Claims for Additional Costs. 11.3.1 If the Contractor wishes to make a claim for an increase in the Contract Sum not related to a requested change, it shall give the Owner and the A/E written notice thereof within twenty-one (21) days after the occurrence of the event giving rise to such claim, but, in any case before proceeding to execute the work considered to give rise to the additional cost or time, except in an emergency endangering life or property in which case the Contractor shall act in accordance with Article 7.2.1. No such claim shall be valid unless so made. If the Owner and the Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined as set forth under Article 15. Any change in the Contract Sum resulting from such claim shall be authorized by Change Order.
Claims for Additional Costs. 11.3.1 If Contractor wishes to make a claim for an increase in the Contract Sum not related to a requested change, it shall give Owner and A/E written notice thereof within twenty-one (21) days after the occurrence of the event or discovery of any conditions giving rise to such claim. Contractor must notify Owner and A/E before proceeding to execute any Work considered to add additional cost or time, except in an emergency endangering life or property in which case Contractor shall act in accordance with Subsection 7.2.1., and failure to provide the required notice will invalidate any subsequent notice or claim for additional cost or time for the Work. If Owner and Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be determined as set forth under Article 15. Any change in the Contract Sum resulting from such claim shall be authorized by a Change Order or a ULCO.
Claims for Additional Costs. If the Contractor claims that additional costs are involved because of (i) any written interpretation of this Agreement issued by the Owner or (ii) any order by the Owner to stop the Work where the Contractor was not at fault, or (iii) any other event, the Contractor shall submit such claim by giving the Owner written notice thereof within seven (7) days after the occurrence of the event or of the time Contractor first becomes aware of the event giving rise to such claim. Such notice shall be in the format displayed in Appendix H (Change Order Request Form) and shall be given by the Contractor before proceeding to execute the Work, except in an emergency endangering life or property. No such claim for additional compensation shall be valid unless so made. Any change in the Agreement Sum resulting from such claim must be authorized by Owner in a change order.
Claims for Additional Costs. If the Contractor wishes to make a claim for an increase in the Contract Price, as a condition precedent to any liability of the Owner therefor, the Contractor shall give the Architect written notice of such claim within seven (7) days after the occurrence of the event, or the first appearance of the condition, giving rise to such claim. Such notice shall be given by the Contractor before proceeding to execute any additional or changed Work. The failure by the Contractor to give such notice and to give such notice prior to executing the Work shall constitute a waiver of any claim for additional compensation.
Claims for Additional Costs. 11.3.1 If Contractor wishes to make a claim for an increase in the Contract Sum not related to a requested change, they it shall give Owner and A/E written notice thereof within twenty-one
Claims for Additional Costs. Strike the first sentence and replace with the following: “Contractor shall not proceed to execute any portion of the Work that is subject to the Claim without prior approval of the costs or method of payment for the costs associated with the Claim as determined by the Architect and approved by the Owner.”
Claims for Additional Costs. 19.1.1 If, for any reason, the Construction Manager claims that it is entitled to an increase in the Contract Sum or Guaranteed Maximum Price or an extension of agreed completion date (paragraph 6.3), the Construction Manager shall give the Principal Representative its written Notice of Claim thereof within fifteen (15) days or such other time period as may be specifically set forth elsewhere in this Agreement, whichever is the lesser, after the occurrence of the event giving rise to such claim and in all cases before proceeding to execute the work, except in an emergency endangering life or property in which case the Construction Manager shall proceed in accordance with paragraph 3.22.10. No such claim shall be valid unless so made. Any approved change in the Contract Sum or Guaranteed Maximum Price resulting from such claim shall be authorized by Amendment.
Claims for Additional Costs. Except as prohibited in Paragraph 8.3.5 herein below, if the Contractor wishes to make a claim for an increase in the Contract Price, as a condition precedent to any liability of the City therefore, the Contractor shall give the City’s Representative and the City written notice of such claim within three (3) days after the occurrence of the event, or the first appearance of the condition, giving rise to such claim. Such notice must be given by the Contractor before proceeding to execute any additional or changed Work. The failure by the Contractor to give such notice and to give such notice prior to executing the Work shall constitute a waiver of any claim for additional compensation.
Claims for Additional Costs. If the Contractor wishes to make a claim for an increase in the Contract Price, as a condition precedent to any liability of the City therefor, the Contractor shall give the City written notice of such claim within seven (7) days after the occurrence of the event, or the first appearance of the condition, giving rise to such claim. Such notice shall be given by the Contractor before proceeding to execute any additional or changed Work. The failure by the Contractor to give such notice prior to executing the Work shall constitute a waiver of any claim for additional compensation.
Claims for Additional Costs. 1. If Contractor wishes to make a claim for an increase in the Contract Price, he shall give the Agency written notice thereof within the time set forth in Paragraph a. above. This notice shall be given by the Contractor before proceeding to execute the work, except in an emergency endangering life or property in which case the Contractor shall, as soon as soon as possible, advise Agency of his intent to do the Work.