Claims by the Contractor. 3.3.1 Liquidated damages for delay, if provided for in Section 9.3 of this Agreement, shall be assessed against the Subcontractor only to the extent caused by the Subcontractor or any person or entity for whose acts the Subcontractor may be liable, and in no case for delays or causes arising outside the scope of this Subcontract.
Appears in 6 contracts
Samples: www.riveter-enterprises.com, Master Subcontract Agreement, Subcontract Agreement
Claims by the Contractor. § 3.3.1 Liquidated damages for delay, if provided for in Section 9.3 of this Agreement, delay shall be assessed against the Subcontractor only to the extent caused by the Subcontractor or any person or entity for whose acts the Subcontractor may be liable, and in no case for delays or causes arising outside the scope of this Subcontract.
Appears in 1 contract
Samples: Subcontract Agreement
Claims by the Contractor. 3.3.1 Liquidated damages for delay, if provided for in Section 9.3 of this Agreement, shall be the Subcontractor, assessed against the Subcontractor only to the extent caused by the Subcontractor or any person or entity for whose acts the Subcontractor may be liable, and in no case for delays or causes arising outside the scope of this Subcontract.
Appears in 1 contract
Samples: Master Agreement