Consequence of Force Majeure Events Sample Clauses

Consequence of Force Majeure Events. Where after taking all measures specified in Clause 2 of this Article but failing to fulfill one part or the whole of its obligations under this Agreement due to the force majeure event, the breaching party shall be exempted from the responsibility related to the failure to fulfill its obligations under the Agreement due to the force majeure event.
Consequence of Force Majeure Events. 不可抗力事件的后果 (a) If the following conditions are met, then the Hindered Party shall be fully or partially released from its liability for its failure to perform its obligations hereunder; (i) the Force Majeure Event is the direct cause of the stoppage, impediment or delay encountered by the Hindered Party in performing its obligations under this Contract; (ii) at the time of the occurrence of the Force Majeure Event, the Hindered Party immediately informed the other Party; (iii) the Hindered Party has adopted measures to prevent the worsening of the damages and to remedy the situation; and (iv) the Hindered Party provides written information on such event within fifteen (15) days of its occurrence, including a statement of the reasons for the delay in performing or partially performing this Contract. 在满足下列条件的情况下,受阻方不履行本合同项下义务的责任应被全部或部分免除:(i)受阻方在履行其在本合同项下的义务时所遇到的停工、障碍或迟延是不可抗力事件直接造成的;(ii)不可抗力事件发生时,受阻方立即通知另一方,(iii)受阻方已尽其最大努力采取行动以防止损失的扩大并进行补救,(iv)受阻方于发生不可抗力事件后十五(15)天内提供该有关事件的书面资料,包括述明延迟履行或部分履行本合同的理由的说明书。 (b) If a Force Majeure Event occurs, the Parties shall decide whether this Contract should be amended in light of the impact of the event upon the performance hereof, and whether the Hindered Party should be partially or fully excused from its obligations hereunder. 如果发生不可抗力事件,双方应根据事件对履行本合同的影响,决定是否修改本合同,以及是否部分或全部解除受阻方在本合同项下的义务。 (c) Subject to the fulfillment of the conditions set forth in Article 21.2(a) above and to the extent affected by Force Majeure Event, neither Party shall be liable for any damage, increased costs or loss which the other Party may sustain by reason of a failure or delay of performance due to such Force Majeure Event, and such failure or delay shall not be deemed a breach of this Contract. 若上述第(a)21.2(a)条项下的条件全部满足,则在受不可抗力事件影响范围内,双方均无需就源于不可抗力事件的不履行和延迟履行所导致的损害、成本或损失的增加而承担责任,该等不履行和延迟履行不应视为对本合同的违约。 CHAPTER 11 LIABILITIES FOR BREACH OF CONTRACT 第11章 违约责任
Consequence of Force Majeure Events. No Party shall be released from any of its obligations under this Agreement as a result of a Force Majeure Event. This Agreement shall remain in effect for the duration of a Force Majeure Event.

Related to Consequence of Force Majeure Events

  • Effect of Force Majeure Event If either party to this contract cannot meet an obligation under this contract because of an event outside the control of that party (‘a force majeure event’): (a) the obligation, other than an obligation to pay money, is suspended to the extent it is affected by the force majeure event for as long as the force majeure event continues; and (b) the affected party must use its best endeavours to give the other party prompt notice of that fact including full particulars of the event, an estimate of its likely duration, the extent to which the affected party’s obligations are affected and the steps being taken to remove, overcome or minimise those effects.

  • Notification of Force Majeure Event 11.5.1 The Affected Party shall give notice to the other Party of any event of Force Majeure as soon as reasonably practicable, but not later than seven (7) days after the date on which such Party knew or should reasonably have known of the commencement of the event of Force Majeure. If an event of Force Majeure results in a breakdown of communications rendering it unreasonable to give notice within the applicable time limit specified herein, then the Party claiming Force Majeure shall give such notice as soon as reasonably practicable after reinstatement of communications, but not later than one (1) day after such reinstatement. Provided that, such notice shall be a pre-condition to the Affected Party’s entitlement to claim relief under this Agreement. Such notice shall include full particulars of the event of Force Majeure, its effects on the Party claiming relief and the remedial measures proposed. The Affected Party shall give the other Party regular reports on the progress of those remedial measures and such other information as the other Party may reasonably request about the Force Majeure. 11.5.2 The Affected Party shall give notice to the other Party of (i) the cessation of the relevant event of Force Majeure; and (ii) the cessation of the effects of such event of Force Majeure on the performance of its rights or obligations/ roles under this Agreement, as soon as practicable after becoming aware of each of these cessations.

  • Consequences of Force Majeure Subject to clauses 24.4, 24.5 and 24.6, if by reason of a Force Majeure Event a Party (Affected Party) is affected in the performance of any obligation or clause under this Agreement: (a) that Party will be excused during the time, and to the extent that, such performance is so affected; and (b) that Party will not, to that extent, be liable to the other Party for any Damage of any kind arising out of, or in any way connected with, that non-performance.

  • Notice of Force Majeure Event 14.2.1. As soon as practicable and in any case within 3 days of the date of occurrence of a Force Majeure Event or the date of knowledge thereof, the Party which is rendered wholly or partially unable to perform any of its obligations under this Agreement because of a Force Majeure Event (the “Affected Party”) shall notify the other party of the same, setting out, inter alia, the following in reasonable detail: a) The nature and extent of the Force Majeure Event ; b) The estimated period for which the Force Majeure Event is expected to last; c) The nature of and the extent to which, performance of any of its obligations under this Agreement is affected by the Force Majeure Event; d) The measures which the Affected Party has taken or proposes to take to alleviate/mitigate the impact of the Force Majeure Event and to resume performance of such of its obligations affected thereby; and e) Any other relevant information concerning the Force Majeure Event, and /or the rights and obligations of the Parties under this Agreement.

  • Event of Force Majeure The Recipient will not be in default by reason only of any failure in the performance of the Project in accordance with Schedule 1 – Statement of Work if such failure arises without the fault or negligence of the Recipient and is caused by any event of Force Majeure.

  • Events of Force Majeure Neither Party shall be held liable or responsible to the other Party nor be deemed to be in default under, or in breach of any provision of, this Agreement for failure or delay in fulfilling or performing any obligation of this Agreement when such failure or delay is due to force majeure, and without the fault or negligence of the Party so failing or delaying. For purposes of this Agreement, force majeure is defined as causes beyond the control of the Party, including, without limitation, acts of God; acts, regulations, or laws of any government; war; civil commotion; destruction of production facilities or materials by fire, flood, earthquake, explosion or storm; labor disturbances; epidemic; and failure of public utilities or common carriers. In such event Medistem or Licensee, as the case may be, shall immediately notify the other Party of such inability and of the period for which such inability is expected to continue. The Party giving such notice shall thereupon be excused from such of its obligations under this Agreement as it is thereby disabled from performing for so long as it is so disabled and the 30 days thereafter. To the extent possible, each Party shall use reasonable efforts to minimize the duration of any force majeure.

  • Effect of Force Majeure If either Party is rendered wholly or partially unable to perform its obligations under this Agreement because of a Force Majeure Act, that Party shall be excused from whatever performance is affected by the Force Majeure Act to the extent so affected, provided that: a) Within five (5) Business Days after the occurrence of the inability to perform due to a Force Majeure Act, the Affected Party provides a written notice to the other Party of the particulars of the occurrence, including an estimation of its expected duration and probable impact on the performance of its obligations hereunder, and continues to furnish periodic reports with respect thereto, every seven (7) days, during the period of Force Majeure, b) The Affected Party shall use all reasonable efforts to continue to perform its obligations hereunder and to correct or cure as soon as possible the Force Majeure Act, c) The suspension of performance shall be of no greater scope and no longer duration than is reasonably necessitated by the Force Majeure Act, d) The Affected Party shall provide the other Party with prompt notice of the cessation of the Force Majeure Act giving rise to the excuse from performance and shall thereupon resume normal performance of obligations under this Agreement with utmost promptitude, e) The non-performance of any obligation of either Party that was required to be performed prior to the occurrence of a Force Majeure Act shall not be excused as a result of such subsequent Force Majeure Act, f) The occurrence of a Force Majeure Act shall not relieve either Party from its obligations to make any payment hereunder for performance rendered prior to the occurrence of Force Majeure Act or for partial performance hereunder during period of subsistence Force Majeure Act; and g) The Force Majeure Act, shall not relieve either Party from its obligation to comply with Applicable Laws. The Affected Party shall exercise all reasonable efforts to mitigate or limit damages to the other Party.

  • Force Majeure Events a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following: i) acts of God; ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities; iii) acts of war (whether declared or undeclared), invasion or civil unrest; iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG or of any Law or any of their respective obligations under this Agreement); v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals; vi) earthquakes, explosions, accidents, landslides; fire; vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality; viii) chemical or radioactive contamination or ionizing radiation; or ix) damage to or breakdown of transmission facilities of GETCO/ DISCOMs; x) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.

  • Duration of Force Majeure An Interconnection Party shall not be responsible, or considered to be in Breach or Default under this Interconnection Service Agreement, for any non-performance, any interruption or failure of service, deficiency in the quality or quantity of service, or any other failure to perform any obligation hereunder to the extent that such failure or deficiency is due to Force Majeure. An Interconnection Party shall be excused from whatever performance is affected only for the duration of the Force Majeure and while the Interconnection Party exercises Reasonable Efforts to alleviate such situation. As soon as the non-performing Interconnection Party is able to resume performance of its obligations excused because of the occurrence of Force Majeure, such Interconnection Party shall resume performance and give prompt notice thereof to the other parties.

  • Definition of Force Majeure For the purposes of this section, an event of force majeure shall mean any cause beyond the control of the affected Interconnection Party or Construction Party, including but not restricted to, acts of God, flood, drought, earthquake, storm, fire, lightning, epidemic, war, riot, civil disturbance or disobedience, labor dispute, labor or material shortage, sabotage, acts of public enemy, explosions, orders, regulations or restrictions imposed by governmental, military, or lawfully established civilian authorities, which, in any of the foregoing cases, by exercise of due diligence such party could not reasonably have been expected to avoid, and which, by the exercise of due diligence, it has been unable to overcome. Force majeure does not include (i) a failure of performance that is due to an affected party’s own negligence or intentional wrongdoing; (ii) any removable or remediable causes (other than settlement of a strike or labor dispute) which an affected party fails to remove or remedy within a reasonable time; or (iii) economic hardship of an affected party.