There shall be no Grouping of activities, and the global Filter for Longest Path shall be applied.
Critical Paths shall be highlighted and Total Float shall be shown for all activities.A second time-scaled bar chart shall also be prepared containing only the Critical Path or, if the Critical Path is not the longest path, the Longest Path using a scale that yields readable plots and that meets the requirements of Subsection 722.61 - Schedule Content and Preparation Requirements.
The Weekly Status Report shall be generated using the activity Layout named Weekly Status Report, with activities grouped by the WBS, and using the standard default filter named Longest Path.
Failure to have a clearly defined Critical Path from the Data Date to the last activity in the schedule, using the Longest Path method.
Failure to have a clearly defined Critical Path from the Data date to the last activity in the schedule, using the Longest Path method.
Set Schedule Option for defining Critical Activities to "Longest Path".
Longest Path: The longest continuous path of activities through a project, which controls project early completion.
Calculation Settings – Default settings must be used, except that Critical activities must be defined as Longest Path activities.
The Longest Path is the Path through a Project network from start to finish where the total duration is longer than any other path.
The Longest Path is determined by the string of activities, relationships that push the Project to its latest early finish dates.