Time for Installation Completion. (a) The Owner shall extend the Date for Installation Completion where the Solar System Installation have been delayed in reaching Installation Completion as a result of:
(i) a breach of the Contract or wilful acts or omissions by the Owner, its personnel or agents (Owner Breach);
(ii) inclement weather occurring at or around the Property; or
(iii) delays in stock procurement or other materials beyond the Retailer’s control.
(b) Delays due to an Owner Breach shall entitle the Retailer to reasonable delay costs payable within 10 business days of invoicing.
Time for Installation Completion. (a) The Owner shall extend the Date for Installation Completion where the System Installation has been delayed in reaching Installation Completion as a result of:
(i) a breach of the Contract or wilful acts or omissions by the Owner, its personnel or agents (Owner Breach);
(ii) inclement weather occurring at or around the Property; or
(iii) delays in stock procurement or other materials beyond SunEnergy’s control.
(b) Delays due to an Owner Breach shall entitle SunEnergy to reasonable delay costs payable within 5 business days of invoicing.