Application for Payment. On or before the twenty-fifth (25th) Day of each calendar month beginning with the first (1st) calendar month following the Notice to Proceed, Design-Builder shall submit to Owner its request for payment for all Work performed and not paid for during the previous Pay Period (the “Application for Payment”). The Application for Payment shall be substantially in the form attached hereto as Exhibit M. Design-Builder shall submit to Owner, along with each Application for Payment, signed lien waivers, substantially in the form attached hereto as Exhibit N, received from Subcontractors and suppliers for the Work included in the Application for Payment submitted for the immediately preceding Pay Period and for which payment has been received.
Appears in 3 contracts
Samples: Master Agreement for Design, Engineering and Construction (US BioEnergy CORP), Master Agreement for Design, Engineering and Construction (US BioEnergy CORP), Master Agreement for Design, Engineering and Construction (US BioEnergy CORP)
Application for Payment. On Following the issuance of Notice to Proceed pursuant to Section 6.2, Design-Builder shall submit to Owner, on or before the twenty-fifth (25th) Day of each calendar month beginning with the first (1st) calendar month following the Notice to Proceedmonth, Design-Builder shall submit to Owner its request for payment for all Work performed and not paid for during the previous Pay Period (the “Application for Payment”). The Application for Payment shall be substantially in the form attached hereto as Exhibit M. Design-Builder shall submit to Owner, along with each Application for Payment, signed lien waivers, substantially in the form attached hereto as Exhibit N, received from Subcontractors and suppliers for the Work included in the Application for Payment submitted for the immediately preceding Pay Period and for which payment has been received.
Appears in 3 contracts
Samples: Lump Sum Design Build Agreement (Highwater Ethanol LLC), Lump Sum Design Build Contract (Ethanol Grain Processors, LLC), Lump Sum Design Build Agreement (Highwater Ethanol LLC)
Application for Payment. On or before the twenty-fifth (25th) Day of each calendar month beginning with the first (1st) calendar month following the Notice to Proceed, Design-Builder shall submit to Owner its request for payment for all Work performed and not paid for during the previous Pay Period (the “Application for Payment”). The Application for Payment shall be substantially in the form attached hereto as Exhibit M. Design-Builder shall submit to Owner, along with each Application for Payment, signed lien waivers, substantially in the form attached hereto as Exhibit N, received from Subcontractors and suppliers for the Work included in the Application for Payment submitted for the immediately preceding Pay Period and for which payment has been received.
Appears in 2 contracts
Samples: Lump Sum Design Build Expansion Agreement (US BioEnergy CORP), Lump Sum Design Build Expansion Agreement (Golden Grain Energy)
Application for Payment. On Following the issuance of Notice to Proceed pursuant to Section 6.2, Design-Builder shall submit to Owner, on or before the twenty-fifth (25th) Day of each calendar month beginning with the first (1st) calendar month following the Notice to Proceedmonth, Design-Builder shall submit to Owner its request for payment for all Work performed and not paid for during the previous Pay Period (the “Application for Payment”). The Application for Payment shall be substantially in the form attached hereto as Exhibit M. Design-Builder shall submit to Owner, along with each Application for Payment, signed lien waivers, substantially in the form attached hereto as Exhibit N, received from Subcontractors and suppliers for the Work included in the Application for Payment submitted for the immediately preceding Pay Period and for which payment has been received...
Appears in 2 contracts
Samples: Lump Sum Design Build Agreement (Advanced BioEnergy, LLC), Lump Sum Design Build Agreement (Advanced BioEnergy, LLC)
Application for Payment. On Following the issuance of Notice to Proceed pursuant to Section 6.2, Design-Builder shall submit to Owner, on or before the twenty-fifth (25th) Day of each calendar month beginning with the first (1st) calendar month following the Notice to Proceedmonth, Design-Builder shall submit to Owner its request for payment for all Work performed and not paid for during the previous Pay Period (the “Application for Payment”). The Application for Payment shall be substantially in the form attached hereto as Exhibit M. Design-Builder shall submit to Owner, along with each Application for Payment, signed lien waivers, substantially in the form attached hereto as Exhibit N, received from Design-Builder, Subcontractors and suppliers for the Work included in the Application for Payment submitted for the immediately preceding Pay Period and for which payment has been received.
Appears in 1 contract
Samples: Lump Sum Design Build Agreement (Cardinal Ethanol LLC)
Application for Payment. On or before the twenty-fifth (25th) Day of each calendar month beginning with the first (1st) calendar month following the Notice to Proceed, Design-Builder shall submit to Owner its request for payment for all Work performed and not paid for during the previous Pay Period (the “Application for Payment”). The Application for Payment shall be substantially in the form attached hereto as Exhibit M. Design-Builder shall submit to Owner, along with each Application for Payment, signed lien waivers, substantially in the form attached hereto as Exhibit N, received from Subcontractors and suppliers for the Work included in the E ENERGY AXXXX, LLC August 1, 2006 Application for Payment submitted for the immediately preceding Pay Period and for which payment has been received.
Appears in 1 contract
Samples: Lump Sum Design Build Agreement (E Energy Adams LLC)
Application for Payment. On Following the issuance of Notice to Proceed pursuant to Section 6.2, Design Builder shall submit to Owner, on or before the twenty-fifth (25th) Day of each calendar month beginning with the first (1st) calendar month following the Notice to Proceedmonth, Design-Builder shall submit to Owner its request for payment for all Work performed and not paid for during the previous Pay Period (the “Application for Payment”). The Application for Payment shall be substantially in the form attached hereto as Exhibit M. Design-Builder shall submit to Owner, along with each Application for Payment, signed lien waivers, substantially in the form attached hereto as Exhibit N, received from Design-Builder, Subcontractors and suppliers for the Work included in the Application for Payment submitted for the immediately preceding Pay Period and for which payment has been received.
Appears in 1 contract
Samples: Lump Sum Design Build Expansion Agreement (Little Sioux Corn Processors LLC)
Application for Payment. On Following the issuance of Notice to Proceed pursuant to Section 6.2, Design Builder shall submit to Owner, on or before the twenty-fifth (25th) Day of each calendar month beginning with the first (1st) calendar month following the Notice to Proceedmonth, Design-Builder shall submit to Owner its request for payment for all Work performed and not paid for during the previous Pay Period (the “Application for Payment”). The Application for Payment shall be substantially in the form attached hereto as Exhibit M. Design-Builder shall submit to Owner, along with each Application for Payment, signed lien waivers, substantially in the form attached hereto as Exhibit N, received from Design-Builder, Subcontractors and suppliers for the Work included in the Application for Payment submitted for the immediately preceding Pay Period and for which payment has been received.
Appears in 1 contract
Samples: Lump Sum Design Build Agreement (First United Ethanol LLC)