Connection Requirements. (a) The Generator shall arrange, at its sole expense, for all Facility connection requirements in accordance with Applicable Law to permit the Delivery of Renewable Electricity to the Connection Point. (b) All Connection Costs shall be for the account of the Generator and, as applicable, the TFO and/or DFO with which the Generator has arranged connection of the Facility pursuant to the Connection Agreement, any Construction Commitment Agreement, and the ISO Tariff, DFO Tariff, and/or TFO Tariff, as applicable. Notwithstanding the foregoing, the Generator shall notify the AESO from time to time during the Term of any such Connection Costs originally paid by it which become refundable or payable, or are refunded or paid, to the Generator in respect of any such agreement or tariff, or in respect of any construction contribution previously paid by the Generator, and the Generator shall assign or pay, as the case may be, all such amounts to the AESO. (c) The Generator shall provide, at its expense, all power system components on the Generator's side of the Connection Point, including all transformation, switching and auxiliary equipment, such as synchronizing and protection and control equipment required, pursuant to Applicable Law and any requirements deemed necessary by the System Operator, the TFO or the DFO, as applicable from time to time, to protect the safety and security of the AIES, the Transmission Facility, the Distribution Facility and each of their customers, each as the case may be. (d) The Generator agrees to install protective equipment to protect its own personnel, property, and equipment from variations in frequency and voltage or from temporary delivery of other than three-phase power, whether caused by the Facility, the AIES, the Transmission Facility or the Distribution Facility.
Appears in 2 contracts
Samples: Renewable Electricity Support Agreement, Renewable Electricity Support Agreement
Connection Requirements. β
(a) The Generator shall arrange, at its sole expense, for all Facility connection requirements in accordance with Applicable Law to permit the Delivery of Renewable Electricity to the Connection Point.
(b) All Connection Costs shall be for the account of the Generator and, as applicable, the TFO and/or DFO with which the Generator has arranged connection of the Facility pursuant to the Connection Agreement, any Construction Commitment Agreement, and the ISO Tariff, DFO Tariff, and/or TFO Tariff, as applicable. Notwithstanding the foregoing, the Generator shall notify the AESO from time to time during the Term of any such Connection Costs originally paid by it which become refundable or payable, or are refunded or paid, to the Generator in respect of any such agreement or tariff, or in respect of any construction contribution previously paid by the Generator, and the Generator shall assign or pay, as the case may be, all such amounts to the AESO.
(c) The Generator shall provide, at its expense, all power system components on the Generator's side of the Connection Point, including all transformation, switching and auxiliary equipment, such as synchronizing and protection and control equipment required, pursuant to Applicable Law and any requirements deemed necessary by the System Operator, the TFO or the DFO, as applicable from time to time, to protect the safety and security of the AIES, the Transmission Facility, the Distribution Facility and each of their customers, each as the case may be.
(d) The Generator agrees to install protective equipment to protect its own personnel, property, and equipment from variations in frequency and voltage or from temporary delivery of other than three-phase power, whether caused by the Facility, the AIES, the Transmission Facility or the Distribution Facility.