Construction Progress Schedule. 7.3.1 The A/E shall review the Construction Progress Schedule for conformance with the Contract Documents, provide a copy of the Construction Progress Schedule and schedule of submittals to the Contracting Authority and Owner. 7.3.1.1 If the Project is administered using the State’s web-based project management software, the A/E shall receive initial and updated schedules from the Contractor, and forward them to the Contracting Authority and Owner, through the “Schedule Approvals” business process. 7.3.2 The A/E shall periodically inform the Contracting Authority and Owner of the need to update the Project Schedule as required to show current conditions, including conformance to the Construction Progress Schedule, as updated from time to time. 7.3.2.1 If such conditions indicate that Milestone completion dates shown on the Project Schedule may not be met, the A/E shall recommend corrective action to the Contracting Authority and Owner and carry out the directions of the Contracting Authority so that the Milestone completion dates may be met, unless the Contracting Authority and Owner agree in writing to revise the Milestone completion dates.
Appears in 5 contracts
Samples: Professional Services, Architect/Engineer Agreement, Architect/Engineer Agreement
Construction Progress Schedule. 7.3.1 The A/E shall review the Construction Progress Schedule for conformance with the Contract Documents, provide a copy of the Construction Progress Schedule and schedule of submittals to the Contracting Authority and Owner.
7.3.1.1 If the Project is administered using the State’s web-based project management software, the A/E shall receive initial and updated schedules from the Contractor, and forward them to the Contracting Authority and Owner, Owner through the “Schedule Approvals” business process.
7.3.2 The A/E shall periodically inform the Contracting Authority and Owner of the need to update the Project Schedule as required to show current conditions, including conformance to the Construction Progress Schedule, as updated from time to time.
7.3.2.1 If such conditions indicate that Milestone completion dates shown on the Project Schedule may not be met, the A/E shall recommend corrective action to the Contracting Authority and Owner and carry out the directions of the Contracting Authority so that the Milestone completion dates may be met, unless the Contracting Authority and Owner agree in writing to revise the Milestone completion dates.
Appears in 3 contracts
Samples: Professional Services, Architect/Engineer Agreement, Architect/Engineer Agreement
Construction Progress Schedule. 7.3.1 8.3.1 The A/E shall review the Construction Progress Schedule for conformance with the Contract Documents, and provide a copy of the Construction Progress Schedule and schedule of submittals to the Contracting Authority and Owner.
7.3.1.1 8.3.1.1 If the Project is administered using the State’s web-based project management software, the A/E shall receive initial and updated schedules from the Contractor, and forward them to the Contracting Authority and Owner, through the “Schedule Approvals” business process.
7.3.2 8.3.2 The A/E shall periodically inform the Contracting Authority and Owner of the need to update the Project Schedule as required to show current conditions, including conformance to the Construction Progress Schedule, as updated from time to time.
7.3.2.1 8.3.2.1 If such conditions indicate that Milestone completion dates shown on the Project Schedule may not be met, the A/E shall recommend corrective action to the Contracting Authority and Owner and carry out the directions of the Contracting Authority so that the Milestone completion dates may be met, unless the Contracting Authority and Owner agree in writing to revise the Milestone completion dates.
Appears in 3 contracts
Samples: Architect/Engineer Agreement, Architect/Engineer Agreement, Professional Services
Construction Progress Schedule. 7.3.1 The A/E shall review the Construction Progress Schedule for conformance with the Contract Documents, provide a copy of the Construction Progress Schedule and schedule of submittals to the Contracting Authority and the Owner.
7.3.1.1 If the Project is administered using the OAKS CIthe State’s web-based project management software, the A/E shall receive initial and updated schedules from the Contractor, and forward them to the Contracting Authority and the Owner, through the “Schedule Approvals” business process.
7.3.2 The A/E shall periodically inform the Contracting Authority and the Owner of the need to update the Project Schedule as required to show current conditions, including including, but not limited to, conformance to the Construction Progress Schedule, as updated from time to time.
7.3.2.1 If such conditions indicate that Milestone completion dates shown on the Project Schedule may not be met, the A/E shall recommend corrective action to the Contracting Authority and the Owner and carry out the directions of the Contracting Authority so that the Milestone completion dates may be met, unless the Contracting Authority and the Owner agree in writing to revise the Milestone completion dates.
Appears in 1 contract
Samples: Professional Services
Construction Progress Schedule. 7.3.1 The A/E shall review the Construction Progress Schedule for conformance with the Contract Documents, provide a copy of the Construction Progress Schedule and schedule of submittals to the Contracting Authority and the Owner.
7.3.1.1 If the Project is administered using the State’s web-based project management softwareOAKS CI, the A/E shall receive initial and updated schedules from the Contractor, and forward them to the Contracting Authority and the Owner, through the “Schedule Approvals” business process.
7.3.2 The A/E shall periodically inform the Contracting Authority and the Owner of the need to update the Project Schedule as required to show current conditions, including including, but not limited to, conformance to the Construction Progress Schedule, as updated from time to time.
7.3.2.1 If such conditions indicate that Milestone completion dates shown on the Project Schedule may not be met, the A/E shall recommend corrective action to the Contracting Authority and the Owner and carry out the directions of the Contracting Authority so that the Milestone completion dates may be met, unless the Contracting Authority and the Owner agree in writing to revise the Milestone completion dates.
Appears in 1 contract
Construction Progress Schedule. 7.3.1 The A/E shall review the Construction Progress Schedule for conformance with the Contract Documents, provide a copy of the Construction Progress Schedule and schedule of submittals to the Contracting Authority and Owner, and assist the CM to incorporate the approved Construction Progress Schedule and schedule of submittals into the Project Schedule.
7.3.1.1 If the Project is administered using the State’s web-based project management software, the A/E shall receive the initial and updated schedules all updates of the Construction Progress Schedule from the Contractor, and forward them to the Contracting Authority and Owner, CM through the “Schedule Approvals” business process.
7.3.2 The A/E shall periodically inform the Contracting Authority and Owner of the need to update the Project Schedule as required to show current conditions, including conformance to the Construction Progress Schedule, as updated from time to time.
7.3.2.1 If such conditions indicate that Milestone completion dates shown on the Project Schedule may not be met, the A/E shall recommend corrective action to the CM, Contracting Authority Authority, and Owner and carry out the directions of the Contracting Authority so that the Milestone completion dates may be met, unless the Contracting Authority and Owner agree in writing to revise the Milestone completion dates.
Appears in 1 contract
Samples: Professional Services
Construction Progress Schedule. 7.3.1 8.3.1 The A/E shall review the Construction Progress Schedule for conformance with the Contract Documents, provide a copy of the Construction Progress Schedule and schedule of submittals to the Contracting Authority and Owner.
7.3.1.1 8.3.1.1 If the Project is administered using the State’s web-based project management software, the A/E shall receive initial and updated schedules from the Contractor, and forward them to the Contracting Authority and Owner, through the “Schedule Approvals” business process.
7.3.2 8.3.2 The A/E shall periodically inform the Contracting Authority and Owner of the need to update the Project Schedule as required to show current conditions, including conformance to the Construction Progress Schedule, as updated from time to time.
7.3.2.1 8.3.2.1 If such conditions indicate that Milestone completion dates shown on the Project Schedule may not be met, the A/E shall recommend corrective action to the Contracting Authority and Owner and carry out the directions of the Contracting Authority so that the Milestone completion dates may be met, unless the Contracting Authority and Owner agree in writing to revise the Milestone completion dates.
Appears in 1 contract
Samples: Professional Services