Traffic Control Plan, Detours, Sequence of Construction. The Engineer shall prepare Traffic Control Plans (TCP) including TCP typical sections, for the project. The Engineer shall complete Form 2229-Significant Project Procedures along with Page 4 of Form 1002, specifically titled Accelerated Construction Procedures. A detailed TCP must be developed in accordance with the latest edition of the TMUTCD. The Engineer shall implement the current Barricade and Construction (BC) standards and TCP standards as applicable. The Engineer shall interface and coordinate phases of work, including the TCP, with adjacent Engineers. The Engineer shall: 1. Provide a written narrative of the construction sequencing and work activities per phase and determine the existing and proposed traffic control devices (regulatory signs, warning signs, guide signs, route markers, construction pavement markings, barricades, flag personnel, temporary traffic signals, etc.) to be used to handle traffic during each construction sequence. The Engineer shall show proposed traffic control devices at grade intersections during each construction phase (stop signs, flagperson, signals, etc.). The Engineer shall show temporary roadways, ramps, structures (including railroad shoo-fly) and detours required to maintain lane continuity throughout the construction phasing. If temporary shoring is required, prepare layouts and show the limits on the applicable TCP. 2. Coordinate with the State in scheduling a Traffic Control Workshop and submittal of the TCP for approval by the Traffic Control Approval Team (TCAT). The Engineer shall assist the State in coordinating mitigation of impacts to adjacent schools, emergency vehicles, pedestrians, bicyclists and neighborhoods. 3. Develop each TCP to provide continuous, safe access to each adjacent property during all phases of construction and to preserve existing access. DocuSign Envelope ID: E73D9091-6C82-469F-B42B-3F0B45BB646B The Engineer shall notify the State in the event existing access must be eliminated, and must receive approval from the State prior to any elimination of existing access. 4. Design temporary drainage to replace existing drainage disturbed by construction activities or to drain detour pavement. The Engineer shall show horizontal and vertical location of culverts and required cross sectional area of culverts. 5. Prepare each TCP in coordination with the State. The TCP must include interim signing for every phase of construction. Interim signing must include regulatory, warning, construction, route, and guide signs. The Engineer shall interface and coordinate phases of work, including the TCP, with adjacent Engineers, which are responsible for the preparation of the PS&E for adjacent projects. 6. Maintain continuous access to abutting properties during all phases of the TCP. The Engineer shall develop a list of each abutting property along its alignment. The Engineer shall prepare exhibits for and attend meetings with the public, as requested by the State. 7. Make every effort to prevent detours and utility relocations from extending beyond the proposed Right-of-way lines. If it is necessary to obtain additional permanent or temporary easements and Right-of-Entry, the Engineer shall notify the State in writing of the need and justification for such action. The Engineer shall identify and coordinate with all utility companies for relocations required. 8. Describe the type of work to be performed for each phase of sequence of construction and any special instructions (e.g. storm drain, culverts, bridges, railing, illumination, signals, retaining walls, signing, paving surface sequencing or concrete placement, ROW restrictions, utilities, etc.) that the contractor should be made aware to include limits of construction, obliteration, and shifting or detouring of traffic prior to the proceeding phase. 9. Include the work limits, the location of channelizing devices, positive barrier, location and direction of traffic, work area, stations, pavement markings, and other information deemed necessary for each phase of construction. 10. Identify and delineate any outstanding ROW parcels. 11. Delineate areas of wetlands on traffic control plans. 12. At the request of the State, the TCP phasing shall be designed using Bentley’s OpenRoads 3D modeling technology.
Appears in 1 contract
Samples: Contract for Engineering Services
Traffic Control Plan, Detours, Sequence of Construction. The Engineer shall prepare Traffic Control Plans (TCP) including TCP typical sections, for the project. The Engineer shall complete Form 2229-Significant Project Procedures along with Page 4 of Form 1002, specifically titled Accelerated Construction Procedures. A detailed TCP must be developed in accordance with the latest edition of the TMUTCD. The Engineer shall implement the current Barricade and Construction (BC) standards and TCP standards as applicable. The Engineer shall interface and coordinate phases of work, including the TCP, with adjacent Engineers. The Engineer shall:
1. Provide a written narrative of the construction sequencing and work activities per phase and determine the existing and proposed traffic control devices (regulatory signs, warning signs, guide signs, route markers, construction pavement markings, barricades, flag personnel, temporary traffic signals, etc.) to be used to handle traffic during each construction sequence. The Engineer shall show proposed traffic control devices at grade intersections during each construction phase (stop signs, flagperson, signals, etc.). The Engineer shall show temporary roadways, ramps, structures (including railroad shoo-fly) structures, and detours required to maintain lane continuity throughout the construction phasing. If temporary shoring is required, prepare layouts and show the limits on the applicable TCP.
2. Coordinate with the State in scheduling a District Traffic Control Safety Review Team (DTSRT) Workshop and submittal of the TCP for approval by the Traffic Control Approval Team (TCAT)State. The Engineer shall assist the State in coordinating mitigation of DocuSign Envelope ID: 00030A7D-3D10-434B-B077-86515E98EAAF impacts to adjacent schools, emergency vehicles, pedestrians, bicyclists and neighborhoods.
3. Develop each TCP to provide continuous, safe access to each adjacent property during all phases of construction and to preserve existing access. DocuSign Envelope ID: E73D9091-6C82-469F-B42B-3F0B45BB646B The Engineer shall notify the State in the event existing access must be eliminated, and must receive approval from the State prior to any elimination of existing access.
4. Design temporary drainage to replace existing drainage disturbed by construction activities or to drain detour pavement. The Engineer shall show horizontal and vertical location of culverts and required cross sectional area of culverts.
5. Prepare each TCP in coordination with the State. The TCP must include interim signing for every phase of construction. Interim signing must include regulatory, warning, construction, route, and guide signs. The Engineer shall interface and coordinate phases of work, including the TCP, with adjacent Engineers, which are responsible for the preparation of the PS&E for adjacent projects.
6. Maintain continuous access to abutting properties during all phases of the TCP. The Engineer shall develop a list of each abutting property along its alignment. The Engineer shall prepare exhibits for and attend meetings with the public, as requested by the State.
7. Make every effort to prevent detours and utility relocations from extending beyond the proposed Right-of-way lines. If it is necessary to obtain additional permanent or temporary easements and Right-of-Entry, the Engineer shall notify the State in writing of the need and justification for such action. The Engineer shall identify and coordinate with all utility companies for relocations required.
8. Describe the type of work to be performed for each phase of sequence of construction and any special instructions (e.g. storm drain, culverts, bridges, railing, illumination, signals, retaining walls, signing, paving surface sequencing or concrete placement, ROW restrictions, utilities, etc.) that the contractor should be made aware to include limits of construction, obliteration, and shifting or detouring of traffic prior to the proceeding phase.
9. Include the work limits, the location of channelizing devices, positive barrier, location and direction of traffic, work area, stations, pavement markings, and other information deemed necessary for each phase of construction.
10. Identify and delineate any outstanding ROW parcels.
11. Delineate areas of wetlands (previously identified from the environmental study) on traffic control plans.
12. At the request of the State, the TCP phasing shall be designed using Bentley’s OpenRoads 3D modeling technology.. DocuSign Envelope ID: 00030A7D-3D10-434B-B077-86515E98EAAF
Appears in 1 contract
Samples: Contract for Engineering Services
Traffic Control Plan, Detours, Sequence of Construction. The Engineer shall prepare Traffic Control Plans (TCP) including TCP typical sections, for the project. The Engineer shall complete Form 2229-Significant Project Procedures along with Page 4 of Form 1002, specifically titled Accelerated Construction Procedures. A detailed TCP must be developed in accordance with the latest edition of the TMUTCD. The Engineer shall implement the current Barricade and Construction (BC) standards and TCP standards as applicable. The Engineer shall interface and coordinate phases of work, including the TCP, with adjacent Engineers. The Engineer shall:
1. Provide a written narrative of the construction sequencing and work activities per phase and determine the existing and proposed traffic control devices (regulatory signs, warning signs, guide signs, route markers, construction pavement markings, barricades, flag personnel, temporary traffic signals, etc.) to be used to handle traffic during each construction sequence. The Engineer shall show proposed traffic control devices at grade intersections during each construction phase (stop signs, flagpersonflag person, signals, etc.). The Engineer shall show temporary roadways, ramps, structures (including railroad shoo-fly) and detours required to maintain lane continuity throughout the construction phasing. If Where temporary shoring is required, prepare layouts per the direction of the State and show the limits on the applicable TCP.. If temporary roadways are required, prepare plan, profile and cross sections. DocuSign Envelope ID: 81F7252A-C4FA-4500-8C54-29C866EB3486
2. Coordinate with the State in scheduling a Traffic Control Workshop and submittal of the TCP for approval by the Traffic Control Approval Team (TCAT). The Engineer shall assist the State in coordinating mitigation of impacts to adjacent schools, emergency vehicles, pedestrians, bicyclists and neighborhoods.
3. Develop each TCP to provide continuous, safe access to each adjacent property during all phases of construction and to preserve existing access. DocuSign Envelope ID: E73D9091-6C82-469F-B42B-3F0B45BB646B The Engineer shall notify the State in the event existing access must be eliminated, and must receive approval from the State prior to any elimination of existing access.
4. Design temporary drainage to replace existing drainage disturbed by construction activities or to drain detour pavement. The Engineer shall show horizontal and vertical location of culverts and required cross sectional area of culverts.
5. Prepare each TCP in coordination with the State. The TCP must include interim signing for every phase of construction. Interim signing must include regulatory, warning, construction, route, and guide signs, and changeable message boards. The Engineer shall interface and coordinate phases of work, including the TCP, with adjacent Engineers, which are responsible for the preparation of the PS&E for adjacent projects.
6. Maintain continuous access to abutting properties during all phases of the TCP. The Engineer shall develop a list of each abutting property along its alignment. The Engineer shall prepare exhibits for and attend meetings with the public, as requested by the State.
7. Make every effort to prevent detours and utility relocations from extending beyond the proposed Right-of-way lines. If it is necessary to obtain additional permanent or temporary easements and Right-of-Entry, the Engineer shall notify the State in writing of the need and justification for such action. The Engineer shall identify and coordinate with all utility companies for relocations required.
8. Describe the type of work to be performed for each phase of sequence of construction and any special instructions (e.g. storm drain, culverts, bridges, railing, illumination, signals, retaining walls, signing, paving surface sequencing or concrete placement, ROW restrictions, utilities, etc.) that the contractor should be made aware to include limits of construction, obliteration, and shifting or detouring of traffic prior to the proceeding phase.. DocuSign Envelope ID: 81F7252A-C4FA-4500-8C54-29C866EB3486
9. Include the work limits, the location of channelizing devices, positive barrier, location and direction of traffic, work area, stations, pavement markings, and other information deemed necessary for each phase of construction.
10. Identify and delineate any outstanding ROW parcels.
11. Delineate areas of wetlands on traffic control plans.
12. At the request of the State, the TCP phasing shall be designed using Bentley’s OpenRoads 3D modeling technology.
Appears in 1 contract
Samples: Contract for Engineering Services
Traffic Control Plan, Detours, Sequence of Construction. The Engineer shall prepare Traffic Control Plans (TCP) including TCP typical sections, for the project. The Engineer shall is to complete Form 2229-Significant Project Procedures along with Page 4 of Form 1002, specifically titled Accelerated Construction Procedures. A detailed TCP must shall be developed in accordance with the latest edition of the TMUTCDTMUTCD (Oct 2014). The Engineer shall is to implement the current Barricade and Construction (BC) standards and TCP standards as applicable. The Engineer shall interface and coordinate phases of work, including the TCP, with adjacent Engineers.
1. The Engineer shall:
1. Provide shall provide a written narrative of the construction sequencing and work activities per phase and determine the existing and proposed traffic control devices (regulatory signs, warning signs, guide signs, route markers, construction pavement markings, barricades, flag personnel, temporary traffic signals, etc.) to be used to handle traffic during each construction sequence. The Engineer shall show proposed traffic control devices at grade intersections during each construction phase (stop signs, flagpersonflag person, signals, etc.). The Engineer shall show temporary roadways, ramps, structures (including railroad shoo-fly) and detours required to maintain lane continuity throughout the construction phasing. If temporary special shoring is required, prepare layouts and show the limits on the applicable TCP.
2. Coordinate with the State in scheduling a Traffic Control Workshop and submittal of the TCP for approval by the Traffic Control Approval Team (TCAT). The Engineer shall assist DocuSign Envelope ID: BB9CB9F4-FE9A-4C53-8095-241296FD342F the State in coordinating mitigation of impacts to adjacent schools, emergency vehicles, pedestrians, bicyclists and neighborhoods.
3. Develop each TCP to provide continuous, safe access to each adjacent property during all phases of construction and to preserve existing access. DocuSign Envelope ID: E73D9091-6C82-469F-B42B-3F0B45BB646B The Engineer shall notify the State in the event existing access must be eliminated, and must receive approval from the State prior to any elimination of existing access.
4. Design temporary drainage to replace existing drainage disturbed by construction activities or to drain detour pavement. The Engineer shall show horizontal and vertical location of culverts and required cross sectional area of culverts.
5. Prepare each TCP in coordination with the State. The TCP must shall include interim signing for every phase of construction. Interim signing must shall include regulatory, warning, construction, route, and guide signs. The Engineer shall interface and coordinate phases of work, including the TCP, with adjacent Engineers, which are responsible for the preparation of the PS&E for adjacent projects.
5. Provide detours and coordinate with local entities on off-system roadways TCP and closures.
6. Maintain continuous access to abutting properties during all phases of the TCP. The Engineer shall develop a list of each abutting property along its alignment. The Engineer shall prepare exhibits for and attend meetings with the public, as requested by the State.
7. Make every effort to prevent detours and utility relocations from extending beyond the proposed Right-of-way ROW lines. If it is necessary to obtain additional permanent or temporary easements and Right-of-Entry, the Engineer shall notify the State in writing of the need and justification for such action. The Engineer shall identify and coordinate provide coordination assistance with all utility companies for relocations required.
8. Describe the type of work to be performed for each phase of sequence of construction and any special instructions (e.g. storm drainsewer, culverts, bridges, railing, illumination, signals, temporary retaining walls, permanent retaining walls, signing, paving surface sequencing or concrete placement, ROW restrictions, utilities, etc.) that the contractor should be made aware to include limits of construction, obliteration, and shifting or detouring of traffic prior to the proceeding phase.
9. Include the work limits, the location of channelizing devices, positive barrier, location and direction of traffic, work area, stations, pavement markings, and other information deemed necessary for each phase of construction.
10. Identify The Engineer shall identify and delineate any outstanding ROW parcels.
11. Delineate areas Investigate utilization of wetlands on traffic control plansaccelerated bridge construction including self propelled modular transport.
12. At the request of the StatePrepare layouts for smart work zone for corridor, the TCP phasing shall be designed using Bentley’s OpenRoads 3D modeling technologyincluding portable ITS and queue end detection and prepare special specifications
13. Prepare construction timeline schedule utilizing Primavera P6 and prepare milestones.
Appears in 1 contract
Samples: Contract for Engineering Services