Examples of Line Facilities in a sentence
The cost to Owner of the #High Line# Facilities Work shall not exceed $1,150,000.
In some Stations, generally the larger ones, certain Bid Areas may consist of several different Work Areas (i.e.: Line, Facilities, Terminal, Hanger, Test Cell, Stalls, WC324, etc.) In these instances all employees will have the option to bid, by seniority, into different work areas within the same Bid Area during each local Shift Bid.
All Transmission Line Facilities shall be designed to withstand the independent load cases defined in Sections 3.2.1.1 through 3.2.1.7. The effects of gravity, wind, ice, wire tension, construction, and maintenance loads shall be included as applicable.
Transmission Line Facilities shall be designed to resist the wind loads corresponding to a 100 year return period (RP) as defined in the latest edition of ASCE Manual of Practice (MOP) 74.Wind pressures shall be calculated in accordance with the procedures of the latest edition of ASCE MOP 74, properly adjusted for structure shape, gust, and height.
The Ingress/Egress Easement is granted for the express and sole purpose of allowing Grantee to perpetually use the property within the Ingress/Egress Easement to reasonably access its Water Line Facilities contained within the Water Line Easement for the purposes provided therein.
Transmission Line Facilities shall be designed to resist ice loads resulting from freezing rain, snow, and in- cloud icing as defined in below.In each case, the weight of ice shall be considered 57 pounds per cubic foot, the temperature 0°F, and the wind speed 0 mph.
Transmission Line Facilities shall be designed to resist the loading conditions defined in Rules 250B, 250C, and 250D of the NESC.
Transmission Line Facilities shall have sufficient strength to resist the individual and cumulative effects of all load cases defined in Section 3.2.1, including all subsections.
Where Transmission Line Facilities terminate in substations owned by others, the Designated Entity shall coordinate with these owners to ensure adequate strength is provided for each station line terminal structure.
The applied loads shall be adjusted by the Load Factors defined in the subsections of Section 3.2.1, and the material strengths shall be adjusted by the material strength reduction factors specified by the applicable governing industry publications referenced in Section 3.2.2.Transmission Line Facilities include all supporting structures, conductors and other wires, insulators, hardware, and foundations.