Examples of Substantial Completion Payment in a sentence
Seller shall include with such Change Notice the best information and documentation then reasonably available to Seller to support any change proposed by Seller to the Purchase Price (including the Substantial Completion Payment Amount) or the Guaranteed Substantial Completion Date based on such claim.
Any dispute regarding a Change Notice for Force Majeure or Buyer-Caused Delay submitted by Seller to Buyer (including any provisional Change Order under this Section 8.6(b)) prior to the Substantial Completion Payment Date must be resolved between Seller and Buyer prior to the Substantial Completion Payment Date.
The Substantial Completion Payment Date shall be extended day for day for each day that the Project Performance Test Results show that the Minimum Performance Test Requirements have not been achieved.
If Buyer adds new Work or reduces the scope of Work by a Buyer Discretionary Change initiated after the Closing and prior to the Substantial Completion Payment Date, any Purchase Price adjustment shall be effectuated through a payment by Buyer to Seller or a decrease of the Substantial Completion Payment Amount, as applicable, based on the best cost adjustment information reasonably available to Seller and Buyer at the time of such adjustment.
Contracting Authority shall pay the Substantial Completion Payment as directed by Project Co in accordance with this Section 4.4(a) and shall not accept any redirection without the consent of the Lenders’ Agent.
By executing a Change Order, Seller thereafter waives the right to assert any further claim for an extension to the Guaranteed Substantial Completion Date (or any dates that are a function of the Guaranteed Substantial Completion Date), or an increase to the Purchase Price (including by modification of the Substantial Completion Payment Amount), or any other compensation, relief, or right or remedy based on, arising out of, or relating to the subject matter of, or the claim addressed by, such Change Order.
Contracting Authority shall pay the Substantial Completion Payment as directed by Project Co in accordance with this Section 4.4(b) and shall not accept any redirection without the consent of the Lenders’ Agent.
The Authority shall pay the Substantial Completion Payment to Developer within thirty (30) days of receipt by the Authority of the invoice being submitted to the Authority in accordance with the requirements of this Section 14.1.2.4. 14.1.2.5 Within thirty (30) days of the Final Acceptance Date, the Authority shall pay the Final Acceptance Payment to Developer.
Such Substantial Completion Deduction Amount shall be deducted from the BE MP Obligation for the Substantial Completion Payment made to the Developer pursuant to the C-70 Project Agreement.
Project Co acknowledges that the Substantial Completion Payment is subject to Construction Period Deductions in accordance with Schedule 21 - Construction Period Failures to this Project Agreement.