Claims by the Contractor. 8.1.1 All Contractor claims shall be initiated by written notice and claim to the City. Such written notice and claim must be furnished within seven (7) days after occurrence of the event, or the first appearance of the condition, giving rise to the claim.
Appears in 4 contracts
Samples: Contract, Contract, Contract Agreement
Claims by the Contractor. 8.1.1 8.2.1 All Contractor claims shall be initiated by written notice and claim to the CityOwner attention the Procurement Department. Such written notice and claim must be furnished within seven (7) days after occurrence of the event, or the first appearance of the condition, giving rise to the claim.
Appears in 3 contracts
Samples: Fixed Price Agreement, Fixed Price Agreement, Fixed Price Agreement
Claims by the Contractor. 8.1.1 All 8.3.1 Except as prohibited in Paragraph 8.3.5.1 herein below, all Contractor claims shall be initiated by written notice and claim to the City and the City’s Representative, as applicable. Such written notice and claim must be furnished within seven three (73) days after occurrence of the event, or the first appearance of the condition, condition giving rise to the claim.
Appears in 2 contracts
Claims by the Contractor. 8.1.1 8.3.1 All Contractor claims shall be initiated by written notice and claim to the CityOwner and the Architect. Such written notice and claim must be furnished within seven (7) days after occurrence of the event, or the first appearance of the condition, giving rise to the claim.
Appears in 2 contracts
Claims by the Contractor. 8.1.1 8.3.1 All Contractor claims shall be initiated by written notice and claim to the CityOwner. Such written notice and claim must be furnished within seven (7) days after occurrence of the event, or the first appearance of the condition, giving rise to the claim.
Appears in 2 contracts
Samples: Contract for Construction and Incorporated General Conditions, Contract for Construction and Incorporated General Conditions
Claims by the Contractor. 8.1.1 All Contractor claims shall be initiated by written notice and claim to the CityAuthority. Such written notice and claim Claims must be furnished made within seven (7) days after occurrence of the event, or the first appearance of the condition, giving rise to the claim.
Appears in 1 contract
Samples: North Carolina Agreement
Claims by the Contractor. 8.1.1 8.3.1 All Contractor claims shall be initiated by written notice and claim to the CityCity and the Assigned Representative(s) / Contract Administrator(s). Such written notice and of a claim must be furnished within no later than seven (7) calendar days after occurrence occurrence, or seven (7) calendar days after the Contractor’s first knowledge of the event, or the first appearance of the condition, occurrence giving rise to the claim, whichever first occurs.
Appears in 1 contract
Samples: www.eastpointcity.org
Claims by the Contractor. 8.1.1 12.1. All Contractor claims shall be initiated by written notice and claim to the CityCity Public Works Field Superintendent. Such written notice and claim must be furnished within seven (7) calendar days after occurrence of the event, or the first appearance of the condition, giving rise to the claim.
Appears in 1 contract
Samples: Construction Agreement