Contract Documents and Submittals for the Work Sample Clauses

Contract Documents and Submittals for the Work. General Contractor shall keep one complete set of all Contract Documents, including Drawings, Specifications and one complete set of submittals at the Site in good order, available to the Board, Architect, and Construction Manager. General Contractor shall keep the Drawings, Specifications and submittals up to date by replacing obsolete sheets with revised sheets as they are issued. General Contractor shall carefully study and compare the Contract Documents with each other and with information furnished by the Board and shall at once report to the Architect any errors, inconsistencies or omissions discovered or which should have been discovered. If General Contractor performs any construction activity which General Contractor knew or should have known involves a recognized error, inconsistency or omission in the Contract Documents without notice to Architect, General Contractor assumes responsibility for the performance and shall bear the costs for correction. General Contractor shall take field measurements and verify field conditions and shall carefully compare the field measurements and conditions and other information known (or which should have been known) to General Contractor with the Contract Documents before commencing activities. General Contractor shall immediately report to Architect errors, inconsistencies or omissions discovered or which should have been discovered.
AutoNDA by SimpleDocs

Related to Contract Documents and Submittals for the Work

  • REVIEW OF CONTRACT DOCUMENTS 4.2.1 The Contractor shall carefully study and compare the Contract Documents and shall immediately report in writing to the Architect and the State any error, inconsistency or omission he may discover. The Contractor shall not be liable to the State or the Architect for any damage resulting from any such errors, inconsistencies or omissions in the Contract Documents. The Contractor shall perform no portion of the Work at any time without Contract Documents or, where required, approved Shop Drawings, Product Data or Samples for such portion of the Work.

  • Construction Contract Documents The Construction Contract Documents shall consist of the plans and specifications prepared by the Engineer, and any addenda and change orders thereto, and the Owner-Contractor Agreement, all of which shall be compatible and consistent with this Agreement.

  • Contract Documents The contract documents shall consist of the following:

  • Contractor’s Submittals The Contract shall submit with reasonable promptness consistent with the Work Project Schedule and in orderly sequence all Shop Drawings, Samples, or other information required by the Contract Documents, or subsequently required by Change Order. Prior to submitting, the Contractor shall review each submittal for compliance with the Contract Documents and certify its approval by an approval stamp affixed to each copy. Submittal data presented without the Contractor’s certification will be returned without review or comment, and any delay resulting from such certification is the Contractor's responsibility.

  • THE CONTRACT DOCUMENTS The Contract Documents consist of the State-Contractor Agreement, the Conditions of the Contract (General, Supplementary and other Conditions), the Drawings, the Specifications, and all Addenda issued prior to bid opening and any Change Orders after execution of the Contract.

  • CONTRACTOR’S SUBMISSION OF CONTRACT MODIFICATIONS In connection with any Contract modification, OGS reserves the right to:  request additional information  reject Contract modifications  remove Products from Contract modification requests  request additional discounts for new or existing Products

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • OGS Contract Documents This Centralized Contract is composed of the following documents:  The Contract (that portion preceding the signatures)  Appendix A - Standard Clauses for New York State Contracts (January 2014)  Appendix B - General Specifications January 2015 22772 Project Based Information Technology Consulting (Statewide)  Appendix C - Contract Modification Procedure  Appendix D – Pricing Schedule  Appendix E – Report of Contract Purchases  Appendix F – Project Based Information Technology Consulting Services Processes and Forms o Attachment 1- Mini-Bid Template o Attachment 2- How to Use This Contract o Attachment 3- Enhancement Request Template o Attachment 4- No Cost Change Request Template o Attachment 5- Mini-Bid Participation Interest Template  Appendix G – Contractor and OGS Information

  • Construction Progress Schedule; Overall Project Schedule The Contractor shall submit for review by the Design Professional and approval by the Owner a Construction Progress Schedule based upon the Design Professional’s Preliminary Design and Construction Schedule and prepared using a CPM (Critical Path Method) process within sixty days after the Effective Date of the Contract, utilizing a full-featured software package in a form satisfactory to the Design Professional and Owner, showing the dates for commencement and completion of the Work required by the Contract Documents, including coordination of mechanical, plumbing, and electrical disciplines, as well as coordination of the various subdivisions of the Work within the Contract. Milestones must be clearly indicated and sequentially organized to identify the critical path of the Project. The Construction Schedule will be developed to represent the CSI specification divisions. It shall have the minimum number of activities required to adequately represent to the Owner the complete scope of Work and define the Project’s (and each Phase’s if phased) critical path and associated activities. The format of the Construction Progress Schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, inspections for Material Completion and Occupancy Date, and Final Completion Date. The Contractor shall submit, along with the Construction Progress Schedule, the Submittal Schedule for approval by the Design Professional, correlating the associated approval dates for the documents with the Construction Progress Schedule. Upon recommendation by the Design Professional and approval by the Owner, the Construction Progress Schedule shall become the Overall Project Schedule, which shall be utilized by the Design Professional, Owner and Contractor. The Contractor must provide the Design Professional and the Owner with monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations, including approved change orders. See also Article 3.3.5.

  • Construction Documents Phase 2.2.1.5. Bidding or Negotiation Phase: 2.2.1.6. Construction Administration Phase

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!