Continuing Events Sample Clauses

Continuing Events. If the direction or fact, matter or thing upon which the Claim under clause 13.1(b) or clause 13.2 is based or the consequences of the direction or fact, matter or thing are continuing, the Consultant must continue to give the information required by clause 13.3(b) every 28 days after the written claim under clause 13.1(b) or 13.3(b) (as the case may be) was submitted or given to the Commonwealth's Representative, until after the direction or fact, matter or thing upon which the Claim is based has, or the consequences thereof have, ceased. Time Bar If the Consultant fails to comply with clause 13.1, 13.2, 13.3 or 13.4: the Commonwealth will not be liable (insofar as it is possible to exclude such liability) upon any Claim by the Consultant; and the Consultant will be absolutely barred from making any Claim against the Commonwealth, arising out of, or in any way in connection with, the relevant direction or fact, matter or thing (as the case may be) to which clause 13.1 or 13.2 applies.
AutoNDA by SimpleDocs
Continuing Events. If the direction or fact, matter or thing upon which the Claim under clause 16.1(b) or 16.2 is based or the consequences of the direction or fact, matter or thing are continuing, the Contractor must continue to give the information required by clause 16.3(b) every 28 days after the written claim under clause 16.1(b) or 16.3(b) (as the case may be) was submitted or given to the Contract Administrator, until after the direction or fact, matter or thing upon which the Claim is based has, or the consequences thereof have, ceased. Time Bar If the Contractor fails to comply with clause 16.1, 16.2, 16.3 or 16.4: the Commonwealth will not be liable (insofar as it is possible to exclude such liability) upon any Claim by the Contractor; and the Contractor will be absolutely barred from making any Claim against the Commonwealth, arising out of or in connection with the relevant direction or fact, matter or thing (as the case may be) to which clause 16.1 or 16.2 applies.
Continuing Events. If the events upon which the claim is based or the consequences of the events are continuing, the Contractor must continue to give the information required under clause 12.1(b) every 28 days after the claim under clause 12.1(b) was given until after the events or the consequences have ceased. Bar If the Contractor fails to comply with clauses 12.1 and 12.2, the: Contract Price will not be adjusted as a result of; and Principal will not be liable upon any claim by the Contractor, whether under the Contract or otherwise in law or in equity arising out of or in connection with, the relevant fact, matter or thing. COMPLETION
Continuing Events. If the direction or fact, matter or thing upon which the Claim under clause 16.1(b) or 16.2 is based or the consequences of the direction or fact, matter or thing are continuing, the Subcontractor must continue to give the information required by clause 16.3(b) every 28 days after the written claim under clause 16.1(b) or 16.3(b) (as the case may be) was submitted or given to the Contractor’s Representative, until after the direction or fact, matter or thing upon which the Claim is based has, or the consequences thereof have, ceased. Time Bar If the Subcontractor fails to comply with clause 16.1, 16.2, 16.3 or 16.4: the Contractor will not be liable (insofar as it is possible to exclude such liability) upon any Claim by the Subcontractor; and the Subcontractor will be absolutely barred from making any Claim against the Contractor, arising out of or in connection with the relevant direction or fact, matter or thing (as the case may be) to which clause 16.1 or 16.2 applies.
Continuing Events. If the direction or fact, matter or thing upon which the Claim under clause 14.1(b) or clause 14.2 is based or the consequences of the direction or fact, matter or thing are continuing, the Consultant must continue to give the information required by clause 14.3(b) every 28 days after the written claim under clause 14.1(b) or 14.3(b) (as the case may be) was submitted or given to the Contract Administrator, until after the direction or fact, matter or thing upon which the Claim is based has, or the consequences thereof have, ceased. Time Bar If the Consultant fails to comply with clause 14.1, 14.2, 14.3 or 14.4, the: Commonwealth will not be liable (insofar as it is possible to exclude such liability) upon any Claim by the Consultant; and Consultant will be absolutely barred from making any Claim against the Commonwealth, arising out of or in connection with the relevant direction or fact, matter or thing (as the case may be) to which clause 14.1 or 14.2 applies.
Continuing Events. If the events upon which the claim is based or the consequences of the events are continuing, the Subcontractor must continue to give the information required under clause 12.1(e) every 28 days after the claim under clause 12.1(e) was given until after the events or the consequences have ceased. Bar If the Subcontractor fails to comply with clause 12.1 or 12.2: the Subcontract Price will not be adjusted as a result of; and the Subcontractor will not be entitled to make (nor will the Contractor be liable upon) any claim (whether under the Subcontract or otherwise at law or in equity) arising out of or in connection with, the relevant fact, matter or thing. COMPLETION
Continuing Events. ‌ If the events upon which the Claim in accordance with Clause 52.2(b) is based or the consequences of the events are continuing, Project Co must continue to give information required by Clause 52.2(b) every 20 Business Days after the Claim in accordance with Clause 52.2(b) was submitted, until 21 Business Days after the events or consequences have ceased.
AutoNDA by SimpleDocs
Continuing Events. If the direction, event, circumstance, act, omission, fact, matter or thing upon which a Claim is based, or their consequences are continuing, the Developer must continue to give the information required by clause 56.2.2 every 28 days after the written Claim under clause
Continuing Events. If the matter in respect of which the Claim under clause 31.1 is based or the consequences of the matter are continuing, the Supplier must continue to give the information required by clause 31.2(b) every 20 Business Days after the written notice under clause 31.2(b) was submitted or given to the Principal and the Principal’s Representative, until after the matter in respect of which the Claim is based has, or the consequences of it have, ceased.
Continuing Events. If the direction or fact, matter or thing upon which the Claim under Clause 46.1 is based or the consequences of the direction or fact, matter or thing are continuing, the Contractor must continue to give the information required by Clause 46.2(b) every 20 Business Days after the written Claim under Clause 46.2(b) was submitted or given to the Superintendent, until after the direction or fact, matter or thing upon which the Claim is based has, or the consequences thereof, have ceased.
Time is Money Join Law Insider Premium to draft better contracts faster.