Water Supply System. Water Supply and its Charges a) Necessary Water infrastructure system to bring the water at Solar Park shall be arranged by GPCL. b) GPCL will arrange and provide the necessary water supply for operations and maintenance of the Solar Power Plant from the SCOD. c) GPCL has entered into contract with DSIRA/DICDL to off-take necessary water. Supply ot water shall be governed as per the contract between GPCL and DICDL d) Initially the water charges shall be paid / or to be paid by GPCL e) Such payment would be charged SPD along with administrative charges on pro- rata basis either MW or water quantity declared by SPD or water used as the case may be. f) Water supply charges are over and above ( exclusive) O & M Charges levided by GPCL g) It is proposed to supply 4 KL/MW/Cycle so as to complete one cleaning cycle every week. However the supply of water shall be dependent upon the availability of water. h) GPCL will provide water at a single source through a meter for each plot. SPD shall collect the water supplied by GPCL in a ground level water tank and water from this tank shall be used by SPD by making its own arrangements as required. i) However, GPCL shall not provide water supply during the construction phase. The SPD is advised to make its own arrangements for obtaining water during construction. SPD has to obtain necessary approvals/permissions from local authorities to dig bore xxxxx or to get water from nearest reservoir by tankers and GPCL will extend necessary support in obtaining such approvals/permissions, if required.
Appears in 2 contracts
Samples: Implementation and Support Agreement, Implementation and Support Agreement
Water Supply System. Water Supply and its Charges
a) Necessary Water infrastructure system to bring the water at Solar Park shall be arranged by GPCL.
b) GPCL will arrange and provide the necessary water supply for operations and maintenance of the Solar Power Plant from the SCOD.
c) GPCL has entered into contract with DSIRA/DICDL SSNNL to off-take necessary waterwater from Narmada Main Canal. Supply ot water shall be governed as per the contract between GPCL and DICDLSSNNL
d) Initially the water charges shall be paid / or to be paid by GPCL
e) Such payment would be charged SPD along with administrative charges on pro- rata basis either MW or water quantity declared by SPD or water used as the case may be.
f) Water supply charges are over and above ( exclusive) O & M Charges levided levied by GPCL
g) It is proposed to supply maximum 4 KL/MW/Cycle so as to complete one cleaning cycle every week. However the supply of water shall be dependent upon the availability of water.
h) The park is developed in water scarce area, SPD and SPIA should endeavour to utilize less water and maximize its effort to conserve water.
i) GPCL will provide water at a single source through a meter for each plot. SPD shall collect the water supplied by GPCL in a ground level water tank and water from this tank shall be used by SPD by making its own arrangements as required.
ij) However, GPCL shall not provide water supply during the construction phase. The SPD is advised to make its own arrangements for obtaining water during construction. SPD has to obtain necessary approvals/permissions from local authorities to dig bore xxxxx or to get water from nearest reservoir by tankers and GPCL will extend necessary support in obtaining such approvals/permissions, if required.
Appears in 2 contracts
Samples: Implementation and Support Agreement, Implementation and Support Agreement
Water Supply System. Water Supply and its Charges
a) Necessary Water infrastructure system to bring the water at one point of Solar Park shall be arranged by GPCLGIPCL.
b) GPCL GIPCL will arrange and provide the necessary water supply for operations and maintenance of the Solar Power Plant from the SCOD.Plant
c) GPCL has entered into contract with DSIRA/DICDL GIPCL shall develop brackish water desalination plant for supply of water up to off-take necessary waterofftake point. Supply ot of water shall be governed as per the contract between GPCL GIPCL and DICDLSPD.
d) Initially the Payment towards water charges shall be paid / or to be paid by GPCL
e) Such payment would be charged to SPD along with administrative charges on pro- rata basis either based on MW or water quantity declared by SPD or water used as the case may be.
fe) Water supply charges are over and above ( exclusive) O & M Charges levided levied by GPCLGIPCL
gf) It is proposed to supply 4 maximum 6 KL/MW/Cycle so as to complete one three cleaning cycle every weekmonth. However the supply of water shall be dependent upon the availability of water. In view of special geographical conditions of the park, Solar project developers shall preferably provide Dry Cleaning System for the solar module cleaning.
g) The park is developed in water scarce area, SPD and SPPD should endeavor to utilize less water and maximize its effort to conserve water.
h) GPCL GIPCL will provide water at a single source source/off take point through a meter for each plot. SPD shall collect the water supplied by GPCL GIPCL in a ground level water tank and water from this tank shall be used by SPD by making its own arrangements as required.
i) However, GPCL GIPCL shall not provide water supply during the construction phase. The SPD is advised to make its own arrangements for obtaining water during construction. SPD has to obtain necessary approvals/permissions from local authorities to dig bore xxxxx or to get water from nearest reservoir by tankers and GPCL will extend necessary support in obtaining such approvals/permissions, if requiredreservoir.
Appears in 1 contract
Samples: Implementation and Support Agreement
Water Supply System. Water Supply and its Charges
a) Necessary Water infrastructure system to bring the water at Solar Park shall be arranged by GPCL.
b) GPCL will arrange and provide the necessary water supply for operations and maintenance of the Solar Power Plant from the SCOD.
c) GPCL has entered into contract with DSIRA/DICDL to off-take necessary water. Supply ot water shall be governed as per the contract between GPCL and DICDL
d) Initially the water charges shall be paid / or to be paid by GPCL
e) Such payment would be charged SPD along with administrative charges on pro- rata basis either MW or water quantity declared by SPD or water used as the case may be.
f) Water supply charges are over and above ( exclusive) O & M Charges levided levied by GPCL
g) It is proposed to supply 4 KL4KL/MW/Cycle so as to complete one cleaning cycle every week. However the supply of water shall be dependent upon the availability of water. Cost for arrangement of supply in case of shortfall has to be borne by SPD (Project Developer).
h) GPCL will provide water at a single source through a meter for each plotat one location of Solar Park. SPD shall collect the water supplied by GPCL in a ground level water tank and water from this tank shall be used by SPD by making transfer up to its own arrangements as requiredplot thorough its own pipe line. SPD has to bear the cost of this pipeline and own water supply system.
i) However, GPCL shall not provide water supply during the construction phase. The SPD is advised to make its own arrangements for obtaining water during construction. SPD has to obtain necessary approvals/permissions from local authorities to dig bore xxxxx or to get water from nearest reservoir by tankers and GPCL will extend necessary support in obtaining such approvals/permissions, if required.
Appears in 1 contract
Samples: Implementation and Support Agreement
Water Supply System. Water Supply and its Charges
a) Necessary Water infrastructure system to bring the water at Solar Park shall be arranged by GPCL.
b) GPCL will arrange and provide the necessary water supply for operations and maintenance of the Solar Power Plant from the SCOD.
c) GPCL has entered into contract with DSIRA/DICDL to off-take necessary water. Supply ot water shall be governed as per the contract between GPCL and DICDL
d) Initially the water charges shall be paid / or to be paid by GPCL
e) Such payment would be charged SPD along with administrative charges on pro- rata basis either MW or water quantity declared by SPD or water used as the case may be.
f) Water supply charges are over and above ( exclusive) O & M Charges levided levied by GPCL
g) It is proposed to supply 4 KL/MW/Cycle so as to complete one cleaning cycle every week. However the supply of water shall be dependent upon the availability of water.
h) GPCL will provide water at a single source through a meter for each plot. SPD shall collect the water supplied by GPCL in a ground level water tank and water from this tank shall be used by SPD by making its own arrangements as required.
i) However, GPCL shall not provide water supply during the construction phase. The SPD is advised to make its own arrangements for obtaining water during construction. SPD has to obtain necessary approvals/permissions from local authorities to dig bore xxxxx or to get water from nearest reservoir by tankers and GPCL will extend necessary support in obtaining such approvals/permissions, if required.
Appears in 1 contract
Samples: Implementation and Support Agreement
Water Supply System. Water Supply and its Charges
a) Necessary Water infrastructure system to bring the water at Solar Park shall be arranged by GPCL.
b) GPCL will arrange and provide the necessary water supply for operations and maintenance of the Solar Power Plant from the SCOD.
c) GPCL has entered into contract with DSIRA/DICDL SSNNL to off-take necessary waterwater from Narmada Main Canal. Supply ot water shall be governed as per the contract between GPCL and DICDLSSNNL
d) Initially the water charges shall be paid / or to be paid by GPCL
e) Such payment would be charged SPD along with administrative charges on pro- rata basis either MW or water quantity declared by SPD or water used as the case may be.
f) Water supply charges are over and above ( exclusive) O & M Charges levided levied by GPCL
g) It is proposed to supply 4 KLmaximum 4KL/MW/Cycle so as to complete one cleaning cycle every week. However the supply of water shall be dependent upon the availability of water.
h) The park is developed in water scarce area, SPD and SPIA should endeavour to utilize less water and maximize its effort to conserve water.
i) GPCL will provide water at a single source through a meter for each plot. SPD shall collect the water supplied by GPCL in a ground level water tank and water from this tank shall be used by SPD by making its own arrangements as required.
ij) However, GPCL shall GPCLshall not provide water supply during the construction phase. The SPD is advised to make its own arrangements for obtaining water during construction. SPD has to obtain necessary approvals/permissions from local authorities to dig bore xxxxx or digbore wellsor to get water from nearest reservoir by tankers and GPCL will GPCLwill extend necessary support in obtaining such approvals/permissions, if required.
Appears in 1 contract
Samples: Implementation and Support Agreement