Examples of Facility Capacity Rating in a sentence
In the event of an unscheduled outage or curtailment exceeding twenty-five (25) percent of the Facility Capacity Rating (other than curtailments due to lack of motive force), Seller immediately shall notify PacifiCorp of the necessity of such unscheduled outage or curtailment, the time when such has occurred or will occur and the anticipated duration.
Seller shall be responsible for ensuring that any planned increase in the Facility Capacity Rating or the maximum instantaneous capacity of the Facility complies with Seller’s Generation Interconnection Agreement and any other agreements with PacifiCorp.
In the case of substantial upgrades, PacifiCorp may require Seller to comply with Section 3.2.8(e) (in the event that the Facility upgrade causes the Facility Capacity Rating to exceed 3,000 kW) and increase its Minimum Annual Delivery obligation in Section 4.3 (if appropriate).
If Seller’s Facility has a Facility Capacity Rating of 100 kW or less, Seller’s failure to satisfy the minimum delivery obligation of Section 4.3 for two (2) consecutive years; else Seller’s failure to satisfy the minimum delivery obligation of Section 4.3 for one year.
If Seller increases the Facility Capacity Rating above 3,000 kW for solar or 10,000 kW for all other resource types, then (on a going forward basis) PacifiCorp shall pay Seller the Contract Price for the fraction of total Net Output equal to 10,000 kW divided by the Facility Capacity Rating of the upgraded Facility.
So long as the Facility Capacity Rating after the upgrade is 3,000 kW or less for solar or 10,000 kW or less for all other resource types, Seller will continue to receive the Contract Price for the Net Output, as set forth in Sections 5.1, 5.2, and 5.3 of this Agreement.
If Seller increases the Facility Capacity Rating above 10,000 kW, then (on a going forward basis) PacifiCorp shall pay Seller the Contract Price for the fraction of total Net Output equal to 10,000 kW divided by the Facility Capacity Rating of the upgraded Facility.
So long as the Facility Capacity Rating after the upgrade is 10,000 kW or less, Seller will continue to receive the Contract Price for the Net Output, as set forth in Sections 5.1 and 5.2 of this Agreement.
In the event of an unscheduled outage or curtailment exceeding twenty-five (25) percent of the Facility Capacity Rating (other than curtailments due to lack of motive force) expected to last more than 48 hours, Seller reasonably shall notify PacifiCorp of the unscheduled outage or curtailment, the time when such has occurred or will occur, and the anticipated duration.
PacifiCorp shall designate the Facility as a Network Resource under Section 30.2 of the Tariff and take all action during the Term necessary on PacifiCorp’s part to obtain Network Integration Transmission Service under the Tariff for the full amount of the Expected Facility Capacity Rating.