Contractor's Claims. 8.1.1 If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Project Manager, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance.
Appears in 56 contracts
Samples: Framework Agreement, Contract Agreement, Contract Agreement
Contractor's Claims. 8.1.1 1.1.1 If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Project Manager, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance.
Appears in 4 contracts
Contractor's Claims. 8.1.1 If 8.1.1If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Project Manager, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance.
Appears in 3 contracts
Samples: www.tenderskenya.co.ke, www.kisumu.go.ke, www.landcommission.go.ke
Contractor's Claims. 8.1.1 91.1 If the Contractor considers himself to be entitled to any extension of the Completion Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Project ManagerProcuring Entity, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 twenty-eight (28) days after the Contractor became aware, or should have become aware, of the event or circumstance.
Appears in 2 contracts
Samples: Service Agreement, Term Service Agreement
Contractor's Claims. 8.1.1 7.1.1 If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Project Manager, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance.
Appears in 2 contracts
Samples: Proposed Framework Agreement, Proposed Framework Agreement
Contractor's Claims. 8.1.1 24.1.1 If the Contractor considers himself itself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice Notice to the Project Manager, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 30 days after the Contractor became aware, or should have become aware, of the event or circumstance.
Appears in 1 contract
Samples: Tana Water Works Development Agency