Outside Commercial Operation Date definition

Outside Commercial Operation Date means the date that is 18 Months after the Target Commercial Operation Date.
Outside Commercial Operation Date means the later of (i) 60 days after the Construction Commencement Date, or (ii) 180 days after the Effective Date.
Outside Commercial Operation Date means the later of one-hundred eighty (180) days from the Effective Date or one-hundred eighty (180) days after Developer receives notification from DOER that DOER has issued a final Statement of Qualifications approving the developer’s enrollment in the SMART Program.

Examples of Outside Commercial Operation Date in a sentence

  • Lessee’s obligations under Section 4(a) are conditioned on the occurrence of the Commercial Operation Date for the System by the Outside Commercial Operation Date.

  • Purchaser’s obligations under Section 4(a) are conditioned on the occurrence of the Commercial Operation Date for the System by the Outside Commercial Operation Date.

  • Purchaser’s obligations under Section 5.a are conditioned on the occurrence of the Commercial Operation Date for the System by the Outside Commercial Operation Date.

  • Seller fails to achieve Commercial Operation on or before the Outside Commercial Operation Date.

  • Any Buyer may, in its sole discretion and without penalty to such Buyer, withdraw from this Agreement, and Buyers may collectively, in their sole discretion and without penalty to Buyers, terminate this Agreement, in either case, effective upon notice to Seller, if Seller fails to achieve the Commercial Operation Date on or before the Outside Commercial Operation Date, except as set forth in Section 3.3.


More Definitions of Outside Commercial Operation Date

Outside Commercial Operation Date means May 1, 2027, as such date may be extended pursuant to Section 2.5(c).
Outside Commercial Operation Date means three hundred sixty five (365) days after the Construction Commencement Date.
Outside Commercial Operation Date means the date that is [______] Months after the Target Commercial Operation Date.
Outside Commercial Operation Date means one hundred eighty (180) days after the Outside Construction Commencement Date.
Outside Commercial Operation Date means fourteen (14) months from the Effective Date for a roof mounted PV System and eighteen (18) months from the Effective Date for a ground mounted PV System.
Outside Commercial Operation Date means the Outside Commercial Operation Date set forth in the Milestone Schedule set forth in Exhibit F. In no event shall this date be later than two years following the Effective Date.
Outside Commercial Operation Date in Section 1 of the Agreement is hereby replaced with the following