New Transmission Facilities definition
Examples of New Transmission Facilities in a sentence
Seller acknowledges that Buyer will receive such notice solely for information purposes, and Buyer shall have no responsibility or liability for the development, construction, operation or maintenance of the Hydro-Québec Power Resources or any Transmission System or New Transmission Facilities.
The Parties acknowledge that, throughout the Term, U.S. Transmission Provider and TransÉnergie shall coordinate all planned maintenance for the New Transmission Facilities with ISO-NE, consistent with ISO-NE Rules, and shall promptly provide applicable information concerning scheduled outages, as determined by ISO-NE, to Buyer.
Applied updates to further standardize the “Allocation Adjustment for New Transmission Facilities and/or Designated Network Resources” process.
Changes have been made to Appendix F – FERC Dispute Resolution and Appendix G – Allocation Adjustments for New Transmission Facilities and/or Designated Network Resources.
Seller acknowledges that Buyer will receive such notice solely to monitor progress toward the Commercial Operation Datefor information purposes, and Buyer shall have no responsibility or liability for the development, construction, operation or maintenance of the FacilityHydro-Québec Power Resources or any Transmission System or New Transmission Facilities.
The Generator shall ensure that the New Transmission Facilities and the Facility Switchyard shall be ready for energizing on or before the Scheduled Energizing Date, and that the First Unit and Second Unit shall be ready for Dispatch on or before their respective Scheduled Commercial Operation Dates.
The initial inspection and testing of the NTF Connection Point and the New Transmission Facilities shall be scheduled for a date agreed by the Parties which shall be not more than seven (7) days after EGAT's receipt of such statement.
EGAT shall energize the NTF Connection Point on or before the Scheduled NTF Energizing Date for testing and commissioning of the New Transmission Facilities and the Facility Switchyard, and to enable Dispatch of the First Unit and Second Unit on or before their respective Scheduled Commercial Operation Dates.
The PTO may enter into appropriate contracts to fulfill any obligations associated with the ownership and construction of such New Transmission Facilities or Transmission Upgrades.
EGAT shall allow the Generator, as EGAT's agent, to exercise all uses of the Access Rights that are required for the Generator's design, engineering, construction, testing, and commissioning of the New Transmission Facilities.