Common use of Unforeseeable difficulties Clause in Contracts

Unforeseeable difficulties. Except as otherwise stated in the Agreement: (a) the Contractor accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Works; (b) the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs; and (c) the Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.

Appears in 129 contracts

Samples: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement, Construction Contract

AutoNDA by SimpleDocs

Unforeseeable difficulties. Except as otherwise stated in the Agreement: (a) the The Contractor accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Works; (b) the The Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs; and (c) the The Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.

Appears in 11 contracts

Samples: Construction Contract, Epc Agreement, Epc Agreement

Unforeseeable difficulties. Except as otherwise stated in the Agreement: (a) : the Contractor accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Works; (b) ; the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs; and (c) and the Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.

Appears in 6 contracts

Samples: Construction Contract, Contract Agreement, Contract Agreement

Unforeseeable difficulties. Except as otherwise stated in the Agreement: (a) : the Contractor accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Works; (b) ; the Contract Price shall not be adjusted to take account of any unforeseen difficulties unforeseendifficulties or costs; and (c) and the Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.

Appears in 5 contracts

Samples: Construction Contract, Contract Agreement, Construction Contract

Unforeseeable difficulties. Except as otherwise stated Stated in the Agreement: (a) the Contractor accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Works; (b) the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs; and (c) the Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.

Appears in 2 contracts

Samples: Construction Contract, Construction Contract

Unforeseeable difficulties. Except as otherwise stated in the Agreement: (a) 4.8.1 the Contractor accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Works; (b) 4.8.2 the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs; and (c) 4.8.3 the Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.

Appears in 1 contract

Samples: Contract Agreement

Unforeseeable difficulties. β€Œ Except as otherwise stated in the Agreement: (a) the The Contractor accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Works; (b) the The Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs; and (c) the The Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.

Appears in 1 contract

Samples: Demonstration Agreement

Unforeseeable difficulties. Except as otherwise stated in the Agreement: (a) the Contractor accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Works; (b) the Contract Price shall not be adjusted to take account of any unforeseen difficulties diffi- culties or costs; and (c) the Scheduled Completion Date shall not be adjusted to take account of any unforeseen un- foreseen difficulties or costs.

Appears in 1 contract

Samples: Construction Contract

Unforeseeable difficulties. Except as otherwise stated in the Agreement: (a) the Contractor accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Works; (b) the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs; and (c) the Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.

Appears in 1 contract

Samples: Engineering Procurement and Construction (Epc) Agreement

AutoNDA by SimpleDocs

Unforeseeable difficulties. Except as otherwise stated in the Agreement: (a) a. the Contractor accepts complete total responsibility for having foreseen all difficulties and costs of successfully completing the Works;; and (b) b. the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs; and (c) the Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.

Appears in 1 contract

Samples: Epc Agreement

Unforeseeable difficulties. Except as otherwise stated in the Agreement: (a) the Contractor Concessionaire accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Construction Works; (b) the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs; and (cb) the Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.

Appears in 1 contract

Samples: Concession Agreement

Unforeseeable difficulties. Except as otherwise stated in the Agreement: (a) the Contractor accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Works; (b) the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs; and (cd) the The Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.

Appears in 1 contract

Samples: Engineering Procurement and Construction Agreement

Unforeseeable difficulties. Except as otherwise stated in the Agreement: (a) the Contractor accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Works; (b) the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs; and (c) the Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.. Page 38 of 149

Appears in 1 contract

Samples: Contract Agreement

Unforeseeable difficulties. Except as otherwise stated specified in the Agreement: (a) the Contractor accepts complete responsibility for having foreseen all difficulties and costs of successfully completing the Works; (b) the Contract Price shall not be adjusted to take account of any unforeseen difficulties or costs; and (c) the Scheduled Completion Date shall not be adjusted to take account of any unforeseen difficulties or costs.

Appears in 1 contract

Samples: Epc Agreement