Examples of Plus GST in a sentence
However, under GST regime, IGST Plus GST compensation cess (if applicable) would be leviable on such imports.
After the completion of the entire job including clearance of the site to the entire satisfaction of the Engineer-in-charge, final bill shall be submitted for verifications by Engineer-in charge.In case the contractor fails to submit the bill by the last day of the following month, a penalty of 1% of the billed amount for every month of delay or part thereof subject to minimum of Rs.1000.00 Plus GST as applicable shall be recovered from the bill.
However, under GST regime, IGST Plus GST compensation cess (if applicable) would be liveable on such imports.
Supplier shall, therefore, be liable to pay ground rent @ 0.1% (Plus GST as may be applicable) per day of purchase cost of the material to be lifted from the date of intimation of rejection till the actual date of lifting.
Any delay that may take place in erection and commissioning activities beyond contractual out of date shall be subject to penalty at the rate of 2% of the contract value (of delayed materials/works) per month or part thereof subject to a maximum of 10% of total contract value, Plus GST as applicable.
Any delay that may take place in erection and commissioning activities beyond contractual out of date shall be subject to penalty at the rate of 2% of the contract value (of delayed materials/works) per month or part thereof subject to a maximum of 10% of total contract value, Plus GST as applicable.Bidders shall have to furnish relevant documents for payment of GST as applicable along with each RA.Bill.
Any delay that may take place in supply and erection beyond Contractual cut off date stated as per stipulated delivery period shall be subject to the penalty at the rate of ½ % of the value of work (Plus GST as applicable) executed after due date of completion per week with a ceiling of 10 % of the total contract value (Plus GST as applicable).
Sr.NoAmount of contract in Rupees.Penalty amount in Rupees.1Up- to 1 Lac.5000.00 Plus GST as applicable2Above 1 Lac to 10 Lacs.25000.00 Plus GST as applicable3Above 10 Lacs.
In case the contractor fails to submit the bill by the last day of the following month, a penalty of 1% of the billed amount for every month of delay or part thereof subject to minimum of Rs.1000.00 Plus GST as applicable shall be recovered from the bill.
However, under GST regime, IGST Plus GST compensation cess (if applicable) would be leyiable on such imports.