Change Notices (Change Order Requests) Sample Clauses

Change Notices (Change Order Requests). All change order requests shall be submitted via email to the Counterparty on Owner’s Change Order Request Form with all applicable supporting documentation attached as set forth within the Agreement.
AutoNDA by SimpleDocs

Related to Change Notices (Change Order Requests)

  • Change Order Procedure The Agency may at any time request a modification to the Scope of Work using a change order. The following procedures for a change order shall be followed:

  • CHANGE REQUEST PROCEDURE (a) Any Change Request of Customer or SAP must be in writing and in the format as provided by SAP.

  • Change Request Procedures 4.1. Either party can request changes to the Service in accordance with the change request form attached to the Order Form or provided by SAP from time to time (“Change Request”).

  • Notice of Network Changes If a Party makes a change in the information necessary for the transmission and routing of services using that Party’s facilities or network, or any other change in its facilities or network that will materially affect the interoperability of its facilities or network with the other Party’s facilities or network, the Party making the change shall publish notice of the change at least ninety (90) days in advance of such change, and shall use reasonable efforts, as commercially practicable, to publish such notice at least one hundred eighty (180) days in advance of the change; provided, however, that if an earlier publication of notice of a change is required by Applicable Law (including, but not limited to, 47 CFR 51.325 through 51. 335) notice shall be given at the time required by Applicable Law.

  • Change Requests 4.1.1. Either party can request changes to the Service.

  • Notice of Changes If a Party makes a change in its network which it believes will materially affect the interoperability of its network with the other Party, the Party making the change shall provide at least ninety (90) days advance written notice of such change to the other Party.

  • Owner-Requested Changes If the Owner requests changes in the Contract Documents that would materially affect the completion of the Work by lengthening the critical path of the Overall Project Schedule, the Design Professional shall determine the appropriate number of days and thereby extend the Material Completion and Occupancy Date. The Contractor expressly agrees that the Contractor’s sole monetary remedy for such extensions of Contract Time shall be calculated at the daily rate established for Time Dependent Overhead Costs in the Contract.

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • Change Order (5) The Change Order is then submitted to the Project Manager who immediately processes the CO with OPC as required by Bulletin 3.5 and BGS’ Contracting Plan.

  • Change Order Formats Formats for Lump Sum Change Orders and for Change Orders based upon either a force account or upon unit pricing with an indeterminate number of units are in Section 7, Forms.