BERTH LAYTIME. 7.12.1 The allotted laytime for each LNG Tanker (“Allotted Laytime”) shall be thirty (30) hours, as extended by any period of delay that is caused by: (a) reasons attributable to a Governmental Authority, Buyer, the Transporter, the LNG Tanker or its master, crew, owner or operator or any Third Party outside of the reasonable control of Seller, Seller’s Affiliates or the operator of the Driftwood LNG Terminal, including security clearance review by the US Coast Guard; (b) Force Majeure or Adverse Weather Conditions; (c) unscheduled curtailment or temporary discontinuation of operations at the Driftwood LNG Terminal necessary for reasons of safety, except to the extent such unscheduled curtailment or temporary discontinuation of operations is due to Seller’s failure to operate and maintain its facilities as a Reasonable and Prudent Operator; (d) time at berth during any cool-down pursuant to Sections 7.16.1(a) and (c); (e) time at berth during any gas-up pursuant to Section 7.17; (f) nighttime transit restrictions, if applicable; (g) time to transit from the PBS or anchorage location, as applicable, to a berth of the Driftwood LNG Terminal, in the event Actual Laytime commences pursuant to Section 7.12.2(a)(1); and (h) any other interruption impacting the Loading Port, including the unavailability or delay of Pilot services, tugs, and other similar interruptions, to the extent such interruptions are not caused by reasons attributable to Seller or the operator of the Driftwood LNG Terminal. 7.12.2 The actual laytime for each LNG Tanker (“Actual Laytime”) shall commence (a) if a valid NOR was given pursuant to Section 7.10.1 prior to or during the Delivery Window for such LNG Tanker, the earlier of (1) twelve (12) hours after the later of the start of the Delivery Window and the time 49 that such valid NOR was given pursuant to Section 7.10.1, and (2) when the NOR is effective, or (b) in all other cases, when the NOR is effective, and shall end when (i) the last loading arm of the Driftwood LNG Terminal has been disconnected from the LNG Tanker, (ii) the cargo documents are on board of the LNG Tanker and (iii) Seller or its operator has cleared the LNG Tanker for departure. 7.12.3 In the event Actual Laytime exceeds Allotted Laytime (as extended pursuant to Section 7.12.1) (“Demurrage Event”), Seller shall pay to Buyer as liquidated damages demurrage in USD (which shall be prorated for a portion of a Day) at a rate equal to the Demurrage Rate. The “Demurrage Rate” initially shall be USD eighty thousand (US$80,000) per Day and shall be revised by Seller each Contract Year ending in five (5) or zero (0) (e.g., 2025 and 2030) to reflect the average of three quotes, each received from a different ship broker, for then-current long-term LNG vessel charter rates. Seller shall determine such revised Demurrage Rate and notify Buyer of such revised Demurrage Rate at least thirty (30) days prior to the start of such Contract Year ending in five (5) or zero (0), as applicable, and such revised Demurrage Rate shall be effective starting on the first day of such Contract Year ending in five (5) or zero (0), as applicable, and continuing for five (5) years until subsequently revised pursuant to this Section 7.12.3. If a Demurrage Event occurs, Buyer shall invoice Seller for such demurrage within ninety (90) Days pursuant to Section 10.1.5. 7.12.4 In the event (a) an LNG Tanker is delayed in berthing at the Driftwood LNG Terminal or commencement of LNG loading due to an event occurring at or near the Driftwood LNG Terminal (including at the berth) and for a reason that would not result in an extension of Allotted Laytime under Section 7.12.1, and (b) as a result thereof, the commencement of LNG loading is delayed beyond twenty-four (24) hours after the LNG Tanker (i) has either tendered a valid NOR or berthed and (ii) is cleared by the Governmental Authorities to commence loading (“Excess Boil-Off Event”), Seller shall pay Buyer as liquidated damages an amount, on account of excess boil-off. The amount payable shall equal (x) the total number of full hours by which commencement of LNG loading is delayed beyond the aforementioned twenty-four (24) hour period, multiplied by (y) initially, the Provisional Transfer Price for purposes of a Provisional Invoice, and thereafter the Final Transfer Price upon the determination thereof for purposes of the Final Invoice (in accordance with Section 10.1.6), multiplied by (z) a quantity in MMBtu equal to (A) the guaranteed daily ballast rate of boil-off of such LNG Tanker pursuant to Form B of the relevant charterparty or similar description provided by the LNG Tanker’s owner in the relevant charterparty, divided by (B) twenty-four (24) hours per Day, multiplied by (C) the cargo containment capacity of such LNG Tanker (in MMBtu), provided that in no event shall such quantity of MMBtu exceed the quantity of LNG onboard 50 the LNG Tanker at the time it issued its valid NOR. Buyer shall invoice Seller for such excess boil-off within ninety (90) Days after the applicable event, pursuant to Section 10.1.5.
Appears in 1 contract
Samples: Equity Capital Contribution Agreement (Tellurian Inc. /De/)
BERTH LAYTIME. 7.12.1 The allotted laytime for each LNG Tanker (“Allotted Laytime”) shall be thirty (30) hours, as extended by any period of delay that is caused by:
(a) reasons attributable to a Governmental Authority, Buyer, the Transporter, the LNG Tanker or its master, crew, owner or operator or any Third Party outside of the reasonable control of Seller, Seller’s Affiliates or the operator of the Driftwood LNG Terminal, including security clearance review by the US Coast Guard;
(b) Force Majeure or Adverse Weather Conditions;
(c) unscheduled curtailment or temporary discontinuation of operations at the Driftwood LNG Terminal necessary for reasons of safety, except to the extent such unscheduled curtailment or temporary discontinuation of operations is due to Seller’s failure to operate and maintain its facilities as a Reasonable and Prudent Operator;
(d) time at berth during any cool-down pursuant to Sections 7.16.1(a) and (c);
(e) time at berth during any gas-up pursuant to Section 7.17;
(f) nighttime transit restrictions, if applicable;
(g) time to transit from the PBS or anchorage location, as applicable, to a berth of the Driftwood LNG Terminal, in the event Actual Laytime commences pursuant to Section 7.12.2(a)(1); and
(h) any other interruption impacting the Loading Port, including the unavailability or delay of Pilot services, tugs, and other similar interruptions, to the extent such interruptions are not caused by reasons attributable to Seller or the operator of the Driftwood LNG Terminal.
7.12.2 The actual laytime for each LNG Tanker (“Actual Laytime”) shall commence (a) if a valid NOR was given pursuant to Section 7.10.1 prior to or during the Delivery Window for such LNG Tanker, the earlier of (1) twelve (12) hours after the later of the start of the Delivery Window and the time 49 that such valid NOR was given pursuant to Section 7.10.1, and (2) when the NOR is effective, or (b) in all other cases, when the NOR is effective, and shall end when (i) the last loading arm of the Driftwood LNG Terminal has been disconnected from the LNG Tanker, (ii) the cargo documents are on board of the LNG Tanker and (iii) Seller or its operator has cleared the LNG Tanker for departure.
7.12.3 In the event Actual Laytime exceeds Allotted Laytime (as extended pursuant to Section 7.12.1) (“Demurrage Event”), Seller shall pay to Buyer as liquidated damages demurrage in USD (which shall be prorated for a portion of a Day) at a rate equal to the Demurrage Rate. The “Demurrage Rate” initially shall be USD eighty thousand (US$80,000) per Day and shall be revised by Seller each Contract Year ending in five (5) or zero (0) (e.g., 2025 and 2030) to reflect the average of three quotes, each received from a different ship broker, for then-current long-term LNG vessel charter rates. Seller shall determine such revised Demurrage Rate and notify Buyer of such revised Demurrage Rate at least thirty (30) days prior to the start of such Contract Year ending in five (5) or zero (0), as applicable, and such revised Demurrage Rate shall be effective starting on the first day of such Contract Year ending in five (5) or zero (0), as applicable, and continuing for five (5) years until subsequently revised pursuant to this Section 7.12.3. If a Demurrage Event occurs, Buyer shall invoice Seller for such demurrage within ninety (90) Days pursuant to Section 10.1.5.. 45
7.12.4 In the event (a) an LNG Tanker is delayed in berthing at the Driftwood LNG Terminal or commencement of LNG loading due to an event occurring at or near the Driftwood LNG Terminal (including at the berth) and for a reason that would not result in an extension of Allotted Laytime under Section 7.12.1, and (b) as a result thereof, the commencement of LNG loading is delayed beyond twenty-four (24) hours after the LNG Tanker (i) has either tendered a valid NOR or berthed and (ii) is cleared by the Governmental Authorities to commence loading (“Excess Boil-Off Event”), Seller shall pay Buyer as liquidated damages an amount, on account of excess boil-off. The amount payable shall equal (x) the total number of full hours by which commencement of LNG loading is delayed beyond the aforementioned twenty-four (24) hour period, multiplied by (y) initially, the Provisional Transfer Price for purposes of a Provisional Invoice, and thereafter the Final Transfer Price upon the determination thereof for purposes of the Final Invoice (in accordance with Section 10.1.6), multiplied by (z) a quantity in MMBtu equal to (A) the guaranteed daily ballast rate of boil-off of such LNG Tanker pursuant to Form B of the relevant charterparty or similar description provided by the LNG Tanker’s owner in the relevant charterparty, divided by (B) twenty-four (24) hours per Day, multiplied by (C) the cargo containment capacity of such LNG Tanker (in MMBtu), provided that in no event shall such quantity of MMBtu exceed the quantity of LNG onboard 50 the LNG Tanker at the time it issued its valid NOR. Buyer shall invoice Seller for such excess boil-off within ninety (90) Days after the applicable event, pursuant to Section 10.1.5.
Appears in 1 contract
Samples: Equity Capital Contribution Agreement (Tellurian Inc. /De/)
BERTH LAYTIME. 7.12.1 The allotted laytime for each LNG Tanker (“Allotted Laytime”) shall be thirty (30) hours, as extended by any period of delay that is caused by:
(a) reasons attributable to a Governmental Authority, Buyer, the Transporter, the LNG Tanker or its master, crew, owner or operator or any Third Party outside of the reasonable control of Seller, Seller’s Affiliates Seller or the operator of the Driftwood LNG Terminal, including security clearance review by the US United States Coast Guard;
(b) Force Majeure or Adverse Weather Conditions;
(c) unscheduled curtailment or temporary discontinuation of operations at the Driftwood LNG Terminal necessary for reasons of safety, except to the extent such unscheduled curtailment or temporary discontinuation of operations is due to Seller’s failure to operate and maintain its facilities as a Reasonable and Prudent Operator;
(d) time at berth during any cool-down pursuant to Sections 7.16.1(a7.16.1(a) and (c(c);
(e) time at berth during any gas-up pursuant to Section 7.177.17;
(f) nighttime transit restrictions, if applicable;
(g) time to transit from the PBS or anchorage location, as applicable, to a berth of the Driftwood LNG Terminal, in the event Actual Laytime commences pursuant to Section 7.12.2(a)(1)tidal restrictions; and
(h) any other interruption impacting the Loading Port, including the unavailability or delay of Pilot services, tugs, and other similar interruptions, to the extent such interruptions are not caused by reasons attributable to Seller or the operator of the Driftwood LNG Terminal.
7.12.2 The actual laytime for each LNG Tanker (“Actual Laytime”) shall commence (a) if a valid NOR was given pursuant to Section 7.10.1 prior to or during the Delivery Window for such LNG Tanker, the earlier of (1) twelve (12) hours after the later of the start of the Delivery Window and the time 49 that such valid NOR was given pursuant to Section 7.10.1, and (2) when the NOR is effective, or (b) in all other cases, when the NOR is effective, and shall end when (i) the last loading arm of the Driftwood LNG Terminal has been disconnected from the LNG Tanker, (ii) Tanker and Seller or the cargo documents are on board operator of the Driftwood LNG Tanker and (iii) Seller or its operator Terminal has cleared the LNG Tanker for departure.
7.12.3 In the event Actual Laytime exceeds Allotted Laytime (as extended pursuant to Section 7.12.17.12.1) (“Demurrage Event”), Seller shall pay to Buyer as liquidated damages demurrage in USD (which shall be prorated for a portion of a Day) at a rate equal to the Demurrage Rate. The “Demurrage Rate” initially shall be USD eighty thousand [***] (US$80,000[***]) per Day and shall be revised by Seller each Contract Year ending in five (5) or zero (0) (e.g., 2025 and 2030) to reflect the average of three quotes, each received from a different ship broker, for then-current long-term LNG vessel charter rates. Seller shall determine such revised Demurrage Rate and notify Buyer of such revised Demurrage Rate at least thirty (30) days prior to the start of such Contract Year ending in five (5) or zero (0), as applicable, and such revised Demurrage Rate shall be effective starting on the first day of such Contract Year ending in five (5) or zero (0), as applicable, and continuing for five (5) years until subsequently revised pursuant to this Section 7.12.3Day. If a Demurrage Event occurs, Buyer shall invoice Seller for such demurrage within ninety (90) Days pursuant to Section 10.1.510.1.4. Any payment that Seller makes under this Section 7.12.3 shall not be treated as an indirect, incidental, consequential or exemplary loss for purposes of Section 15.2.1(a) or a loss of income or profits for purposes of Section 15.2.1(b).
7.12.4 In the event (a) an LNG Tanker is delayed in berthing at the Driftwood LNG Terminal or commencement of LNG loading due to an event occurring at or near the Driftwood LNG Terminal (including at the berth) and for a reason that would not result in an extension of Allotted Laytime under Section 7.12.17.12.1, and (b) as a result thereof, the commencement of LNG loading is delayed beyond twenty-four (24) hours after the LNG Tanker (i) has either tendered a valid NOR or berthed and (ii) is cleared by the Governmental Authorities to commence loading (“Excess Boil-Off Event”)loading, Seller shall pay Buyer as liquidated damages an amount, on account of excess boil-off. The amount payable shall equal (x) the total number of full hours by which commencement of LNG loading is delayed beyond the aforementioned twenty-four (24) hour period, multiplied by (y) initially, the Provisional Transfer Price for purposes of a Provisional Invoice, and thereafter the Final Transfer Price upon the determination thereof for purposes of the Final Invoice (in accordance with Section 10.1.6)CSP, multiplied by (z) a quantity in MMBtu equal to (A) the guaranteed daily ballast rate of boil-off of such LNG Tanker pursuant to Form B of the relevant charterparty or similar description provided by the LNG Tanker’s owner in the relevant charterparty, divided by (B) twenty-four (24) hours per Day, multiplied by (C) the cargo containment capacity of such LNG Tanker (in MMBtu), provided that in no event shall such quantity of MMBtu exceed the quantity of LNG onboard 50 the LNG Tanker at the time it issued its valid NOR. Buyer shall invoice Seller for such excess boil-off within ninety (90) Days after the applicable event, pursuant to Section 10.1.510.1.4. Any payment that Seller makes under this Section 7.12.4 shall not be treated as an indirect, incidental, consequential or exemplary loss for purposes of Section 15.2.1(a) or a loss of income or profits for purposes of Section 15.2.1(b).
Appears in 1 contract
Samples: LNG Sale and Purchase Agreement (Tellurian Inc. /De/)
BERTH LAYTIME. 7.12.1 The allotted laytime for each LNG Tanker (“Allotted Laytime”) shall be thirty (30) hours, as extended by any period of delay that is caused by:
(a) reasons attributable to a Governmental Authority, Buyer, the Transporter, the LNG Tanker or its master, crew, owner or operator or any Third Party outside of the reasonable control of Seller, Seller’s Affiliates Driftwood or the operator of the Driftwood LNG Terminal, including security clearance review by the US Coast Guard;
(b) Force Majeure or Adverse Weather Conditions;
(c) unscheduled curtailment or temporary discontinuation of operations at the Driftwood LNG Terminal necessary for reasons of safety, except to the extent such unscheduled curtailment or temporary discontinuation of operations is due to SellerDriftwood’s failure to operate and maintain its facilities as a Reasonable and Prudent Operator;
(d) time at berth during any cool-down pursuant to Sections 7.16.1(a) and (c);
(e) time at berth during any gas-up pursuant to Section 7.17;
(f) nighttime transit restrictions, if applicable;
(g) time to transit from the PBS or anchorage location, as applicable, to a berth of the Driftwood LNG Terminal, in the event Actual Laytime commences pursuant to Section 7.12.2(a)(1); and
(h) any other interruption impacting the Loading Port, including the unavailability or delay of Pilot services, tugs, and other similar interruptions, to the extent such interruptions are not caused by reasons attributable to Seller Seller, Driftwood or the operator of the Driftwood LNG Terminal.
7.12.2 The actual laytime for each LNG Tanker (“Actual Laytime”) shall commence (a) if a valid NOR was given pursuant to Section 7.10.1 prior to or during the Delivery Window for such LNG Tanker, the earlier of (1) twelve (12) hours after the later of the start of the Delivery Window and the time 49 that such valid NOR was given pursuant to Section 7.10.1, and (2) when the NOR is effective, or (b) in all other cases, when the NOR is effective, and shall end when (i) the last loading arm of the Driftwood LNG Terminal has been disconnected from the LNG Tanker, (ii) the cargo documents are on board of the LNG Tanker and (iii) Seller Seller, Driftwood or its the operator of the Driftwood LNG Terminal has cleared the LNG Tanker for departure.
7.12.3 In the event Actual Laytime exceeds Allotted Laytime (as extended pursuant to Section 7.12.1) (“Demurrage Event”), Seller shall pay to Buyer as liquidated damages demurrage in USD (which shall be prorated for a portion of a Day) at a rate equal to the Demurrage Rate. The “Demurrage Rate” initially shall be USD eighty thousand (US$80,000) per Day and shall be revised by Seller each Contract Year ending in five (5) or zero (0) (e.g., 2025 and 2030) to reflect the average of three quotes, each received from a different ship broker, for then-current long-term LNG vessel charter rates. Seller shall determine such revised Demurrage Rate and notify Buyer of such revised Demurrage Rate at least thirty (30) days prior to the start of such Contract Year ending in five (5) or zero (0), as applicable, and such revised Demurrage Rate shall be effective starting on the first day of such Contract Year ending in five (5) or zero (0), as applicable, and continuing for five (5) years until subsequently revised pursuant to this Section 7.12.3. If a Demurrage Event occurs, Buyer shall invoice Seller for such demurrage within ninety (90) Days pursuant to Section 10.1.510.1.4.
7.12.4 In the event (a) an LNG Tanker is delayed in berthing at the Driftwood LNG Terminal or commencement of LNG loading due to an event occurring at or near the Driftwood LNG Terminal (including at the berth) and for a reason that would not result in an extension of Allotted Laytime under Section 7.12.1, and (b) as a result thereof, the commencement of LNG loading is delayed beyond twenty-four (24) hours after the LNG Tanker (i) has either tendered a valid NOR or berthed and (ii) is cleared by the Governmental Authorities to commence loading (“Excess Boil-Off Event”), Seller shall pay Buyer as liquidated damages an amount, on account of excess boil-off. The amount payable shall equal (x) the total number of full hours by which commencement of LNG loading is delayed beyond the aforementioned twenty-four (24) hour period, multiplied by (y) initially, the Provisional Transfer Price for purposes of a Provisional Invoice, and thereafter the Final Transfer Price upon the determination thereof for purposes of the Final Invoice (in accordance with Section 10.1.6)CSP, multiplied by (z) a quantity in MMBtu equal to (A) the guaranteed daily ballast rate of boil-off of such LNG Tanker pursuant to Form B of the relevant charterparty or similar description provided by the LNG Tanker’s owner in the relevant charterparty, divided by (B) twenty-four (24) hours per Day, multiplied by (C) the cargo containment capacity of such LNG Tanker (in MMBtu), provided that in no event shall such quantity of MMBtu exceed the quantity of LNG onboard 50 the LNG Tanker at the time it issued its valid NOR. For purposes of the foregoing, the CSP shall be determined as of the Month in which the applicable Delivery Window begins. Buyer shall invoice Seller for such excess boil-off within ninety (90) Days after the applicable event, pursuant to Section 10.1.510.1.4.
Appears in 1 contract
Samples: LNG Sale and Purchase Agreement (Tellurian Inc. /De/)