Uninterrupted Access and Use. The Province covenants that the Contractor’s access to and use of the Lands pursuant to Section 4.1 shall be uninterrupted during the duration of this Agreement, shall be without any disturbance or interference from the Province or any person claiming from or under the Province, and shall be adequate to enable the Contractor to carry out the Project throughout the Construction Period and to carry out the O&M throughout the Operating Period, in each case subject to the following:
Appears in 2 contracts
Samples: www.transportation.alberta.ca, www.transportation.alberta.ca
Uninterrupted Access and Use. The Province covenants that the Contractor’s access to and use of the Lands pursuant to Section 4.1 (Access and Use) shall be uninterrupted during the duration of this Agreement, shall be without any disturbance or interference from the Province or any person claiming from or under the Province, and shall be adequate to enable the Contractor to carry out the Project throughout the Construction Period and to carry out the O&M throughout the Operating Period, in each case subject to the following:
Appears in 1 contract
Samples: www.transportation.alberta.ca
Uninterrupted Access and Use. The Province covenants that the Contractor’s access to and use of the Lands pursuant to Section 4.1 shall be uninterrupted during the duration of this Agreement, shall be without any disturbance or interference from the Province or any person claiming from or under the Province, and shall be adequate to enable the Contractor to carry out the Project throughout the Construction Period and to carry out the O&M O&M, as applicable, throughout the Construction Period and the Operating Period, in each case subject to the following:
Appears in 1 contract
Samples: CNR Vegreville Agreement
Uninterrupted Access and Use. The Province covenants that the Contractor’s access to and use of the Lands pursuant to Section 4.1 shall be uninterrupted during the duration of this Agreement, shall be without any disturbance or interference from the Province or any person claiming from or under the Province, and shall be adequate to enable the Contractor to carry out the Project throughout the Construction Period and to carry out the O&M O&M, as applicable, throughout the Construction Period and the Operating Period, in each case subject to the following:
Appears in 1 contract
Samples: www.transportation.alberta.ca