Common use of ADVANCE PAYMENT Clause in Contracts

ADVANCE PAYMENT. 69.1 The Contractor shall be entitled to an advance payment on the Contract amounting to 25% of the value of the Contract Sum less Provisional Sums (hereinafter referred to as the "Builder's Work") but subject to a maximum of RM10 million on compliance with the following conditions:

Appears in 4 contracts

Samples: tender.selangor.my, tender.selangor.my, Bahagian Pengurusan Perolehan

ADVANCE PAYMENT. 69.1 The Contractor shall be entitled to an advance payment on the Contract amounting to 25% of the value of the Contract Sum less Provisional Sums (hereinafter referred to as the "Builder's 46 Work") but subject to a maximum of RM10 million on compliance with the following conditions:

Appears in 1 contract

Samples: Kontrak Kerja)

ADVANCE PAYMENT. 69.1 The Contractor shall be entitled to an advance payment on the Contract amounting to 25% of the value of the Contract Sum less Provisional Sums (hereinafter referred to as the "Builder's Work") but subject to a maximum of RM10 million on compliance with the following conditions:'s

Appears in 1 contract

Samples: Bahagian Pengurusan Perolehan