared with TIPS, if requested. If you agree NOT to increase prices more than 5%, except when justified by supporting documentation, you are awarded 10 points; if 6% to 14%, except when justified by supporting documentation, you receive 1 to 9 points incrementally. Price increases 14% or greater, except when justified by supporting documentation, receive 0 points. increases will be 5% or less annually per question Required Confidentiality Claim Form This completed form is required by TIPS. By submitting a response to this solicitation you agree to download from the “Attachments” section, complete according to the instructions on the form, then uploading the completed form, with any confidential attachments, if applicable, to the “Response Attachments” section titled “Confidentiality Form” in order to provide to TIPS the completed form titled, “CONFIDENTIALITY CLAIM FORM”. By completing this process, you provide us with the information we require to comply with the open record laws of the State of Texas as they may apply to your proposal submission. If you do not provide the form with your proposal, an award will not be made if your proposal is qualified for an award, until TIPS has an accurate, completed form from you. Read the form carefully before completing and if you have any questions, email Xxxx Xxxxxx at TIPS at xxxx.xxxxxx@xxxx-xxx.xxx If the vendor is awarded a contract with TIPS under this solicitation, the vendor agrees to make any Choice of Law clauses in any contract or agreement entered into between the awarded vendor and with a TIPS member entity to read as follows: "Choice of law shall be the laws of the state where the customer resides" or words to that effect.
Mileage Measurement Where required, the mileage measurement for LIS rate elements is determined in the same manner as the mileage measurement for V&H methodology as outlined in NECA Tariff No. 4.
Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by October 31, 2024.