Common use of Budget and Cost Consultation Clause in Contracts

Budget and Cost Consultation. 5.4.1 Construction Manager is responsible for preparing and updating all procurement and construction cost estimates and distributing them to the Project Team throughout the duration of the Project. 5.4.2 Provide Estimated Construction Cost (ECC) reports at the required stages of completion of the schematic design, design development, and construction documents phases of the Project as required in Article 25. The Estimated Construction Cost reports for the design development and construction documents phases shall be detailed estimates derived from cost quantity surveys based on unit prices for labor, materials, overhead and profit, organized in current Construction Specifications Institute Division format for each portion of the Work. 5.4.3 Provide continuous cost consultation services throughout the duration of the Project, including identification and tracking of decisions that affect the scope or quality of the Project and providing ongoing updates of their cost and budget impact. Advise the Project Team immediately if Construction Manager has reason to believe that the most current ECC will exceed the Construction Cost Limitation (CCL) or not meet CPM Schedule requirements and recommend reasonable strategies for bringing the Project in line with the CCL and the CPM Schedule. 5.4.4 Construction Manager shall promptly identify all variances between estimated costs and actual costs during the Construction Phase, and shall promptly report such variances to the Project Team along with recommendations for action, but in any event no more than two (2) business days after acquiring such information. 5.4.5 Should any ECC exceed or fall significantly below the approved CCL, Owner and Construction Manager shall negotiate changes to the Project requirements or the CCL as required.

Appears in 6 contracts

Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Manager at Risk Agreement

AutoNDA by SimpleDocs

Budget and Cost Consultation. 5.4.1 The Construction Manager is responsible for preparing and updating all procurement and construction cost estimates and distributing them to the Project Team throughout the duration of the Project. 5.4.2 Provide Provided Estimated Construction Cost (ECC) reports at the required stages of completion of the schematic design, design development, and construction documents phases of the Project as required in Article 25. The Estimated Construction Cost reports for the design development and construction documents phases shall be detailed estimates derived from cost quantity surveys based on unit prices for labor, materials, overhead and profit, organized in current Construction Specifications Institute Division format for each portion of the Work. 5.4.3 Provide continuous cost consultation services throughout the duration of the Project, including identification and tracking of decisions that affect the scope or quality of the Project and providing ongoing updates of their cost and budget impact. Advise the Project Team immediately if the Construction Manager has reason to believe that the most current ECC will exceed the Construction Cost Limitation (CCL) or not meet CPM Schedule requirements and recommend reasonable strategies for bringing the Project in line with the CCL and the CPM Schedule. 5.4.4 Construction Manager shall promptly identify all variances between estimated costs and actual costs during the Construction Phase, and shall promptly report such variances to the Project Team along with recommendations for action, but in any event no more than two (2) business days after acquiring such information. 5.4.5 Should any ECC exceed or fall significantly below the approved CCL, the Owner and Construction Manager shall negotiate changes to the Project requirements or the CCL as required.

Appears in 4 contracts

Samples: Construction Manager at Risk Agreement, Construction Manager Agreement, Construction Manager Agreement

Budget and Cost Consultation. 5.4.1 The Construction Manager is responsible for preparing and updating all procurement and construction cost estimates and distributing them to the Project Team throughout the duration of the Project. 5.4.2 Provide Estimated Construction Cost (ECC) reports at the required stages of completion of the schematic design, design development, and construction documents phases of the Project as required in Article 25. The Estimated Construction Cost reports for the design development and construction documents phases shall be detailed estimates derived from cost quantity surveys based on unit prices for labor, materials, overhead and profit, organized in current Construction Specifications Institute Division format for each portion of the Work. 5.4.3 Provide continuous cost consultation services throughout the duration of the Project, including identification and tracking of decisions that affect the scope or quality of the Project and providing ongoing updates of their cost and budget impact. Advise the Project Team immediately if the Construction Manager has reason to believe that the most current ECC will exceed the Construction Cost Limitation (CCL) or not meet CPM Schedule requirements and recommend reasonable strategies for bringing the Project in line with the CCL and the CPM Schedule. 5.4.4 Construction Manager shall promptly identify all variances between estimated costs and actual costs during the Construction Phase, and shall promptly report such variances to the Project Team along with recommendations for action, but in any event no more than two (2) business days after acquiring such information. 5.4.5 Should any ECC exceed or fall significantly below the approved CCL, the Owner and Construction Manager shall negotiate changes to the Project requirements or the CCL as required.

Appears in 2 contracts

Samples: Construction Manager Agreement, Construction Manager at Risk Agreement

Budget and Cost Consultation. 5.4.1 The Construction Manager is responsible for preparing and updating all procurement and construction cost estimates and distributing them to the Project Team throughout the duration of the Project. 5.4.2 Provide Estimated Construction Cost (ECC) reports at the required stages of completion of the schematic design, design development, and construction documents phases of the Project as required in Article 25. The Estimated Construction Cost reports for the design development and construction documents phases shall be detailed estimates derived from cost quantity surveys based on unit prices for labor, materials, overhead and profit, organized in current Construction Specifications Institute Division format for each portion of the Work. 5.4.3 Provide continuous cost consultation services throughout the duration of the Project, including identification and tracking of decisions that affect the scope or quality of the Project and providing ongoing updates of their cost and budget impact. Advise the Project Team immediately if the Construction Manager has reason to believe that the most current ECC will exceed the Construction Cost Limitation (CCL) or not meet CPM Schedule requirements and recommend reasonable strategies for bringing the Project in line with the CCL and the CPM Schedule. 5.4.4 Construction Manager shall promptly identify all variances between estimated costs and actual costs during the Construction Phase, and shall promptly report such variances to the Project Team along with recommendations for action, but in any event no more than two (2) business days after acquiring such information. 5.4.5 Should any ECC exceed or fall significantly below the approved CCL, the Owner and Construction Manager shall negotiate changes to the Project requirements or the CCL as required.

Appears in 2 contracts

Samples: Construction Manager Agreement, Construction Manager Agreement

Budget and Cost Consultation. 5.4.1 Construction Manager 5.1.3.1 The Design/Build Contractor is responsible for preparing and updating all procurement and construction cost estimates and distributing them to the Project Team throughout the duration of the Project. 5.4.2 5.1.3.2 Provide Estimated Construction Cost (ECC) reports at the required stages of completion of the schematic design, design development, and construction documents phases document stages of the Project as required in Article 25Project. The Estimated Construction Cost reports for the design development and construction documents phases document stages shall be detailed estimates derived from cost quantity surveys based on unit prices for labor, materials, overhead and profit, organized in current Construction Specifications Institute Division 1-16 format for each portion of the Work. 5.4.3 5.1.3.3 Provide continuous cost consultation services throughout the duration of the Project, including identification and tracking of decisions that affect the scope or quality of the Project and providing ongoing updates of their cost and budget impact. Advise the Project Team immediately if Construction Manager the Design/Build Contractor has reason to believe that the most current ECC will exceed the Construction Cost Limitation (CCL) or not meet CPM Schedule requirements and recommend reasonable strategies for bringing the Project in line with the CCL and the CPM Schedule. 5.4.4 Construction Manager 5.1.3.4 Design/Build Contractor shall promptly identify all variances between estimated costs and actual costs during the Construction Phase, and shall promptly report such variances to the Project Team along with recommendations for action, but in any event no more than two (2) business days after acquiring such information. 5.4.5 5.1.3.5 Should any ECC exceed or fall significantly below the approved CCL, the Owner and Construction Manager Design/Build Contractor shall negotiate changes to the Project requirements or the CCL as required.

Appears in 1 contract

Samples: Design/Build Agreement

Budget and Cost Consultation. 5.4.1 The Construction Manager is responsible for preparing and updating all procurement and construction cost estimates and distributing them to the Project Team throughout the duration of the Project. 5.4.2 Provide Provided Estimated Construction Cost (ECC) reports at the required stages of completion of the schematic design, design development, and construction documents phases of the Project as required in Article 25. The Estimated Construction Cost reports for the design development and construction documents phases shall be detailed estimates derived from cost quantity surveys based on unit prices for labor, materials, overhead and profit, organized in current Construction Specifications Institute Division format for each portion of the Work. 5.4.3 Provide continuous cost consultation services throughout the duration of the Project, including identification and tracking of decisions that affect the scope or quality of the Project and providing ongoing updates of their cost and budget impact. Advise the Project Team immediately if the Construction Manager has reason to believe that the most current ECC will exceed the Construction Cost Limitation (CCL) or not meet CPM Schedule requirements and recommend reasonable strategies for bringing the Project in line with the CCL and the CPM Schedule. 5.4.4 Construction Manager shall promptly identify all variances between estimated costs and actual costs during the Construction Phase, Phase and shall promptly report such variances to the Project Team along with recommendations for action, but in any event no more than two (2) business days after acquiring such information. 5.4.5 Should any ECC exceed or fall significantly below the approved CCL, the Owner and Construction Manager shall negotiate changes to the Project requirements or the CCL as required.

Appears in 1 contract

Samples: Construction Manager Agreement

AutoNDA by SimpleDocs

Budget and Cost Consultation. 5.4.1 The Construction Manager is responsible for preparing and updating all procurement and construction cost estimates and distributing them to the Project Team throughout the duration of the Project. 5.4.2 Provide Provided Estimated Construction Cost (ECC) reports at the required stages of completion of the schematic design, design development, and construction documents phases of the Project as required in Article 25. The Estimated Construction Cost reports for the design development and construction documents phases shall be detailed estimates derived from cost quantity surveys based on unit prices for labor, materials, overhead and profit, organized in current Construction Specifications Institute Division format for each portion of the Work. 5.4.3 Provide continuous cost consultation services throughout the duration of the Project, including identification and tracking of decisions that affect the scope or quality of the Project and providing ongoing updates of their cost and budget impact. Advise the Project Team immediately if the Construction Manager has reason to believe that the most current ECC will exceed the Construction Cost Limitation (CCL) or not meet CPM Schedule requirements and recommend reasonable strategies for bringing the Project in line with the CCL and the CPM Schedule. 5.4.4 Construction Manager shall promptly identify all variances between estimated costs and actual costs during the Construction Phase, and shall promptly report such variances to the Project Team along with recommendations for action, but in any event no more than two (2) business days after acquiring such information. 5.4.5 Should any ECC exceed or fall significantly below the approved CCL, the Owner and Construction Manager shall negotiate changes to the Project requirements or the CCL as required.

Appears in 1 contract

Samples: Construction Manager Agreement

Budget and Cost Consultation. 5.4.1 The Construction Manager is responsible for preparing and updating all procurement and construction cost estimates and distributing them to the Project Team throughout the duration of the Project. 5.4.2 Provide Estimated Construction Cost (ECC) reports at the required stages of completion of the schematic design, design development, and construction documents phases of the Project as required in Article 25. The Estimated Construction Cost reports for the design development and construction documents phases shall be detailed estimates derived from cost quantity surveys based on unit prices for labor, materials, overhead and profit, organized in current Construction Specifications Institute Division format MASTER Format 2011 for each portion of the Work. 5.4.3 Provide continuous cost consultation services throughout the duration of the Project, including identification and tracking of decisions that affect the scope or quality of the Project and providing ongoing updates of their cost and budget impact. Advise the Project Team immediately if the Construction Manager has reason to believe that the most current ECC will exceed the Owner’s Construction Cost Limitation (CCL) Budget or not meet CPM Schedule requirements and recommend reasonable strategies for bringing the Project in line with the CCL Owner’s Construction budget and the CPM Schedule. 5.4.4 Construction Manager shall promptly identify all variances between estimated costs and actual costs during the Construction Phase, and shall promptly report such variances to the Project Team along with recommendations for action, but in any event no more than two (2) business days after acquiring such information. 5.4.5 Should any ECC exceed or fall significantly below the approved CCLOwner’s Construction Budget, the Owner and Construction Manager shall negotiate changes to the Project requirements or the CCL Owner’s Construction Budget as required.

Appears in 1 contract

Samples: Solicitation Amendment

Budget and Cost Consultation. 5.4.1 The Construction Manager is responsible for preparing and updating all procurement and construction cost estimates and distributing them to the Project Team throughout the duration of the Project. 5.4.2 Provide Estimated Construction Cost (ECC) reports at the required stages of completion of the schematic design, design development, and construction documents phases of the Project as required in Article 25. The Estimated Construction Cost reports for the design development and construction documents phases shall be detailed estimates derived from cost quantity surveys based on unit prices for labor, materials, overhead and profit, organized in current Construction Specifications Institute Division format for each portion of the Work. 5.4.3 Provide continuous cost consultation services throughout the duration of the Project, including identification and tracking of decisions that affect the scope or quality of the Project and providing ongoing updates of their cost and budget impact. Advise the Project Team immediately if the Construction Manager has reason to believe that the most current ECC estimated construction costs will exceed the Construction Cost Limitation (CCL) or not meet CPM Schedule requirements and recommend reasonable strategies for bringing the Project in line with the CCL and the CPM Schedule. 5.4.4 Construction Manager shall promptly identify all variances between estimated costs and actual costs during the Construction Phase, Phase and shall promptly report such variances to the Project Team along with recommendations for action, but in any event no more than two (2) business days after acquiring such information. 5.4.5 Should any ECC exceed or fall significantly below the approved CCL, Owner the City and Construction Manager shall negotiate changes to the Project requirements or the CCL as required.

Appears in 1 contract

Samples: Construction Manager at Risk Contract