Transmission Losses. 7.1 IID shall determine, by transmission power flow analysis, the electrical losses (expressed as a percent amount of hourly scheduled energy deliveries) associated with the electrical output from each Plant. Such analysis shall be performed by IID at its sole expense. The initial percent amount, for each Plant, representing the electrical losses as determined herein shall be as specified in Exhibit[s] II, Transmission Service and in any subsequent Plant Amendments. 7.2 Unless otherwise agreed to by Producer's and IID's schedulers and dispatchers, IID shall reduce the amount of all hourly scheduled energy deliveries for Producer or Producer's account by the percent amount of such hourly deliveries for each Plant in accordance with Exhibit[s] II, Transmission Service and in any subsequent Plant Amendments. 7.3 If either Party believes that there has been a significant change in IID's electrical system and the electrical losses associated with any Plant should be redetermined, either Party's Authorized Representative may submit a written request to the other Party's Authorized Representative that the electrical losses be redetermined. Following such request, a transmission flow analysis shall be performed by IID as approved by the Authorized Representatives and paid for by the requesting Party. Whenever the percent amount for electrical losses is redetermined, such percent amount shall become effective as of the first day of the month following the date of such redetermination; provided, that such a redetermination may be no sooner than twelve (12) months after the most recent redetermination. Any redetermination of electrical losses made pursuant to this Section 7 shall be based on conditions in existence at the time of such redetermination. 7.4 Along with the monthly billing pursuant to Section 9.1, for the transmission service for each Plant, IID shall submit a monthly summary of hourly scheduled energy deliveries and of electrical losses for each Plant.
Appears in 2 contracts
Samples: Transmission Service Agreement (Ormat Technologies, Inc.), Transmission Service Agreement (Ormat Technologies, Inc.)
Transmission Losses. 7.1 IID shall determine, by transmission power flow analysis, the electrical losses (expressed as a percent amount of hourly scheduled energy deliveries) associated with the electrical output from each Plant. Such analysis shall be performed by IID at its sole expense. The initial percent amount, for each Plant, representing the electrical losses as determined herein shall be as specified in Exhibit[s] II, Transmission Service Exhibit II and in any subsequent Plant Amendments.
7.2 Unless otherwise agreed to by Producer's and IID's schedulers and dispatchers, IID shall reduce the amount of all hourly scheduled energy deliveries for Producer or Producer's account by the percent amount of such hourly deliveries for each Plant in accordance with Exhibit[s] II, Transmission Service Exhibit II and in any subsequent Plant Amendments.
7.3 If either Party believes that there has been a significant change in IID's electrical system and the electrical losses associated with any Plant should be redetermined, either Party's Authorized Representative may submit a written request to the other Party's Authorized Representative that the electrical losses be redetermined. Following such request, a transmission flow analysis shall be performed by IID as approved by the Authorized Representatives and paid for by the requesting Party. Whenever the percent amount for electrical losses is redetermined, such percent amount shall become effective as of the first day of the month following the date of such redetermination; provided, that such a redetermination may be no sooner than twelve (12) months after the most recent redetermination. Any My redetermination of electrical losses made pursuant to this Section 7 shall be based on conditions in existence at the time of such redetermination.
7.4 Along with the monthly billing pursuant to Section 9.1, for the transmission service for each Plant, IID shall submit a monthly summary of hourly scheduled energy deliveries and of electrical losses for each Plant.
Appears in 2 contracts
Samples: Transmission Service Agreement (Ormat Technologies, Inc.), Transmission Service Agreement (Ormat Technologies, Inc.)
Transmission Losses. 7.1 IID shall determine, by transmission power flow analysis, the electrical losses (expressed as a percent amount of hourly scheduled energy deliveries) associated with the electrical output from each Plant. Such analysis shall be performed by IID at its sole expense. The initial percent amount, for each Plant, representing the electrical losses as determined herein shall be as specified in Exhibit[s] Exhibit(s) II, Transmission Service and in any subsequent Plant Amendments.
7.2 Unless otherwise agreed to by Producer's and IID's schedulers and dispatchers, IID shall reduce the amount of all hourly scheduled energy deliveries for Producer or Producer's account by the percent amount of such hourly deliveries for each Plant in accordance with Exhibit[s] Exhibit(s) II, Transmission Service and in any subsequent Plant Amendments.
7.3 If either Party believes that there has been a significant change in IID's electrical system and the electrical losses associated with any Plant should be redetermined, either Party's Authorized Representative may submit a written request to the other Party's Authorized Representative that the electrical losses be redetermined. Following such request, a transmission flow analysis shall be performed by IID as approved by the Authorized Representatives and paid for by the requesting Party. Whenever the percent amount for electrical losses is redetermined, such percent amount shall become effective as of the first day of the month following the date of such redetermination; provided, that such a redetermination may be no sooner than twelve (12) months after the most recent redetermination. Any redetermination of electrical losses made pursuant to this Section 7 shall be based on conditions in existence at the time of such redetermination.
7.4 Along with the monthly billing pursuant to Section 9.1, for the transmission service for each Plant, IID shall submit a monthly summary of hourly scheduled energy deliveries and of electrical losses for each Plant.
Appears in 2 contracts
Samples: Transmission Service Agreement (Ormat Technologies, Inc.), Transmission Service Agreement (Ormat Technologies, Inc.)
Transmission Losses. 7.1 IID shall determine, by transmission power flow analysis, the electrical losses (expressed as a percent amount of hourly scheduled energy deliveries) associated with the electrical output from each Plant. Such analysis shall may be performed by IID IID, at its sole expense, and as deemed necessary by changing conditions on IID's electrical system. The initial percent amount, for each Plant, representing the electrical losses as determined herein shall be as specified in Exhibit[s] Exhibits II, Transmission Service III, IV, V, VI, VII, VIII and in any subsequent Plant AmendmentsAmendment(s).
7.2 Unless otherwise agreed to by ProducerEdison's and IID's schedulers and dispatchers, IID shall reduce the amount of all hourly scheduled energy deliveries to Edison or for Producer or ProducerEdison's account by the percent amount of such hourly deliveries for each Plant in accordance with Exhibit[s] Exhibits II, Transmission Service III, IV, V, VI, VII, VIII and in any subsequent Plant AmendmentsAmendment(s) plus a transformer loss percent amount if delivered at the Mirage Substation 115/92 kV switchrack.
7.3 If It either Party believes that there has been a significant change in IID's electrical system and the electrical losses associated with any Plant should be redetermined, either Party's Authorized Representative may submit a written request to ________ the other Party's Authorized Representative that the electrical losses be redetermined. Following such request, a transmission flow analysis shall may be performed by IID as approved by the Authorized Representatives and paid for by the requesting Party. Whenever If the percent amount for electrical losses is redetermined, such percent amount shall become effective as of the first day of the month following the date of such redetermination; provided, that such a redetermination may be no sooner than twelve (12) months after the most recent redetermination. Any redetermination of electrical losses made pursuant to this Section 7 shall be based on conditions in existence at the time of such redetermination.
7.4 Along with the monthly billing pursuant to Section 9.1, for the transmission service for each Plant, IID shall submit a monthly summary of hourly scheduled energy deliveries and of electrical losses for each Plant.
Appears in 2 contracts
Samples: Transmission Service Agreement (Ormat Technologies, Inc.), Transmission Service Agreement (Ormat Technologies, Inc.)
Transmission Losses. 7.1 IID shall determine, by transmission power flow analysis, the electrical losses (expressed as a percent amount of hourly scheduled energy deliveries) associated with the electrical output from each Plantthe Plants. Such analysis shall be performed by IID at its sole expense. The initial percent amount, for each Plant, representing the electrical losses as determined herein shall be as specified in Exhibit[s] Exhibit(s) II, Transmission Service and in any subsequent Plant Amendments.
7.2 Unless otherwise agreed to by Producer's and IID's schedulers and dispatchers, IID shall reduce the amount of all hourly scheduled energy deliveries for Producer or Producer's account by the percent amount of such hourly deliveries for each Plant in accordance with Exhibit[s] II, Transmission Service and in any subsequent Plant Amendments.
7.3 If either Party believes that there has been a significant change in IID's electrical system and the electrical losses associated with any Plant should be redetermined, either Party's Authorized Representative may submit a written request to the other Party's Authorized Representative that the electrical losses be redetermined. Following such request, a transmission flow analysis shall be performed by IID as approved by the Authorized Representatives and paid for by the requesting Party. Whenever the percent amount for electrical losses is redetermined, such percent amount shall become effective as of the first day of the month following the date of such redetermination; provided, that such a redetermination may be no sooner than twelve (12) months after the most recent redetermination. Any redetermination of electrical losses made pursuant to this Section 7 shall be based on conditions in existence at the time of such redetermination.
7.4 Along with the monthly billing pursuant to Section 9.1, for the transmission service for each Plant, IID shall submit a monthly summary of hourly scheduled energy deliveries and of electrical losses for each Plant.
Appears in 2 contracts
Samples: Transmission Service Agreement (Ormat Technologies, Inc.), Transmission Service Agreement (Ormat Technologies, Inc.)