Restrictions on Change of Scope Sample Clauses

Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
AutoNDA by SimpleDocs
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Page 83 of 146 Border including Dawki Bridge from (Design km 63+530 to km 71+520) design length of 7.99 km in the State of Meghalaya for execution on EPC mode under JICA funding - (Package-V)-Balance Work (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. Draft Contract AgreementPage 84 of 261 S-D Tunnel 2022 (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
Restrictions on Change of Scope. 11.4.1 No Change of Scope shall be executed unless the RSCL has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. 11.4.2 Change made because of any default of the Contractor in the performance of its obligations under this Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. Rangagara to Kaliabor Tiniali of NH-37 (Old) from Km 297+000 to Km 315+315 (18.315 Km), under SARDP-NE, under EPC Mode at the Risk and Cost of EPC Contractor-2nd Call (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligationsunderthisAgreement,thesameshallnotbedeemedtobeChangeofScope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. 13.4.1 No Change of Scope shall be executed unless the Authority/GMDA has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. 13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10 (ten) per cent of the Contract Price. 13.4.3 Notwithstanding anything to the contrary in this Article 13, no change made necessary because of any default of the Contractor in the performance of its obligations under this Agreement shall be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
AutoNDA by SimpleDocs
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of km) in the state of Manipur – 2nd call September 2020 the Contract Price. (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. (Design Chainage 50+710 to 65+923) of Parokhuwa – Dokmoka Section(Package 2) of NH 29 in the state of Assam on EPC mode. (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of 81+000 (Design Chainage 65+923 to 80+930) of Dokmoka – LoringThepi Section (Package-3) of NH-29 in the state of Assam on EPC mode the Contract Price. 81+000 (Design Chainage 65+923 to 80+930) of Dokmoka – LoringThepi Section (Package-3) of NH-29 in the state of Assam on EPC mode (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.